Nisarga Vastu City
By MUNAF MOHAMMED SAB LANDAKANALLI
RG-KA-66686 · RERA PRM/KA/RERA/1274/352/PR/150526/008659 · Last updated on RERA Karnataka portal: 15 May 2026
Source: official RERA Karnataka filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
Saved.
Nisarga Vastu City is a Residential/Group Housing project by MUNAF MOHAMMED SAB LANDAKANALLI in Uttara Kannada, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1274/352/PR/150526/008659 on 15 May 2026. Possession is promised by 30 Mar 2029.
At a glance
Project
- NameNisarga Vastu City
- TypeResidential/Group Housing
- Location
- Sirsi
- Uttara Kannada
- 581402
- Pincode581402
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1274/352/PR/150526/008659
- ReraGenie IDRG-KA-66686
Builder
- NameMUNAF MOHAMMED SAB LANDAKANALLI
- Entity typeProprietorship
- GSTIN29BZLPS4417A1Z9
- Authorized SignatoryMUNAF MOHAMMED SAB LANDAKANALLI
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on15 May 2026
- Promised completion30 Mar 2029
- Revised completionNone
- Buildings1 building record
- Documents filed62 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| 1 | - | - | - | 182 | 0 | 182 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 15 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
Building:
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | - |
| Foundation footing work | - |
| Upto Plinth Level | - |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | - |
| Retaining wall (All types) | Not applicable |
| RCC or MS Framed structure | - |
| Masonry Construction | - |
| Plastering inside , outside & Ceiling | - |
| Joinery: Doors, Windows, Ventilators etc | - |
| Basic work of Water supply, Sanitary and Electrification | - |
| Dadoing, Skirting, Flooring, Tiles work (All types) | - |
| Railing and Grill fixing | - |
| Electrification, Water supply and Sanitary Finishing | - |
| Painting | - |
| Fire prevention and fire fighting fitting and fixture with network | - |
| Weather Proof work(tile,concrete) | - |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Elevation work | - |
| Internal and External work including landscapes as per sanctioned drawings | - |
Progress on shared amenities40
As on 15 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | - |
| Sewage and Drainage System | Yes | - |
| Water conservation/rain water harvesting/recharge of ground water | Yes | - |
| Energy management | Yes | - |
| Fire protection and fire safety requirements | Yes | - |
| Solid waste management and disposal | Yes | - |
| Emergency Evacuation services | Yes | - |
| Internal Roads & Footpaths | Yes | - |
| Electricity supply transformer and substation | Yes | - |
| Storm water drains | Yes | - |
| Use of renewable energy | Yes | - |
| Sewage Treatment Plant (STP) | Yes | - |
| Parks & Tree planting | Yes | - |
| Street Lighting | Yes | - |
| Electricity | Yes | - |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | - |
| Club House | No | Not applicable |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | No | Not applicable |
| Swimming Pool | No | Not applicable |
| Gym | No | Not applicable |
| Parks | Yes | - |
| Power Backup | No | Not applicable |
| Piped Gas | No | Not applicable |
| Water and Sanitation | Yes | - |
| Air Conditioning | No | Not applicable |
| Staircases | Yes | - |
| Lifts | Yes | - |
| Corridor/Lobbies | Yes | - |
| Fire escapes | No | Not applicable |
| Common entrance and exit for the building/common portico/foyer/verandah | Yes | - |
