ReraGenieLog inGet a buyer report

Home / Browse projects / Anand, Gujarat / Dwarka Greens

Valid until 31 Jul 2026 Residential/Group Housing project

Dwarka Greens

By DWARKADHISH BUILDSPACE LLP

RG-GJ-49265 · RERA PR/GJ/ANAND/ANAND/AUDA/RAA10377/300622 · Last updated on GujRERA portal: 8 Jul 2024

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Jul 2026Possession promisedno revision filed
0 of 45Construction stages doneacross 5 buildings; furthest along: Excavation, 50%
60 of 60Units unsoldnot recorded sold or booked
Jump to the 38 documents Report an error

Dwarka Greens is a Residential/Group Housing project by DWARKADHISH BUILDSPACE LLP in Anand, Gujarat, registered with GujRERA as PR/GJ/ANAND/ANAND/AUDA/RAA10377/300622 on 30 Jun 2022. Possession is promised by 31 Jul 2026. 0 of the 60 units on this registration are recorded sold or booked, and 0 of 45 construction stages are filed complete.

At a glance

Project

  • NameDwarka Greens
  • TypeResidential/Group Housing
  • Location
    • Vadtal Road
    • Behind SPEC Campus
    • Anand
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/ANAND/ANAND/AUDA/RAA10377/300622
  • ReraGenie IDRG-GJ-49265

Builder

  • NameDWARKADHISH BUILDSPACE LLP
  • Entity typeLIMITED LIABILITY PARTNERSHIP FIRM

Key dates

this monthRegisteredJun 2022PromisedJul 2026

Key facts

Registration and timeline

  • StatusValid until 31 Jul 2026
  • Registered on30 Jun 2022
  • Promised completion31 Jul 2026
  • Revised completionNone
  • Buildings5 building records
  • Documents filed38 files

Current status

0%0 of 60 units booked
5.8%Of the estimated cost spent so far

Figures as on 8 Jul 2024, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
1 To 10---10010
11 To 23---13013
24 To 37---14014
38 To 45---808
46 To 60---15015

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building5

As on 8 Jul 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 45 construction stages are filed complete across 5 buildings. The stage furthest along is Excavation, at 50%.

1 To 106%
ActivityProgress
Excavation30%
Podiums (if any)Not applicable
Plinth25%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
11 To 230%
ActivityProgress
Excavation0%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
24 To 3718%
ActivityProgress
Excavation50%
Podiums (if any)Not applicable
Plinth50%
Stilt Floor0%
Slabs of Super Structure50%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing15%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
38 To 450%
ActivityProgress
Excavation0%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
46 To 600%
ActivityProgress
Excavation0%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%

Progress on shared amenities23

As on 8 Jul 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes10%
Water supplyYes20%
Sewerage (chamber, lines, septic tank, STP)Yes20%
Storm water drainsNoNot applicable
Landscaping and tree plantingYes50%
Street lightingYes0%
Community buildingsYes70%
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxNoNot applicable
Compound wallYes50%
Plinth protectionYes0%
Water tankYes10%
Other requirementsNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area8,433 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 14.71 cr
Cost incurredRs 85.00 lakh
Spent of the estimate5.78%
BuildingWingEstimatedIncurred
24 To 37NARs 3.56 crRs 65.00 lakh
46 To 60NARs 3.50 cr-
11 To 23NARs 3.35 cr-
1 To 10NARs 2.50 crRs 20.00 lakh
38 To 45NARs 1.80 cr-

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectNilesh Odhavji Dalsania
EngineerDesai Jaymin Indubhai

Documents filed38

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/ANAND/ANAND/AUDA/RAA10377/300622 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Engineer's certificate (Form 2)8 Jul 2024
Engineer's certificate annexure8 Jul 2024
RERA registration certificate30 Jun 2022
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Anand

0%of this project is bookeddistrict median 57%
17%of Anand projects moved their completion datethis one has not

Computed across the 310+ Anand projects on ReraGenie, from their own filings.

Keep Dwarka Greens on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Anand310+ in Anand

2 kmDwarka GreensOther 8Dot size: filed unitsN

Filed coordinates, straight-line distance. 8 registered projects within 2 km.

Builder: DWARKADHISH BUILDSPACE LLP

DWARKADHISH BUILDSPACE LLP has 1 registration on GujRERA, including Dwarka Greens. Read the full track record. See more projects on the Anand district page.

Frequently asked questions

What are my rights if Dwarka Greens is delayed beyond 31 Jul 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of Dwarka Greens?

The registered promoter entity is DWARKADHISH BUILDSPACE LLP, a limited liability partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in Dwarka Greens?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Dwarka Greens?

The professionals named in the filing: Architect: Nilesh Odhavji Dalsania; Engineer: Desai Jaymin Indubhai. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Dwarka Greens?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Dwarka Greens. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Dwarka Greens to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.