Home / Browse projects / Bengaluru Urban, Karnataka / Ellegenza Phase II

Registration approved No litigation declared Residential/Group Housing project

Ellegenza Phase II

By Nambiar Builders Private Limited

RG-KA-92305 · RERA PRM/KA/RERA/1251/308/PR/161024/007147 · Last updated on RERA Karnataka portal: 12 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Sep 2029Possession promisedno revision filed
0 of 19Construction stages donefurthest along: Earth work and other leveling..., 98%
142 of 206Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 194 documents Report an error

Ellegenza Phase II is a Residential/Group Housing project by Nambiar Builders Private Limited in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/308/PR/161024/007147 on 16 Oct 2024. Possession is promised by 30 Sep 2029. 64 of the 206 units on this registration are recorded sold or booked, and 0 of 19 construction stages are filed complete.

At a glance

Project

  • NameEllegenza Phase II
  • TypeResidential/Group Housing
  • Location
    • Anekal
    • Bengaluru Urban
    • 560099
  • Pincode560099
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/308/PR/161024/007147
  • ReraGenie IDRG-KA-92305

Builder

  • NameNambiar Builders Private Limited
  • Entity typeCompany
  • CINU45201KA2009PTC050747
  • GSTIN29AADCN0664M1Z3
  • Authorized SignatoryRatheesh Nambiar
  • CeoRatheesh Nambiar
  • DirectorsRatheesh Nambiar, Rajesh P K, Ramesh Nambair
  • Project HeadShaji Mudappathi
  • Other registrations3 more →
  • Declared earlier projects12 →

Key dates

this monthRegisteredOct 2024PromisedSep 2029

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on16 Oct 2024
  • Promised completion30 Sep 2029
  • Revised completionNone
  • Buildings14 building records
  • Documents filed194 files

Current status

31%64 of 206 units booked
2.2%Of the estimated cost spent so far

Figures as on 12 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Block 1---606
Block 2---12012
Block 3---16016
Block 4---10010
Block 5---808
Block 6---10010
Block 7---808
Block 8---22022
Block 9---26026
Block 10---26026
Block 11---21021
Block 12---909
Block 13---15015
Block 14---17017

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 12 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 19 construction stages are filed complete. The stage furthest along is Earth work and other leveling preparation work, at 98%.

Building: 18% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work98%
Foundation footing work90%
Upto Plinth Level90%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)0%
Retaining wall (All types)25%
RCC or MS Framed structure25%
Masonry Construction9%
Plastering inside , outside & Ceiling3%
Joinery: Doors, Windows, Ventilators etc0%
Basic work of Water supply, Sanitary and Electrification0%
Dadoing, Skirting, Flooring, Tiles work (All types)0%
Railing and Grill fixing0%
Electrification, Water supply and Sanitary Finishing0%
Painting0%
Fire prevention and fire fighting fitting and fixture with network0%
Weather Proof work(tile,concrete)0%
Wardrobe, Showcase, Kitchen cabinet, Puja work0%
Elevation work0%
Internal and External work including landscapes as per sanctioned drawings0%

Progress on shared amenities40

As on 12 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes93%
Sewage and Drainage SystemYes93%
Water conservation/rain water harvesting/recharge of ground waterYes2%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalYes0%
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsYes98%
Electricity supply transformer and substationYes0%
Storm water drainsYes92%
Use of renewable energyYes0%
Sewage Treatment Plant (STP)Yes0%
Parks & Tree plantingYes3%
Street LightingYes0%
ElectricityYes55%
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityYes0%
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksYes0%
Power BackupYes0%
Piped GasNoNot applicable
Water and SanitationYes0%
Air ConditioningNoNot applicable
StaircasesYes0%
LiftsNoNot applicable
Corridor/LobbiesNoNot applicable
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahNoNot applicable
BasementNoNot applicable
TerraceNoNot applicable
Outer WallNoNot applicable
Open parking areasYes0%
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership14

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area65,736 sq m
Named landowners14
LandownerVillageDistrict
Jyothi N--
Shashank B N--
Ratheesh Nambiar--
Ganesh Nadiga D--
Nambiar Builders Private Limited--
M ShrinivasaRao--
Jyothi N--
Nambiar Builders Private Limited--
Padma P--
Ganesh Nadiga D--
Ratheesh Nambiar--
Sarojamma--
Narayana reddy R--
Vanajakshi G--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 402.40 cr
Cost incurredRs 8.99 cr
Spent of the estimate2.23%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 302.28 crRs 7.49 cr
Principal sum and interest payable to financial institutions-Scheduled BanksRs 52.00 crRs 1.25 cr
On-site expenditure-Site OverheadRs 35.65 crRs 22.62 lakh
On-site expenditure-Consultants FeesRs 12.47 crRs 1.65 lakh

