Home / Browse projects / Ahmedabad, Gujarat / EWS 76

Valid until 20 Jan 2027 Residential/Group Housing project

EWS 76

By AHMEDABAD MUNICIPAL CORPORATION

RG-GJ-64411 · RERA PR/GJ/AHMEDABAD/AHMEDABAD CITY/Ahmedabad Municipal Corporation/RAA14551/211224/200925 · Last updated on GujRERA portal: 21 Dec 2024

Source: official GujRERA filing

Red flags

  • Completion date moved by 16 months
  • 1 extension taken

Clear

  • Nothing verified clear yet
Jan 2027Possession promisedmoved 16 months from the original
88 of 99Construction stages doneacross 11 buildings; furthest along: External plumbing and external plaster, 90%
2,140 of 2,140Units unsoldnot recorded sold or booked
Jump to the 40 documents Report an error

EWS 76 is a Residential/Group Housing project by AHMEDABAD MUNICIPAL CORPORATION in Ahmedabad, Gujarat, registered with GujRERA as PR/GJ/AHMEDABAD/AHMEDABAD CITY/Ahmedabad Municipal Corporation/RAA14551/211224/200925 on 21 Dec 2024. Possession is promised by 20 Jan 2027. The completion date has moved by 16 months from the original filing. 0 of the 2,140 units on this registration are recorded sold or booked, and 88 of 99 construction stages are filed complete.

At a glance

Project

  • NameEWS 76
  • TypeResidential/Group Housing
  • Location
    • EWS F.P. NO. 123
    • 54
    • SARKHEJ
    • AHMEDABAD
    • SARKHEJ
    • Ahmedabad City
    • Ahmedabad
    • 382210
  • Pincode382210
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/AHMEDABAD/AHMEDABAD CITY/Ahmedabad Municipal Corporation/RAA14551/211224/200925
  • ReraGenie IDRG-GJ-64411

Builder

  • NameAHMEDABAD MUNICIPAL CORPORATION
  • Entity typeCOMPETENT AUTHORITY/ GOVERNMENT
  • Other registrations55 more →

Key dates

this monthRegisteredDec 2024First promiseSep 2025Revised toJan 2027

Key facts

Registration and timeline

  • StatusValid until 20 Jan 2027
  • Registered on21 Dec 2024
  • Promised completion20 Jan 2027
  • Revised completionRevised to 20 Jan 2027 (originally 20 Sep 2025)
  • Buildings11 building records
  • Documents filed40 files

Current status

0%0 of 2,140 units booked
58.6%Of the estimated cost spent so far

Figures as on 21 Dec 2024, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BLOCK B---1800180
BLOCK C---1900190
BLOCK D---2000200
BLOCK E---2000200
BLOCK F---1200120
BLOCK G---1600160
BLOCK H---1900190
BLOCK I---2000200
BLOCK J+K---2500250
BLOCK L+M---2900290
BLOCK A---1600160

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building11

As on 21 Dec 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

88 of 99 construction stages are filed complete across 11 buildings. The stage furthest along is External plumbing and external plaster, at 90%.

BLOCK B94%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing50%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
BLOCK C99%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing90%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
BLOCK D94%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing50%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
BLOCK E92%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing30%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
BLOCK F89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
BLOCK G94%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing50%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
BLOCK H94%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing50%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
BLOCK I94%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing50%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
BLOCK J+K94%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing50%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
BLOCK L+M94%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing50%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
BLOCK A99%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing90%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities23

As on 21 Dec 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes0%
Water supplyYes0%
Sewerage (chamber, lines, septic tank, STP)Yes0%
Storm water drainsYes0%
Landscaping and tree plantingYes0%
Street lightingYes0%
Community buildingsYes0%
Treatment and disposal of sewage and sullage waterYes0%
Solid waste management and disposalYes0%
Water conservation, rain water harvestingYes0%
Energy managementYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationNoNot applicable
Fire fightingYes0%
Drinking water facilitiesYes0%
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes0%
Letter boxNoNot applicable
Compound wallYes0%
Plinth protectionYes0%
Water tankYes0%
Other requirementsYes0%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area25,194 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 160.00 cr
Cost incurredRs 93.72 cr
Spent of the estimate58.58%
BuildingWingEstimatedIncurred
BLOCK L+MNARs 22.02 crRs 13.21 cr
BLOCK J+KNARs 19.08 crRs 11.45 cr
BLOCK DNARs 14.77 crRs 8.86 cr
BLOCK ENARs 14.77 crRs 7.39 cr
BLOCK INARs 14.77 crRs 8.86 cr
BLOCK CNARs 14.20 crRs 9.23 cr
BLOCK HNARs 14.20 crRs 8.52 cr
BLOCK BNARs 13.34 crRs 8.00 cr
BLOCK GNARs 11.92 crRs 7.15 cr
BLOCK ANARs 11.91 crRs 8.34 cr
BLOCK FNARs 9.00 crRs 2.70 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRAKESHKUMAR KANNAIYALAL PRAJAPATI
EngineerNITINKUMAR PATEL

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionApplied Mar 2026; no approval date filed

Documents filed40

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/AHMEDABAD/AHMEDABAD CITY/Ahmedabad Municipal Corporation/RAA14551/211224/200925 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
RERA registration certificate21 Dec 2024
Engineer's certificate (Form 2)4 Dec 2024
Engineer's certificate annexure4 Dec 2024
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Declaration in Form B-
Approved building or plotting plan-
NOCs from authorities-
Title clearance certificate-
Title report-
Property card-
Statutory document-
Project photograph-
Proforma sale deed-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Ahmedabad

0%of this project is bookeddistrict median 53%
14%of Ahmedabad projects moved their completion datethis one moved by 16 months

Computed across the 5,400+ Ahmedabad projects on ReraGenie, from their own filings.

Keep EWS 76 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near SARKHEJ5,400+ in Ahmedabad

2 kmEWS 76Other 122Dot size: filed unitsN

Filed coordinates, straight-line distance. 122 registered projects within 2 km.

Builder: AHMEDABAD MUNICIPAL CORPORATION

AHMEDABAD MUNICIPAL CORPORATION has 56 registrations on GujRERA, including EWS-23 and EWS-24. Read the full track record. See more projects on the Ahmedabad district page.

Frequently asked questions

What are my rights if EWS 76 is delayed beyond 20 Jan 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of EWS 76?

The registered promoter entity is AHMEDABAD MUNICIPAL CORPORATION, a competent authority/ government as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in EWS 76?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at EWS 76?

The professionals named in the filing: Architect: RAKESHKUMAR KANNAIYALAL PRAJAPATI; Engineer: NITINKUMAR PATEL. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in EWS 76?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About EWS 76. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save EWS 76 to a free account