ReraGenieLog inGet a buyer report

Home / Browse projects / Uttara Kannada, Karnataka / GULABI HERITAGE

Registration approved No litigation declared Residential/Group Housing project

GULABI HERITAGE

By Ashoka Realty (Prop.Ashok Gulabi Kumtekar)

RG-KA-88728 · RERA PRM/KA/RERA/1274/356/PR/010325/007533 · Last updated on RERA Karnataka portal: 17 Jan 2025

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Dec 2025Possession promisedno revision filed
0Complaints at RERA Karnatakaon this registration
Jump to the 109 documents Report an error

GULABI HERITAGE is a Residential/Group Housing project by Ashoka Realty (Prop.Ashok Gulabi Kumtekar) in Uttara Kannada, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1274/356/PR/010325/007533 on 1 Mar 2025. Possession is promised by 25 Dec 2025.

At a glance

Project

  • NameGULABI HERITAGE
  • TypeResidential/Group Housing
  • Location
    • Kumta
    • Uttara Kannada
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1274/356/PR/010325/007533
  • ReraGenie IDRG-KA-88728

Builder

  • NameAshoka Realty (Prop.Ashok Gulabi Kumtekar)
  • Entity typeProprietorship
  • GSTIN29HYUPK1880F1ZP
  • Authorized SignatoryAshoka Gulabi Kumtekar

Key dates

this monthRegisteredMar 2025PromisedDec 2025

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on1 Mar 2025
  • Promised completion25 Dec 2025
  • Revised completionNone
  • Buildings1 building record
  • Documents filed109 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Ashoka Realty---12012

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 17 Jan 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Upto Plinth Level-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
Retaining wall (All types)-
RCC or MS Framed structure-
Masonry Construction-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Painting-
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)Not applicable
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation workNot applicable
Internal and External work including landscapes as per sanctioned drawings-

Progress on shared amenities40

As on 17 Jan 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Sewage and Drainage SystemYes-
Water conservation/rain water harvesting/recharge of ground waterYes-
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes-
Solid waste management and disposalNoNot applicable
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsNoNot applicable
Electricity supply transformer and substationYes-
Storm water drainsYes-
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes-
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupYes-
Piped GasNoNot applicable
Water and SanitationYes-
Air ConditioningNoNot applicable
StaircasesYes-
LiftsYes-
Corridor/LobbiesYes-
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahNoNot applicable
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership2

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Named landowners2
LandownerVillageDistrict
Ashoka Gulabi Kumtekar--
Ashoka Gulabi Kumtekar--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 4.24 cr
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 4.00 cr-
On-site expenditure-Consultants FeesRs 24.00 lakh-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSANTHOSH B SHETTY
EngineerPrakruthi N
Chartered AccountantLakshmi G K