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectGnanavel Thirumaran
EngineerChinnaswamy Ethiraj
Chartered AccountantK B Sandeep Kumar

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed194

As listed on the registration, under the names the promoter filed them with; the newest 80 of 194 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/308/PR/161024/007147 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Ellegenza P2 - Form - 4 - CA Certificate - Q2.pdf12 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Ellegenza P2 - Form 5 - Architect Certificate (Q2).pdf12 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Ellegenza P2 - Form 6 - Engineer Certificate (Q2).pdf12 Oct 2026
Q2 2026-27 Water supply and sewage board12 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)12 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Ellegenza P2 - Form 4 - CA Certificate - Q1.pdf14 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Ellegenza P2 - Form-5 Architect Certificate (Q1).pdf14 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Ellegenza P2 - Form-6 Engineer Certificate (Q1).pdf14 Jul 2026
Q1 2026-27 Water supply and sewage board14 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)14 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 along with NOC.pdf15 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5_Q4_FY 2025-26_ Ellegenza Ph II.pdf15 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6_Q4_FY 2025-26_ Ellegenza Ph II.pdf15 Apr 2026
Q4 2025-26 Water supply and sewage board15 Apr 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)15 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4_Q3_FY 2025-26_ Ellegenza Phase 2.pdf15 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5_Q3_FY 2025-26_ Ellegenza Phase 2.pdf15 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6_Q3_FY 2025-26_ Ellegenza Phase 2.pdf15 Jan 2026
Q3 2025-26 Water supply and sewage board15 Jan 2026
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)15 Jan 2026
Reshmi PK KYCFile: KYC - Reshmi.pdf3 Oct 2024
Bank account opening letterFile: Bank account opening letter.pdf3 Oct 2024
Sources of fund to complete the projectFile: Sources of Funds.pdf3 Oct 2024
Title deed - Sy No 151-1File: Sy No - 151-1 - Sale Deed.pdf3 Oct 2024
Title deed - Sy No 151-4File: Sy No - 151-4 - Sale Deed.pdf3 Oct 2024
Title deed - Sy No 152-1File: Sy No - 152-1 - Sale deed.pdf3 Oct 2024
Title deed - Sy No 152-5File: Sy No - 152-5 - Sale Deed.pdf3 Oct 2024
Title deed - Sy No 152-6File: Sy No - 152-6 - Sale Deed.pdf3 Oct 2024
Title deed - Sy No 153-1File: Sy No - 153-1 - Gift Deed.pdf3 Oct 2024
Title deed - Sy No 153-2File: Sy No - 153-2 - Sale Deed.pdf3 Oct 2024
Title deed - Sy No 153-3File: Sy No - 153-3 - Gift Deed.pdf3 Oct 2024
Title deed - Sy No 153-4File: Sy No - 153-4 - Sale Deed.pdf3 Oct 2024
Title deed - Sy No 154File: Sy No - 154 - Sale Deed.pdf3 Oct 2024
Title deed - Sy No 162-1File: Sy No - 162-1 - Partition Deed.pdf3 Oct 2024
Title deed - Sy No 165-5File: Sy No - 165-5 - Partition Deed.pdf3 Oct 2024
EC - Sy No 151-1File: SY NO 151-1 EC 01-04-2008 TO 30-08-2024.pdf3 Oct 2024
EC - Sy No 151-4File: SY NO 151-4 EC 01-04-2008 TO 30-08-2024.pdf3 Oct 2024
EC - Sy No 152-1File: SY NO 152-1 EC 01-04-2008 TO 30-08-2024.pdf3 Oct 2024
EC - Sy No 152-5File: SY NO 152-5 EC 01-04-2008 TO 30-08-2024.pdf3 Oct 2024
EC - Sy No 152-6File: SY NO 152-6 EC 01-04-2008 TO 30-08-2024.pdf3 Oct 2024
EC - Sy No 153-1File: SY NO 153-1 EC 01-04-2008 TO 30-08-2024.pdf3 Oct 2024
EC - Sy No 153-2File: SY NO 153-2 EC 01-04-2008 TO 29-08-2024.pdf3 Oct 2024
EC - Sy No 153-3File: SY NO 153-3 EC 01-04-2008 TO 29-08-2024.pdf3 Oct 2024
EC - Sy No 153-4File: SY NO 153-4 EC 01-04-2008 TO 30-08-2024.pdf3 Oct 2024
EC - Sy No 154File: SY NO 154 EC 01-04-2008 TO 29-08-2024.pdf3 Oct 2024
EC - Sy No 162-1File: SY NO 162-1 EC 01-04-2008 TO 30-08-2024.pdf3 Oct 2024
EC - Sy No 165-5File: SY NO 165-5 EC 01-04-2008 TO 30-08-2024.pdf3 Oct 2024
Document for change of Sy No 165/2 to 165/5File: SY No 165-5- MR No T65-2022-23.pdf3 Oct 2024
Engineer license certificate issued by concerned developmentFile: Engineer - Registration Certificate.pdf3 Oct 2024
Amenities and common areas details certified by engineerFile: Common area and Amenities.pdf3 Oct 2024
Structural stability certificateFile: Nambiar Structural certificate.pdf3 Oct 2024
STP drawings certified by an engineerFile: STP Drawing.pdf3 Oct 2024
Land cost calculationFile: Ellegenza Phase II Land Cost Calculations.pdf3 Oct 2024
Water Permission LetterFile: Water Permission Letter.pdf3 Oct 2024
Allotment letterFile: Allotment Letter.pdf3 Oct 2024
Estimated cost of construction certified by the EngineerFile: Estimated Cost of Construction.pdf3 Oct 2024
Project name, address and project specification certified by the EngineerFile: Project Specification.pdf3 Oct 2024
Proforma - Agreement for SaleFile: ELLEGENZA PHASE 2 - Sale Agreement.pdf3 Oct 2024
RTC, survey 151/1-
Mutation, survey 151/1-
Encumbrance Certificate, survey 151/1-
Conversion/Alienation Order, survey 151/1-
Sale/Title/Gift Deed, survey 151/1-
JDA, survey 151/1-
Khatha, survey 151/1-
RTC, survey 151/4-
Mutation, survey 151/4-
Encumbrance Certificate, survey 151/4-
Conversion/Alienation Order, survey 151/4-
Sale/Title/Gift Deed, survey 151/4-
JDA, survey 151/4-
Khatha, survey 151/4-
RTC, survey 152/1-
Mutation, survey 152/1-
Encumbrance Certificate, survey 152/1-
Conversion/Alienation Order, survey 152/1-
Sale/Title/Gift Deed, survey 152/1-
JDA, survey 152/1-
Khatha, survey 152/1-
RTC, survey 152/5-

