Godrej Woodland Phase 2
RG-KA-89838 · RERA PRM/KA/RERA/1250/304/PR/020922/005201 · Last updated on RERA Karnataka portal: 15 Oct 2026
Source: official RERA Karnataka filing
Red flags
- 1 complaint at RERA Karnataka
- Completion date moved by 12 months
- 1 extension taken
Clear
- No litigation declared
- Separate project account declared
Saved.
Godrej Woodland Phase 2 is a Plotted Development project by Godrej Properties Limited in Bengaluru Rural, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1250/304/PR/020922/005201 on 2 Sep 2022. Possession is promised by 31 Dec 2026. The completion date has moved by 12 months from the original filing. 1 complaint is on record with the regulator.
At a glance
Project
- NameGodrej Woodland Phase 2
- TypePlotted Development
- Location
- Hosakote
- Bengaluru Rural
- 560067
- Pincode560067
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1250/304/PR/020922/005201
- ReraGenie IDRG-KA-89838
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on2 Sep 2022
- Promised completion31 Dec 2026
- Revised completionRevised to 31 Dec 2026 (originally 31 Dec 2025)
- BuildingsNot stated in filing
- Documents filed92 files
Current status
Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Land and ownership1
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Godrej Properties Limited | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 14.69 cr | Rs 13.44 cr |
| Payment of fees | Rs 8.54 cr | - |
| Principal sum and interest payable to financial institutions-Scheduled Banks | Rs 4.20 cr | - |
| Payment of charges | Rs 2.89 cr | - |
| On-site expenditure-Site Overhead | Rs 2.57 cr | - |
| On-site expenditure-Consultants Fees | Rs 1.74 cr | Rs 11.76 cr |
| Payment of Premiums | Rs 5.73 lakh | - |
| Principal sum and interest payable to financial institutions-Non Banking financial institution (NBFC) | - | Rs 3.96 cr |
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Engineer | Abhishek Arora |
| Chartered Accountant | Bhavesh Shah |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterothers
Complaints filed with RERA Karnataka1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| 00621/2023 | - | Godrej Properties Limited | 02/05/2023 |
Documents filed92
As listed on the registration, under the names the promoter filed them with; the newest 80 of 92 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1250/304/PR/020922/005201 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Phase 2.pdf | 15 Oct 2026 |
| Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form-6 Engg Ph 2 - 30-Sep-26.pdf | 15 Oct 2026 |
| Q2 2026-27 Water supply and sewage board | 15 Oct 2026 |
| Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres) | 15 Oct 2026 |
| Q2 2026-27 KPTCL- BESCOM | 15 Oct 2026 |
| Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form-4 Woodland P2 Q1 26-27.PDF | 15 Jul 2026 |
| Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form-6 & 5 Woodland P2 Q1 26-27.pdf | 15 Jul 2026 |
| Q1 2026-27 Water supply and sewage board | 15 Jul 2026 |
| Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres) | 15 Jul 2026 |
| Q1 2026-27 KPTCL- BESCOM | 15 Jul 2026 |
| Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 GODREJ WOODLAND PH2-FINAL.pdf | 13 Apr 2026 |
| Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form-6 Engg Ph 2 - 31-Mar-26.pdf | 13 Apr 2026 |
| Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 Woodland phase 2.pdf | 13 Jan 2026 |
| Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form-6 Engg Ph 2 - 31-Dec-25.pdf | 13 Jan 2026 |
| Arc certificate - work completed P 2File: Arc certificate - work completed P 2.pdf | 17 Oct 2025 |
| Arc certificate - work pending P 2File: Arc certificate - work pending P 2.pdf | 17 Oct 2025 |
| Engg certificate - work completed Ph 2File: Engg certificate - work completed Ph 2.pdf | 17 Oct 2025 |
| Engg certificate - work pending -Ph2File: Engg certificate - work pending -Ph2.pdf | 17 Oct 2025 |
| RTCs of year 2021-2022File: All RTC .pdf | 17 Aug 2022 |
| MRsFile: MR.pdf | 17 Aug 2022 |
| conversion ordersFile: All_compressed.pdf | 17 Aug 2022 |
| Guidance valueFile: Woodlands valuation.pdf | 17 Aug 2022 |
| CA certificateFile: GODREJ WOODLAND PHASE 2.pdf | 17 Aug 2022 |
| Engineer CertificateFile: Form - 3 Engineer - Woodland Phase 2.pdf | 17 Aug 2022 |
| KSPCB NocFile: CFE.pdf | 17 Aug 2022 |
| Panchayat Water LetterFile: Panchayath - Water Commitment.pdf | 17 Aug 2022 |
| bank account statementFile: Bank Statement .png | 27 Jul 2022 |
| RTCFile: All RTC .pdf | 27 Jul 2022 |
| MutationFile: MR.pdf | 27 Jul 2022 |
| conversion orderFile: Conversion order.pdf | 27 Jul 2022 |
| sale deedFile: Sale deed.pdf | 27 Jul 2022 |
| title deed of godrej agrovet limitedFile: Title Deed .pdf | 27 Jul 2022 |
| advocate search reportFile: titlecertificate-24,26,31-2,31-3,53-1.pdf | 27 Jul 2022 |
| Non- litigation affidavitFile: Non - litigation affidavit .pdf | 27 Jul 2022 |
| Guidance ValueFile: Woodlands valuation.pdf | 27 Jul 2022 |
| Layout OrderFile: Approval Letter - Phase-2 - Woodland.pdf | 27 Jul 2022 |
| KSPCB CFEFile: CFE.pdf | 27 Jul 2022 |
| Layout PlanFile: Thiruvarangha_10A-26G approval LAO.pdf | 27 Jul 2022 |
| upload the Estimated cost of construction certified by the EngineerFile: Form - 3 Engineer - Woodland Phase 2.pdf | 27 Jul 2022 |
| Proforma of Agreement for saleFile: AFS Woodland Phase II 3103 (005).pdf | 27 Jul 2022 |
| Panchayat NOCFile: Panchayath - Water Commitment.pdf | 27 Jul 2022 |
| BESCOM NOCFile: BESCOM - NoC.pdf | 27 Jul 2022 |
| BrochureFile: Godrej Woodland_flipchart_Phase-2_Low.pdf | 27 Jul 2022 |
| RTC, survey SY NO. 24/2, 26/1, 26/2, 31/2, 31/3 & 53/1 THIRUVARANGA VILLAGE | - |
| Mutation, survey SY NO. 24/2, 26/1, 26/2, 31/2, 31/3 & 53/1 THIRUVARANGA VILLAGE | - |
| Encumbrance Certificate, survey SY NO. 24/2, 26/1, 26/2, 31/2, 31/3 & 53/1 THIRUVARANGA VILLAGE | - |
| Conversion/Alienation Order, survey SY NO. 24/2, 26/1, 26/2, 31/2, 31/3 & 53/1 THIRUVARANGA VILLAGE | - |
| Sale/Title/Gift Deed, survey SY NO. 24/2, 26/1, 26/2, 31/2, 31/3 & 53/1 THIRUVARANGA VILLAGE | - |
| Khatha, survey SY NO. 24/2, 26/1, 26/2, 31/2, 31/3 & 53/1 THIRUVARANGA VILLAGE | - |
| Registration CertificateFile: AA2901190053949_RC18012019.pdf | - |
| GST Certificate | - |
| Organization StructureFile: Organisation Structure.pdf | - |
| Certificate issued by CA Form 1File: GODREJ WOODLAND PHASE 2.pdf | - |
| Certificate issued by Engineer Form 3File: Form - 3 Engineer - Woodland Phase 2.pdf | - |
| Project Chartered Accountant | - |
| Project Engineer | - |
| AffidavitFile: Non litigation affidavit .pdf | - |
| Certificate issued by ArchitectFile: Form - 2 Architect - Phase 2_.pdf | - |
| Balance Sheet 2020 - 2021File: BS FY 2020-21.pdf | - |
| Balance Sheet 2019 - 2020File: BS FY 2019-20.pdf | - |
| Balance Sheet 2018 - 2019File: BS FY 2018-19.pdf | - |