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed109

As listed on the registration, under the names the promoter filed them with; the newest 80 of 109 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1274/356/PR/010325/007533 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Loan should be deposited to RERA designated account as per notification date 19.07.2023File: Covering letter 16012025.pdf17 Jan 2025
there are service charges received please clarifyFile: Covering letter 16012025.pdf17 Jan 2025
What are all the sources of funds to complete the project? With supporting documentsFile: Covering letter 16012025.pdf17 Jan 2025
Promoter need to upload conversion order issued by the deputy commissioner for the project propertieFile: Final Converion order.pdf17 Jan 2025
copy of HESCOM letter for temporary connection instead of NOC. please upload the valid HESCOM NOCFile: HESCOM Connection letter.pdf17 Jan 2025
SOF wit supporting documentFile: 3 SOF wit supporting document.pdf17 Oct 2024
FORM-H Conversion orderFile: 4 FORM-H Conversion order.pdf17 Oct 2024
ADLR SURVEY SCKETCHFile: SURVEY SCKETCH.pdf17 Oct 2024
Single plot layoutFile: 6 Single plot layout.pdf17 Oct 2024
Renewed Plan With description ORIGINAL COPYFile: Renewed Plan With description.pdf17 Oct 2024
Village Map Sy No markedFile: Village Map Sy No marked.pdf17 Oct 2024
STP Drwaing CERTIFIED BY ENGINEERFile: 12 STP Drwaing.pdf17 Oct 2024
Hescom NOCFile: 13 Hescom NOC.pdf17 Oct 2024
Water NOCFile: 13 Water NOC.pdf17 Oct 2024
SOF wit supporting documentFile: 3 SOF wit supporting document.pdf18 Sep 2024
Single plot layoutFile: 7 Single plot layout.pdf18 Sep 2024
Architect LicenseFile: 8 Architect License.pdf18 Sep 2024
AmenitiesFile: 9 Amenities.pdf18 Sep 2024
Common area detailsFile: 9 Common area details.pdf18 Sep 2024
Structural Stability certificateFile: 10 Structural Stability certificate.pdf18 Sep 2024
Renewed Plan With descriptionFile: Renewed Plan With description.pdf18 Sep 2024
Release deed 1File: 4 Release deed 1.pdf18 Sep 2024
Release Deed 2File: 4 Release Deed 2.pdf18 Sep 2024
Release deed 3File: 4 Release deed 3.pdf18 Sep 2024
ITR 2022-23File: ITR 2022-23.pdf13 Aug 2024
Balance Sheet with Shedule 2021 - 2022File: Balance Sheet with Shedule 2021 - 2022.pdf13 Aug 2024
PL 2021 - 2022File: PL 2021 - 2022.pdf13 Aug 2024
ITR 2023-24File: ITR 2023-24.pdf13 Aug 2024
Balance Sheet with Shedule 2022 - 2023File: Balance Sheet with Shedule 2022 - 2023.pdf13 Aug 2024
PL 2022 - 2023File: PL 2022 - 2023.pdf13 Aug 2024
Balance Sheet with Shedule 2023 - 2024File: Balance Sheet with Shedule 2023 - 2024.pdf13 Aug 2024
PL 2023- 2024File: PL 2023- 2024.pdf13 Aug 2024
SOF wit supporting documentFile: 2 SOF wit supporting document.pdf13 Aug 2024
loan sanction letterFile: 3 loan sanction letter.jpeg13 Aug 2024
Mortagage deedFile: 3 Mortagage deed.pdf13 Aug 2024
Declar on loan amount to Rera AccFile: 4 Declar on loan amount to Rera Acc.jpeg13 Aug 2024
Guidance Value CertificateFile: 12 Guidance Value Certificate.pdf13 Aug 2024
Building Licence renewed till 16-9-25File: 13 Building Licence renewed till 16-9-25.pdf13 Aug 2024
Renewed Plan With descriptiFile: 15 Renewed Plan With descripti.pdf13 Aug 2024
Form-5, ArchitectFile: 16 Form-5, Architect.pdf13 Aug 2024
Architect LicenseFile: 16 Architect License.pdf13 Aug 2024
RTC, survey 465-A (134)-
Mutation, survey 465-A (134)-
Encumbrance Certificate, survey 465-A (134)-
Sale/Title/Gift Deed, survey 465-A (134)-
Khatha, survey 465-A (134)-
RTC, survey 465-A (135)-
Mutation, survey 465-A (135)-
Encumbrance Certificate, survey 465-A (135)-
Sale/Title/Gift Deed, survey 465-A (135)-
Khatha, survey 465-A (135)-
Registration CertificateFile: udyam registration.pdf-
GST CertificateFile: GST.pdf-
Certificate issued by CA Form 1File: Form-1 CA Certificate.pdf-
Certificate issued by Architect Form 2File: Form-5, Architect.pdf-
Certificate issued by Engineer Form 3File: Form 6 Engineer Certificate.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: No litigation affidavit.pdf-
Certificate from Chartered AccountFile: Form-1 CA Certificate.pdf-
Balance Sheet 2022 - 2023File: Balance Sheet with Shedule 2023 - 2024.pdf-
Balance Sheet 2021 - 2022File: Balance Sheet with Shedule 2022 - 2023.pdf-
Balance Sheet 2020 - 2021File: Balance Sheet with Shedule 2021 - 2022.pdf-
Audited Profit and Loss Statement 2022 - 2023File: PL 2023- 2024.pdf-
Audited Profit and Loss Statement 2021 - 2022File: PL 2022 - 2023.pdf-
Audited Profit and Loss Statement 2020 - 2021File: PL 2021 - 2022.pdf-
Income Tax Return Acknowledgement 2022 - 2023File: ITR 2023-24.pdf-
Income Tax Return Acknowledgement 2021 - 2022File: ITR 2022-23.pdf-
Income Tax Return Acknowledgement 2020 - 2021File: ITR 2021-22.pdf-
Building Licence renewed till 16-9-25-
Hescom NOC-
Water Permission letter-
Renewed Plan With description-
Plan with Specification-
Renewed Plan With description-
Project Specification-
Renewed Plan With description-
Renewed Plan With description-
Legal Opinion-

How this compares with Uttara Kannada

22%of Uttara Kannada projects moved their completion datethis one has not
0%of Uttara Kannada registrations are shown as withdrawn or revokedthis one is not

Computed across the 100+ Uttara Kannada projects on ReraGenie, from their own filings.

Keep GULABI HERITAGE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Uttara Kannada100+ in Uttara Kannada

Builder: Ashoka Realty (Prop.Ashok Gulabi Kumtekar)

Ashoka Realty (Prop.Ashok Gulabi Kumtekar) has 1 registration on RERA Karnataka, including GULABI HERITAGE. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Uttara Kannada district page.

Frequently asked questions

What are my rights if GULABI HERITAGE is delayed beyond 25 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of GULABI HERITAGE?

The registered promoter entity is Ashoka Realty (Prop.Ashok Gulabi Kumtekar), a proprietorship as per the filing. Its GSTIN 29HYUPK1880F1ZP can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in GULABI HERITAGE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at GULABI HERITAGE?

The professionals named in the filing: Architect: SANTHOSH B SHETTY; Engineer: Prakruthi N; Chartered Accountant: Lakshmi G K. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in GULABI HERITAGE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About GULABI HERITAGE. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save GULABI HERITAGE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.