ReraGenieLog inGet a buyer report

Home / Browse projects / Bengaluru Urban, Karnataka / GRANDUS 118

Registration approved No litigation declared Residential/Group Housing project

GRANDUS 118

By GRANDUS PROJECTS PRIVATE LIMITED

RG-KA-64884 · RERA PRM/KA/RERA/1251/309/PR/250526/008680 · Last updated on RERA Karnataka portal: 13 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Nov 2028Possession promisedno revision filed
1 of 17Construction stages donefurthest along: Foundation footing work, 90%
4 of 7Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 69 documents Report an error

GRANDUS 118 is a Residential/Group Housing project by GRANDUS PROJECTS PRIVATE LIMITED in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/309/PR/250526/008680 on 25 May 2026. Possession is promised by 30 Nov 2028. 3 of the 7 units on this registration are recorded sold or booked, and 1 of 17 construction stages are filed complete.

At a glance

Project

  • NameGRANDUS 118
  • TypeResidential/Group Housing
  • Location
    • Bengaluru North
    • Bengaluru Urban
    • 560038
  • Pincode560038
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/309/PR/250526/008680
  • ReraGenie IDRG-KA-64884

Builder

  • NameGRANDUS PROJECTS PRIVATE LIMITED
  • Entity typeCompany
  • CINU45205KA2012PTC062850
  • GSTIN29AAFCG4739A1ZP
  • Authorized SignatorySrinath Munireddy
  • CmdSrinath Munireddy
  • DirectorsSrinath Munireddy, Sandhya Srinath Reddy
  • Project HeadSupriya H N

Key dates

this monthRegisteredMay 2026PromisedNov 2028

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on25 May 2026
  • Promised completion30 Nov 2028
  • Revised completionNone
  • Buildings1 building record
  • Documents filed69 files

Current status

43%3 of 7 units booked
71.5%Of the estimated cost spent so far

Figures as on 13 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tower---707

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 13 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

1 of 17 construction stages are filed complete. The stage furthest along is Foundation footing work, at 90%.

Building: 17% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work90%
Upto Plinth Level90%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)0%
Retaining wall (All types)Not applicable
RCC or MS Framed structure6%
Masonry Construction0%
Plastering inside , outside & Ceiling0%
Joinery: Doors, Windows, Ventilators etc0%
Basic work of Water supply, Sanitary and Electrification0%
Dadoing, Skirting, Flooring, Tiles work (All types)0%
Railing and Grill fixing0%
Electrification, Water supply and Sanitary Finishing0%
Painting0%
Fire prevention and fire fighting fitting and fixture with network0%
Weather Proof work(tile,concrete)0%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work0%
Internal and External work including landscapes as per sanctioned drawings0%

Progress on shared amenities34

As on 13 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes0%
Sewage and Drainage SystemYes0%
Water conservation/rain water harvesting/recharge of ground waterNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalNoNot applicable
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsNoNot applicable
Electricity supply transformer and substationYes0%
Storm water drainsYes0%
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)NoNot applicable
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes0%
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
StaircasesYes0%
LiftsYes0%
Corridor/LobbiesYes0%
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahNoNot applicable
BasementNoNot applicable
TerraceYes0%
Outer WallNoNot applicable
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership2

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area556 sq m
Named landowners2
LandownerVillageDistrict
Bidanda Monapa Chengappa--
Bopaya Bidanda--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 4.73 cr
Cost incurredRs 3.38 cr
Spent of the estimate71.55%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 4.73 crRs 2.85 cr
On-site expenditure-Consultants Fees-Rs 14.10 lakh
On-site expenditure-Site Overhead-Rs 38.86 lakh

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAMIT RASTOGI
EngineerPrashanth Kumar L
Chartered AccountantMahaveer Bhansali Jain