| Basement | Yes | - |
| Terrace | Yes | - |
| Outer Wall | Yes | - |
| Open parking areas | Yes | - |
| Provision for lodging of management staff and security staff | Yes | - |
| Water conservation and renewable energy | Yes | - |
| Common storage spaces | No | Not applicable |
Land and ownership1
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| MUNAF MOHAMMED SAB LANDAKANALLI | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 128.89 cr | - |
| Principal sum and interest payable to financial institutions-Scheduled Banks | Rs 20.00 cr | - |
| On-site expenditure-Cost Of Services(Water, Electricity, Sewage) | Rs 9.00 cr | - |
| On-site expenditure-Site Overhead | Rs 2.58 cr | - |
| On-site expenditure-Salaries of workers | Rs 2.16 cr | - |
| On-site expenditure-Consultants Fees | Rs 1.93 cr | - |
Certifying professionals and partners3
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Nishant Nathani |
| Engineer | SHANAWAZ M KATHEWADI |
| Chartered Accountant | SANKET SHRIDHAR HEGDE |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed62
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1274/352/PR/150526/008659 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form-1 CA CertificateFile: 2 Form-1 CA Certificate.pdf | 15 May 2026 |
| Bank AffidavitFile: 3 Bank Affidavit.pdf | 15 May 2026 |
| RERA Bank Account LetterFile: 1 RERA Bank Account Letter.pdf | 15 May 2026 |
| RERA Bank AccountsFile: 1 RERA Bank Accounts.pdf | 12 May 2026 |
| Form-1 CA CertificateFile: 2 Form-1 CA Certificate.pdf | 12 May 2026 |
| Bank AffidavitFile: 3 Bank Affidavit.pdf | 12 May 2026 |
| Sales ClarificationFile: 4 Sales Clarification.pdf | 12 May 2026 |
| FY 24-25 - MunafFile: 5 FY 24-25 - Munaf.pdf | 12 May 2026 |
| FY 23-24 - MunafFile: 5 FY 23-24 - Munaf.pdf | 12 May 2026 |
| FY 22-23 - MunafFile: 5 FY 22-23 - Munaf.pdf | 12 May 2026 |
| Legal OpinionFile: 1 Legal Opinion.pdf | 12 May 2026 |
| DP PlanFile: 1 DP Plan.pdf | 12 May 2026 |
| DP Plan OrderFile: 2 DP Plan Order.pdf | 12 May 2026 |
| Building Commencement and LicenseFile: 3 Building Approval Letter.pdf | 12 May 2026 |
| Survey Sketch - NAFile: 4 Survey Sketch - NA.pdf | 12 May 2026 |
| Building SANCTION DRWGFile: 6 Building SANCTION DRWG.pdf | 12 May 2026 |
| Common Areas And AmenitiesFile: 8 Common Areas And Amenities.pdf | 12 May 2026 |
| CDP DemarcationFile: 9 CDP Demarcation.pdf | 12 May 2026 |
| Village Map DemarcationFile: 10 Village Map Demarcation.pdf | 12 May 2026 |
| Structural Stability Certificate with LicenseFile: 11 Structural Stability Certificate with License.pdf | 12 May 2026 |
| Project specificationFile: 12 Project specification.pdf | 12 May 2026 |
| Proforma Allotment LetterFile: 14 Proforma Allotment Letter.pdf | 12 May 2026 |
| Brief project estimationFile: 17 Brief project estimation.pdf | 12 May 2026 |
| Land cost calculation sheetFile: 19 Land cost calculation sheet.pdf | 12 May 2026 |
| STP Drawing - Nisarga Vastu CityFile: 18 STP Drawing - Nisarga Vastu City.pdf | 12 May 2026 |
| 100KLD STP- Sirsi- SignedFile: 22 100KLD STP- Sirsi- Signed.pdf | 12 May 2026 |
| SEIAA NOC Declaration AffidavitFile: 23 SEIAA NOC Declaration Affidavit.pdf | 12 May 2026 |
| KSPCB NOC Declaration AffidavitFile: 24 KSPCB NOC Declaration Affidavit.pdf | 12 May 2026 |
| Fire NOC Declaration AffidavitFile: 25 Fire NOC Declaration Affidavit.pdf | 12 May 2026 |
| Affidavit Form BFile: 26 Affidavit Form B.pdf | 12 May 2026 |
