ReraGenieLog inGet a buyer report

Home / Browse projects / Uttara Kannada, Karnataka / Durga Pride Residency

Registration approved Mixed Development project

Durga Pride Residency

By Om Ganeshaya Namah Constructions

RG-KA-52164 · RERA PRM/KA/RERA/1274/351/PR/191116/003001

Source: official RERA Karnataka filing

Red flags

  • Completion date moved by 9 months
  • 1 extension taken

Clear

  • No complaints on record
  • Separate project account declared
Sep 2022Possession promisedmoved 9 months from the original
0Complaints at RERA Karnatakaon this registration
Jump to the 44 documents Report an error

Durga Pride Residency is a Mixed Development project by Om Ganeshaya Namah Constructions in Uttara Kannada, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1274/351/PR/191116/003001 on 16 Nov 2019. Possession is promised by 30 Sep 2022. The completion date has moved by 9 months from the original filing.

At a glance

Project

  • NameDurga Pride Residency
  • TypeMixed Development
  • Location
    • Karwar
    • Uttara Kannada
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1274/351/PR/191116/003001
  • ReraGenie IDRG-KA-52164

Builder

  • NameOm Ganeshaya Namah Constructions
  • Entity typeProprietorship Firm
  • Authorized SignatoryChalamani M Balaraju
  • OthersChalamani.M.Balaraju
  • Other registrations2 more →

Key dates

this monthRegisteredNov 2019First promiseDec 2021Revised toSep 2022

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on16 Nov 2019
  • Promised completion30 Sep 2022
  • Revised completionRevised to 30 Sep 2022 (originally 31 Dec 2021)
  • Buildings1 building record
  • Documents filed44 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Durga Pride Residency-----40

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja work-
Fire prevention and fire fighting fitting and fixture with network-
Weather Proof work(tile,concrete)-
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities41

Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsYes-
Sewage and Drainage SystemYes-
Parks & Tree plantingYes-
Street LightingYes-
Provision for community buildings and for treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservationNoNot applicable
Energy managementYes-
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesYes-
Electricity supply transformer and substationNoNot applicable
Emergency Evacuation servicesNoNot applicable
Storm water drainsNoNot applicable
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterNoNot applicable
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupNoNot applicable
GasNoNot applicable
Water and SanitationNoNot applicable
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesYes-
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementNoNot applicable
TerraceNoNot applicable
Outer WallNoNot applicable
Open parking areas and common storage spacesNoNot applicable
Provision for lodging of management staff and security staffYes-
Water conservation and renewable energyYes-

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,160 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 7.21 cr

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionDec 2021 → Sep 2022

No reason recorded in the filing

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed44

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1274/351/PR/191116/003001 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Commencement certificate 1-
approved layout-min-
approved layout-min-
Performa of sale deed-
Performa of Agreement for sale-
Sale deed & Khatha-
approved layout-min-
Area Development-
Provisional Allotment Letter-
Brochure-
Project Specification-
ec-
Affidavit-
JD Affidavit cum Declaration-
khata-
JDA Declaration-
legal title deed-
conversion order-
Approved Layout-
layout and project specifiaction-
conversion order-
Balance Sheet 2017 - 2018File: Balance sheet.pdf-
Balance Sheet 2016 - 2017File: Balance sheet.pdf-
Balance Sheet 2015 - 2016File: Balance sheet.pdf-
Audited Profit and Loss Statement 2017 - 2018File: Proft & Loss statement.pdf-
Audited Profit and Loss Statement 2016 - 2017File: Profit & Loss statement.pdf-
Audited Profit and Loss Statement 2015 - 2016File: Profit & Loss statement.pdf-
Director's Report 2017 - 2018File: Director's Report.pdf-
Director's Report 2016 - 2017File: Director's Report.pdf-
Director's Report 2015 - 2016File: Director's Report.pdf-
Cash Flow Statement 2017 - 2018File: Cash Flow Statement.pdf-
Cash Flow Statement 2016 - 2017File: Cash Flow Statement.pdf-
Auditor's Report 2017 - 2018File: Auditor s Report.pdf-
Auditor's Report 2016 - 2017File: Auditor s Report.pdf-
Auditor's Report 2015 - 2016File: Auditor s Report.pdf-
Income Tax Return Acknowledgement 2017 - 2018File: ITR.pdf-
Income Tax Return Acknowledgement 2016 - 2017File: ITR.pdf-
Income Tax Return Acknowledgement 2015 - 2016File: ITR.pdf-
form b-
Prospectus/BrochureFile: Brochure_1555584666231 (1).pdf-
Advertisement Copy 1File: Brochure_1555584666231 (1).pdf-
Tower Excel SheetFile: PRMKARERA1274351PR191116003001.xlsx-
Occupancy CertificateFile: OC.pdf-
Affidavit cum declaration from promoter for having completed the project as per specification and as per adverFile: Durga Heights Affidavit.pdf-

How this compares with Uttara Kannada

22%of Uttara Kannada projects moved their completion datethis one moved by 9 months
0%of Uttara Kannada registrations are shown as withdrawn or revokedthis one is not

Computed across the 100+ Uttara Kannada projects on ReraGenie, from their own filings.

Keep Durga Pride Residency on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Uttara Kannada100+ in Uttara Kannada

2 kmDurga Pride ResidencyOther 11Dot size: filed unitsN

Filed coordinates, straight-line distance. 11 registered projects within 2 km.

Builder: Om Ganeshaya Namah Constructions

Om Ganeshaya Namah Constructions has 3 registrations on RERA Karnataka, including DIMA Heights and NAKSHATRA APARTMENT. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Uttara Kannada district page.

Frequently asked questions

What are my rights if Durga Pride Residency is delayed beyond 30 Sep 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Durga Pride Residency?

The registered promoter entity is Om Ganeshaya Namah Constructions, a proprietorship firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Durga Pride Residency?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

What should I check before booking in Durga Pride Residency?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Durga Pride Residency. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Durga Pride Residency to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.