Red flags

  • Completion date moved by 10 months
  • 2 extensions taken

Clear

  • Nothing verified clear yet
Mar 2026Possession promisedmoved 10 months from the original
16 of 18Construction stages doneacross 2 buildings; furthest along: Stilt Floor, 0%
43 of 133Units unsoldnot recorded sold or booked
Jump to the 42 documents Report an error

EMPYREAN COURTYARD II is a Mixed Development project by ARIES REALTY in Vadodara, Gujarat, registered with GujRERA as PR/GJ/VADODARA/VADODARA/Others/MAA06604/EX1/EX2/200126/310326 on 9 Jan 2020. Possession is promised by 31 Mar 2026. The completion date has moved by 10 months from the original filing. 90 of the 133 units on this registration are recorded sold or booked, and 16 of 18 construction stages are filed complete.

At a glance

Project

  • NameEMPYREAN COURTYARD II
  • TypeMixed Development
  • Location
    • Block No. 308/1
    • Besides Vedant Sunshine Duplex
    • Nr. Shroff Foundation
    • Kalali
    • Kalali
    • Vadodara
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/VADODARA/VADODARA/Others/MAA06604/EX1/EX2/200126/310326
  • ReraGenie IDRG-GJ-11524

Builder

  • NameARIES REALTY
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredJan 2020First promiseMay 2025Revised toMar 2026

Key facts

Registration and timeline

  • StatusValid until 31 Mar 2026
  • Registered on9 Jan 2020
  • Promised completion31 Mar 2026
  • Revised completionRevised to 31 Mar 2026 (originally 15 May 2025)
  • Buildings2 building records
  • Documents filed42 files

Current status

68%90 of 133 units booked
100.0%Of the estimated cost spent so far

Figures as on 30 Dec 2025, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---281341
B+C+D---722092

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building2

As on 30 Dec 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

16 of 18 construction stages are filed complete across 2 buildings. The stage furthest along is Stilt Floor, at 0%.

A89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
B+C+D89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 30 Dec 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsYes100%
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalYes100%
Water conservation, rain water harvestingYes100%
Energy managementYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingYes100%
Drinking water facilitiesYes100%
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxYes100%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,703 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 19.15 cr
Cost incurredRs 19.15 cr
Spent of the estimate100.0%
BuildingWingEstimatedIncurred
B+C+DNARs 13.55 crRs 13.55 cr
ANARs 5.60 crRs 5.60 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRuchir Sheth
EngineerR V Patel Associates

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/VADODARA/VADODARA/Others/MAA06604/EX1/040825/311225Applied Jul 2025; approved Aug 2025
PR/GJ/VADODARA/VADODARA/Others/MAA06604/EX1/EX2/200126/310326Applied Dec 2025; approved Jan 2026

Documents filed42

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VADODARA/VADODARA/Others/MAA06604/EX1/EX2/200126/310326 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)30 Dec 2025
Engineer's certificate (Form 2)30 Dec 2025
Engineer's certificate annexure30 Dec 2025
Accountant's certificate (Form 3)30 Dec 2025
Site photograph, A30 Dec 2025
Site photograph, B+C+D30 Dec 2025
RERA registration certificate9 Jan 2020
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Vadodara

68%of this project is bookeddistrict median 70%
23%of Vadodara projects moved their completion datethis one moved by 10 months

Computed across the 2,900+ Vadodara projects on ReraGenie, from their own filings.

Keep EMPYREAN COURTYARD II on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Kalali2,900+ in Vadodara

2 kmEMPYREAN COURTYARD IIOther 236Dot size: filed unitsN

Filed coordinates, straight-line distance. 236 registered projects within 2 km.

Builder: ARIES REALTY

ARIES REALTY has 1 registration on GujRERA, including EMPYREAN COURTYARD II. Read the full track record. See more projects on the Vadodara district page.

Frequently asked questions

What are my rights if EMPYREAN COURTYARD II is delayed beyond 31 Mar 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of EMPYREAN COURTYARD II?

The registered promoter entity is ARIES REALTY, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in EMPYREAN COURTYARD II?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at EMPYREAN COURTYARD II?

The professionals named in the filing: Architect: Ruchir Sheth; Engineer: R V Patel Associates. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in EMPYREAN COURTYARD II?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About EMPYREAN COURTYARD II. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save EMPYREAN COURTYARD II to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.