| Audited Profit and Loss Statement 2020 - 2021File: P & L FY 2020-21.pdf | - |
| Audited Profit and Loss Statement 2019 - 2020File: P & L FY 2019-20.pdf | - |
| Audited Profit and Loss Statement 2018 - 2019File: P & L FY 2018-19 .pdf | - |
| Director's Report 2020 - 2021File: Directors Report 2020.pdf | - |
| Director's Report 2019 - 2020File: Director Report 2018-19.pdf | - |
| Director's Report 2018 - 2019File: Director Report 2018-19.pdf | - |
| Cash Flow Statement 2020 - 2021File: CF FY 2020-21.pdf | - |
| Cash Flow Statement 2019 - 2020File: CF FY 2019-20.pdf | - |
| Income Tax Return Acknowledgement 2020 - 2021File: GPL - ITR 6 Ack - FY 2019-20.pdf | - |
| Income Tax Return Acknowledgement 2019 - 2020File: GPL - ITR 6 Ack - FY 2019-20.pdf | - |
| Income Tax Return Acknowledgement 2018 - 2019File: GPL ITR Ack AY 2018-19.pdf | - |
| BESCOM - NoC | - |
| Thiruvarangha_10A-26G approval LAO | - |
| Thiruvarangha_10A-26G approval LAO | - |
| Thiruvarangha_10A-26G approval LAO | - |
| titlecertificate-24,26,31-2,31-3,53-1 | - |
| AFS Woodland Phase II 3103 | - |
| Allotment Letter Woodland phase 2 | - |
| Form B | - |
Promoter's earlier projects2
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Status | Promised | Delivered |
|---|---|---|---|---|
| Godrej Park Retreat | SY.NO.77,175/1,175/2A,175/2B,176/2A,176/2B & 177 KODATHI VILLAGE, VARTHUR HOBLI, BANGALORE EAST TALUK, Bangalore East, BANGALORE | Ongoing | Feb 2027 | Not due yet |
| Godrej Woodland | Sy.No. 19, 25, 31/1, 32, 33, 34, 35/1, 35/2, 37, 38/1, 38/2 , Thiruvaranga Village, Anugondanahalli Hobli, Hoskote Taluk | Ongoing | Dec 2025 | Not delivered |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Rural
Computed across the 650+ Bengaluru Rural projects on ReraGenie, from their own filings.
Keep Godrej Woodland Phase 2 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Rural650+ in Bengaluru Rural
Prestige Park Grove
PRESTIGE PROJECTS PRIVATE LIMITED
DS MAX SKY FIELDS
DS Max Properties Private Limited
Sowparnika Rhythm of Rain
SOWPARNIKA HOMES PRIVATE LIMITED
WORLD OF GARDENS
RLP TRENDSQUARES PROJECTS PRIVATE LIMITED
DS MAX SKYSAMPURN
DS MAX PROPERTIES PRIVATE LIMITED
Amrutha Lake Vista
Amrutha Shelters Private Limited
See every Bengaluru Rural project, with the district possession charts
Builder: Godrej Properties Limited
Godrej Properties Limited has 17 registrations on RERA Karnataka, including Godrej Woodland Phase 2 and GODREJ PARKSHIRE. Its filings declare 8 earlier projects, none of them declared completed. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Bengaluru Rural district page.
Frequently asked questions
What are my rights if Godrej Woodland Phase 2 is delayed beyond 31 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of Godrej Woodland Phase 2?
The registered promoter entity is Godrej Properties Limited, a company as per the filing. Its GSTIN 29AAACG3995M1ZX can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in Godrej Woodland Phase 2?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Godrej Woodland Phase 2?
Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
Who certifies construction progress at Godrej Woodland Phase 2?
The professionals named in the filing: Engineer: Abhishek Arora; Chartered Accountant: Bhavesh Shah. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Godrej Woodland Phase 2?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.