Promoter's earlier projects6

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

3 not delivered by the promised date2 under way, not due yet1 declared completed, no finish date filed
ProjectLocationStatusPromisedDelivered
Ellegenza Phase I Extension-2Sy No 6/3. 12/1, 12/2, 12/3, 13/2, 13/3 Gopasandra Village , Sarjapura Hobli ,Anekal Taluk , AnekalOngoingMay 2027Not due yet
Ellegenza Phase I ExtensionSarjapura Hobli, AnekalOngoingMar 2027Not due yet
Bellezea Phase VNarayanaghatta Village, Anekal TalukOngoingJun 2025Not delivered
Bellezea Phase IVNarayanaghatta Village, Anekal TalukOngoingJan 2025Not delivered
Bellezea-AnnexNarayanaghatta Village Anekal TalukOngoingSep 2024Not delivered
Elleganza Phase IGopasandra Village, Sarjapura Hobli, Anekal TalukCompleted-No date filed

How this compares with Bengaluru Urban

31%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Ellegenza Phase II on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmEllegenza Phase IIOther 11Dot size: filed unitsN

Filed coordinates, straight-line distance. 11 registered projects within 2 km.

Builder: Nambiar Builders Private Limited

Nambiar Builders Private Limited has 4 registrations on RERA Karnataka, including Ellegenza Phase II and BELLEZEA PHASE V. Its filings declare 12 earlier projects, 1 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Ellegenza Phase II is delayed beyond 30 Sep 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Ellegenza Phase II?

The registered promoter entity is Nambiar Builders Private Limited, a company as per the filing. Its CIN U45201KA2009PTC050747 and GSTIN 29AADCN0664M1Z3 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Ellegenza Phase II?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Ellegenza Phase II?

The professionals named in the filing: Architect: Gnanavel Thirumaran; Engineer: Chinnaswamy Ethiraj; Chartered Accountant: K B Sandeep Kumar. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Ellegenza Phase II?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Ellegenza Phase II. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Ellegenza Phase II to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.