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed69

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/309/PR/250526/008680 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4- Grandus 118.pdf13 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Form 5_Grandus 118_Oct 2026.pdf13 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form 6 Eng Cert - Sep 26 - Grandus 118.pdf13 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4 -118 Q1 -2026-27 Grandus 118.pdf8 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form 5_Grandus 118_July 2026.pdf8 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form-6 Eng Cert - June 26 - Grandus 118.pdf8 Jul 2026
Stability Certificate with licenseFile: 1 Stability Certificate with license.pdf23 May 2026
Sale Agreement DraftFile: 2 Sale Agreement Draft.pdf23 May 2026
Registration CertificateFile: Grandus Projects _COI.PDF-
Memorandum of AssociationFile: Grandus Projects _MOA.PDF-
Article of AssociationFile: Grandus Projects _AOA.PDF-
GST CertificateFile: GST Certificate Updated Projects.pdf-
Certificate issued by CA Form 1File: Form -1 Rera New Format - Grandus Project sd.pdf-
Certificate issued by Architect Form 2File: Form 2_Architect Certificate_Signed.pdf-
Certificate issued by Engineer Form 3File: Form 3 Eng cert - Grandus 118.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: Affidavit for Non-Litigation Details- With JDA.pdf-
Balance Sheet 2024 - 2025File: Grandus Project Pvt Ltd - FY 2024-25.pdf-
Balance Sheet 2023 - 2024File: Grandus Project Pvt Ltd - FY 2023-24.pdf-
Balance Sheet 2022 - 2023File: Grandus Project Pvt Ltd - FY 2022-23.pdf-
Audited Profit and Loss Statement 2024 - 2025File: Grandus Project Pvt Ltd - FY 2024-25.pdf-
Audited Profit and Loss Statement 2023 - 2024File: Grandus Project Pvt Ltd - FY 2023-24.pdf-
Audited Profit and Loss Statement 2022 - 2023File: Grandus Project Pvt Ltd - FY 2022-23.pdf-
Income Tax Return Acknowledgement 2024 - 2025File: ITR FY 2024-25.pdf-
Income Tax Return Acknowledgement 2023 - 2024File: ITR FY 2023-24.pdf-
Income Tax Return Acknowledgement 2022 - 2023File: ITR FY 2022-23.pdf-
Director's Report 2024 - 2025File: Grandus Project Pvt Ltd - FY 2024-25.pdf-
Director's Report 2023 - 2024File: Grandus Project Pvt Ltd - FY 2023-24.pdf-
Director's Report 2022 - 2023File: Grandus Project Pvt Ltd - FY 2022-23.pdf-
Cash Flow Statement 2024 - 2025File: Grandus Project Pvt Ltd - FY 2024-25.pdf-
Cash Flow Statement 2023 - 2024File: Grandus Project Pvt Ltd - FY 2023-24.pdf-
Auditor's Report 2024 - 2025File: Grandus Project Pvt Ltd - FY 2024-25.pdf-
Auditor's Report 2023 - 2024File: Grandus Project Pvt Ltd - FY 2023-24.pdf-
Auditor's Report 2022 - 2023File: Grandus Project Pvt Ltd - FY 2022-23.pdf-
Building Plan Approval Letter 118-
Plan Sanction 118 GBA_BCCC_0317_25-26-
Plan Sanction 118 GBA_BCCC_0317_25-26-
Grandus 118 Project Specification-
VR_Sale Agreement Draft-
Proforma Allotment Letter-
Affidavit FORM B-
Notarized Affidavit for 3(1) Voilation-
Joint Affidavit from Promoter and Landowner-
Site No 118 Legal Opinion-
BESCOM NOC Clarification-
Water NOC Clarification-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Land cost Calculation-
Deed of Sale Site No 118-
Endorsement-
GPA Site No 118-
Property Tax 25-26 Site No 118-
Cost Estimation Summary - Grandus 118-
Clarification about sold and Unsold Details-
Clarification on STP-
Existing Site plan and possession letter-
Clarification on Village Map and CDP-

How this compares with Bengaluru Urban

43%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep GRANDUS 118 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmGRANDUS 118Other 4Dot size: filed unitsN

Filed coordinates, straight-line distance. 4 registered projects within 2 km.

Builder: GRANDUS PROJECTS PRIVATE LIMITED

GRANDUS PROJECTS PRIVATE LIMITED has 1 registration on RERA Karnataka, including GRANDUS 118. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if GRANDUS 118 is delayed beyond 30 Nov 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of GRANDUS 118?

The registered promoter entity is GRANDUS PROJECTS PRIVATE LIMITED, a company as per the filing. Its CIN U45205KA2012PTC062850 and GSTIN 29AAFCG4739A1ZP can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in GRANDUS 118?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at GRANDUS 118?

The professionals named in the filing: Architect: AMIT RASTOGI; Engineer: Prashanth Kumar L; Chartered Accountant: Mahaveer Bhansali Jain. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in GRANDUS 118?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About GRANDUS 118. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save GRANDUS 118 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.