Valid until 1 Sep 2019 Residential/Group Housing project

EWS 41

By AHMEDABAD MUNICIPAL CORPORATION

RG-GJ-44690 · RERA PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/RAA04244/041218 · Last updated on GujRERA portal: 27 Feb 2021

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
  • Separate project account declared
Sep 2019Possession promisedno revision filed
40 of 40Construction stages doneacross 5 buildings; every applicable stage filed complete
15 of 448Units unsoldnot recorded sold or booked
Jump to the 41 documents Report an error

EWS 41 is a Residential/Group Housing project by AHMEDABAD MUNICIPAL CORPORATION in Ahmedabad, Gujarat, registered with GujRERA as PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/RAA04244/041218 on 4 Dec 2018. Possession is promised by 1 Sep 2019. 433 of the 448 units on this registration are recorded sold or booked, and 40 of 40 construction stages are filed complete.

At a glance

Project

  • NameEWS 41
  • TypeResidential/Group Housing
  • Location
    • TP 55(Ishanpur-South) FP 167
    • BR WAREHOUSE GODOWN
    • ISANPUR
    • Ghodasar Isanpur
    • Ahmedabad City
    • Ahmedabad
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/RAA04244/041218
  • ReraGenie IDRG-GJ-44690

Builder

  • NameAHMEDABAD MUNICIPAL CORPORATION
  • Entity typeCOMPETENT AUTHORITY/ GOVERNMENT
  • Other registrations55 more →

Key dates

this monthRegisteredDec 2018PromisedSep 2019

Key facts

Registration and timeline

  • StatusValid until 1 Sep 2019
  • Registered on4 Dec 2018
  • Promised completion1 Sep 2019
  • Revised completionNone
  • Buildings5 building records
  • Documents filed41 files

Current status

97%433 of 448 units booked
100.0%Of the estimated cost spent so far

Figures as on 27 Feb 2021, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
1---98098
2---98098
3---84084
4---84084
5---84084

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building5

As on 27 Feb 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

40 of 40 construction stages are filed complete across 5 buildings.

1100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
2100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
3100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
4100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
5100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 27 Feb 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterYes100%
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationNoNot applicable
Fire fightingYes100%
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area7,279 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 12.49 cr
Cost incurredRs 12.49 cr
Spent of the estimate100.0%
BuildingWingEstimatedIncurred
1NARs 2.50 crRs 2.50 cr
2NARs 2.50 crRs 2.50 cr
3NARs 2.50 crRs 2.50 cr
4NARs 2.50 crRs 2.50 cr
5NARs 2.50 crRs 2.50 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRAKESHKUMAR K PRAJAPATHI
EngineerKETAV P JOSHI

Documents filed41

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/RAA04244/041218 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)27 Feb 2021
Architect's certificate (Form 1)23 Feb 2021
Engineer's certificate (Form 2)23 Feb 2021
Engineer's certificate annexure23 Feb 2021
Site photograph, 123 Feb 2021
Site photograph, 223 Feb 2021
Site photograph, 323 Feb 2021
Site photograph, 423 Feb 2021
Site photograph, 523 Feb 2021
RERA registration certificate4 Dec 2018
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Ahmedabad

97%of this project is bookeddistrict median 53%
14%of Ahmedabad projects moved their completion datethis one has not

Computed across the 5,400+ Ahmedabad projects on ReraGenie, from their own filings.

Keep EWS 41 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Ghodasar Isanpur5,400+ in Ahmedabad

2 kmEWS 41Other 93Dot size: filed unitsN

Filed coordinates, straight-line distance. 93 registered projects within 2 km.

Builder: AHMEDABAD MUNICIPAL CORPORATION

AHMEDABAD MUNICIPAL CORPORATION has 56 registrations on GujRERA, including EWS-23 and EWS-24. Read the full track record. See more projects on the Ahmedabad district page.

Frequently asked questions

What are my rights if EWS 41 is delayed beyond 1 Sep 2019?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of EWS 41?

The registered promoter entity is AHMEDABAD MUNICIPAL CORPORATION, a competent authority/ government as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in EWS 41?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at EWS 41?

The professionals named in the filing: Architect: RAKESHKUMAR K PRAJAPATHI; Engineer: KETAV P JOSHI. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in EWS 41?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About EWS 41. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save EWS 41 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.