Home / Browse projects / Ahmedabad, Gujarat / EWS 39

Valid until 30 Nov 2021 Residential/Group Housing project

EWS 39

By AHMEDABAD MUNICIPAL CORPORATION

RG-GJ-91769 · RERA PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/RAA04239/041218 · Last updated on GujRERA portal: 30 Jul 2024

Source: official GujRERA filing

Red flags

  • Completion date moved by 11 months
  • 1 extension taken

Clear

  • Nothing verified clear yet
Nov 2021Possession promisedmoved 11 months from the original
64 of 72Construction stages doneacross 8 buildings; furthest along: Plinth, 0%
118 of 588Units unsoldnot recorded sold or booked
Jump to the 44 documents Report an error

EWS 39 is a Residential/Group Housing project by AHMEDABAD MUNICIPAL CORPORATION in Ahmedabad, Gujarat, registered with GujRERA as PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/RAA04239/041218 on 4 Dec 2018. Possession is promised by 30 Nov 2021. The completion date has moved by 11 months from the original filing. 470 of the 588 units on this registration are recorded sold or booked, and 64 of 72 construction stages are filed complete.

At a glance

Project

  • NameEWS 39
  • TypeResidential/Group Housing
  • Location
    • TP 84/A (Makarba) FP 98/2
    • OPP NAJRANA RESIDENCY
    • MAKARBA POLICE HEADQUATTERS ROAD
    • MAKARBA
    • Makarba
    • Ahmedabad City
    • Ahmedabad
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/RAA04239/041218
  • ReraGenie IDRG-GJ-91769

Builder

  • NameAHMEDABAD MUNICIPAL CORPORATION
  • Entity typeCOMPETENT AUTHORITY/ GOVERNMENT
  • Other registrations55 more →

Key dates

this monthRegisteredDec 2018First promiseDec 2020Revised toNov 2021

Key facts

Registration and timeline

  • StatusValid until 30 Nov 2021
  • Registered on4 Dec 2018
  • Promised completion30 Nov 2021
  • Revised completionRevised to 30 Nov 2021 (originally 1 Dec 2020)
  • Buildings8 building records
  • Documents filed44 files

Current status

80%470 of 588 units booked
89.4%Of the estimated cost spent so far

Figures as on 30 Jul 2024, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
8---70070
1---70070
2---70070
3---70070
4---70070
5---70070
6---84084
7---84084

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building8

As on 30 Jul 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

64 of 72 construction stages are filed complete across 8 buildings. The stage furthest along is Plinth, at 0%.

889%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
189%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
289%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
389%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
489%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
589%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
689%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
789%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 30 Jul 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterYes100%
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationNoNot applicable
Fire fightingYes100%
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area9,099 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 19.37 cr
Cost incurredRs 17.32 cr
Spent of the estimate89.43%
BuildingWingEstimatedIncurred
1NARs 2.42 crRs 2.17 cr
2NARs 2.42 crRs 2.17 cr
3NARs 2.42 crRs 2.17 cr
4NARs 2.42 crRs 2.17 cr
5NARs 2.42 crRs 2.17 cr
6NARs 2.42 crRs 2.17 cr
7NARs 2.42 crRs 2.17 cr
8NARs 2.42 crRs 2.17 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDIVYESH B DESAI
EngineerJAYESH D DESAI

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionApplied Oct 2021; no approval date filed

Documents filed44

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/RAA04239/041218 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)30 Jul 2024
Engineer's certificate (Form 2)26 Jul 2024
Engineer's certificate annexure26 Jul 2024
Architect's certificate (Form 1)25 Jul 2024
Site photograph, 815 Jul 2024
Site photograph, 115 Jul 2024
Site photograph, 215 Jul 2024
Site photograph, 315 Jul 2024
Site photograph, 415 Jul 2024
Site photograph, 515 Jul 2024
Site photograph, 615 Jul 2024
Site photograph, 715 Jul 2024
RERA registration certificate4 Dec 2018
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Ahmedabad

80%of this project is bookeddistrict median 53%
14%of Ahmedabad projects moved their completion datethis one moved by 11 months

Computed across the 5,400+ Ahmedabad projects on ReraGenie, from their own filings.

Keep EWS 39 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Makarba5,400+ in Ahmedabad

2 kmEWS 39Other 140Dot size: filed unitsN

Filed coordinates, straight-line distance. 140 registered projects within 2 km.

Builder: AHMEDABAD MUNICIPAL CORPORATION

AHMEDABAD MUNICIPAL CORPORATION has 56 registrations on GujRERA, including EWS-23 and EWS-24. Read the full track record. See more projects on the Ahmedabad district page.

Frequently asked questions

What are my rights if EWS 39 is delayed beyond 30 Nov 2021?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of EWS 39?

The registered promoter entity is AHMEDABAD MUNICIPAL CORPORATION, a competent authority/ government as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in EWS 39?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at EWS 39?

The professionals named in the filing: Architect: DIVYESH B DESAI; Engineer: JAYESH D DESAI. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in EWS 39?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About EWS 39. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save EWS 39 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.