| Notarized Affidavit for 3(1) VoilationFile: 27 Notarized Affidavit for 3(1) Voilation.pdf | 12 May 2026 |
| clarification on KSPCB unit numbersFile: 28 clarification on KSPCB unit numbers.pdf | 12 May 2026 |
| Clarification On Building License And Commencement CertificateFile: 29 Clarification On Building License And Commencement Certificate.pdf | 12 May 2026 |
| Proforma Agreement of SaleFile: 13 Proforma Agreement of Sale.pdf | 12 May 2026 |
| Registration CertificateFile: Udyam Registration Certificate.pdf | - |
| GST CertificateFile: GST registration.pdf | - |
| Certificate issued by CA Form 1File: 2 Form-1 CA Certificate.pdf | - |
| Certificate issued by Architect Form 2File: Architect Form 2.pdf | - |
| Certificate issued by Engineer Form 3File: Engineer Form 3.pdf | - |
| Project Chartered Accountant | - |
| Project Engineer | - |
| Project Architect | - |
| AffidavitFile: Affidavit for Non-Litigation Details.pdf | - |
| Balance Sheet 2024 - 2025File: Munaf Sir BS.pdf | - |
| Balance Sheet 2023 - 2024File: munaf BSheet 2023-24.pdf | - |
| Audited Profit and Loss Statement 2024 - 2025File: Munaf Sir P&L.pdf | - |
| Audited Profit and Loss Statement 2023 - 2024File: Munaf Mahammed Sab_31-Dec-2024_794519070.pdf | - |
| Audited Profit and Loss Statement 2022 - 2023File: Munaf AY 2022-23.pdf | - |
| Income Tax Return Acknowledgement 2024 - 2025File: Munaf Mahammed Sab_26-Sep-2025_842803430 (1).pdf | - |
| Income Tax Return Acknowledgement 2023 - 2024File: Munaf ITR3 2023 24.pdf | - |
| Income Tax Return Acknowledgement 2022 - 2023File: ITR 2022-23.pdf | - |
| SANCTION DRWG COMBINED_compressed | - |
| Section | - |
| structural safety of the building | - |
| Project Specifications | - |
| Brochure | - |
| 41_1A relinquishment deed | - |
| Form B Affidavit | - |
| Affidavit RERA | - |
| NOC of Hescom | - |
| Water board NOC | - |
| KSPCB NOC | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Uttara Kannada
Computed across the 100+ Uttara Kannada projects on ReraGenie, from their own filings.
Keep Nisarga Vastu City on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Uttara Kannada100+ in Uttara Kannada
Filed coordinates, straight-line distance. 4 registered projects within 2 km.
ANANTHA RESIDENCY
Ananthamurthy M Hegde
GOPAL BADAVANE
RAMADAS GOPALRAO DIVEKAR
NISARGA COLONY PHASE-II
DEVCONS DEVELOPERS PRIVATE LIMITED
Nisarga Colony Phase-I
DEVCONS DEVELOPERS PRIVATE LIMITED
Signature Apartment
VASANT CONSTRUCTIONS PRIVATE LIMITED
AL MARJAAN RESIDENCY
BRIGHT DEVELOPERS
See every Uttara Kannada project, with the district possession charts
Builder: MUNAF MOHAMMED SAB LANDAKANALLI
MUNAF MOHAMMED SAB LANDAKANALLI has 1 registration on RERA Karnataka, including Nisarga Vastu City. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Uttara Kannada district page.
Frequently asked questions
What are my rights if Nisarga Vastu City is delayed beyond 30 Mar 2029?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of Nisarga Vastu City?
The registered promoter entity is MUNAF MOHAMMED SAB LANDAKANALLI, a proprietorship as per the filing. Its GSTIN 29BZLPS4417A1Z9 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in Nisarga Vastu City?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at Nisarga Vastu City?
The professionals named in the filing: Architect: Nishant Nathani; Engineer: SHANAWAZ M KATHEWADI; Chartered Accountant: SANKET SHRIDHAR HEGDE. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Nisarga Vastu City?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.