Home / Browse projects / Vadodara, Gujarat / DREAM 19
DREAM 19
RG-GJ-09778 · RERA PR/GJ/VADODARA/VADODARA/Vadodara Municipal Corporation/RAA16065/041125/311230 · Last updated on GujRERA portal: 28 May 2026
Source: official GujRERA filing
Red flags
- No red flags in this filing
Clear
- Completion date never moved
Saved.
DREAM 19 is a Residential/Group Housing project by DREAM BUILDCON in Vadodara, Gujarat, registered with GujRERA as PR/GJ/VADODARA/VADODARA/Vadodara Municipal Corporation/RAA16065/041125/311230 on 4 Nov 2025. Possession is promised by 30 Apr 2031. 6 of the 19 units on this registration are recorded sold or booked, and 2 of 54 construction stages are filed complete.
At a glance
Project
- NameDREAM 19
- TypeResidential/Group Housing
- Location
- BEFORE SHRADDHA PETROL PUMP
- NH 48
- OPP. GIRIRAJ HOTEL
- NR. KAPURAI CHOKDI
- KAPURAI
- Vadodara
- 390004
- Pincode390004
- MapView location on Google Maps (as filed on RERA)
- RERA no.PR/GJ/VADODARA/VADODARA/Vadodara Municipal Corporation/RAA16065/041125/311230
- ReraGenie IDRG-GJ-09778
Builder
- NameDREAM BUILDCON
- Entity typePARTNERSHIP FIRM
- Other registrations1 more →
Key dates
Key facts
Registration and timeline
- StatusValid until 30 Apr 2031
- Registered on4 Nov 2025
- Promised completion30 Apr 2031
- Revised completionNone
- Buildings6 building records
- Documents filed38 files
Current status
Figures as on 28 May 2026, this project's latest GujRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| TYPE B | - | - | - | 8 | 0 | 8 |
| TYPE A | - | - | - | 1 | 0 | 1 |
| TYPE D | - | - | - | 7 | 0 | 7 |
| TYPE C | - | - | - | 1 | 0 | 1 |
| TYPE F | - | - | - | 1 | 0 | 1 |
| TYPE E | - | - | - | 1 | 0 | 1 |
The full filing
Everything below is from the project's own GujRERA filing, free to read.
Construction progress by building6
As on 28 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
2 of 54 construction stages are filed complete across 6 buildings. The stage furthest along is External plumbing and external plaster, at 80%.
TYPE B16%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Podiums (if any) | Not applicable |
| Plinth | 50% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 50% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 20% |
| Sanitary fittings within the flats | 0% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 20% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 0% |
TYPE A37%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 50% |
| Sanitary fittings within the flats | 0% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 80% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 0% |
TYPE D3%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Podiums (if any) | Not applicable |
| Plinth | 15% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 15% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 0% |
| Sanitary fittings within the flats | 0% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 0% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 0% |
TYPE C0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Podiums (if any) | Not applicable |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 0% |
| Sanitary fittings within the flats | 0% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 0% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 0% |
TYPE F0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Podiums (if any) | Not applicable |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 0% |
| Sanitary fittings within the flats | 0% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 0% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 0% |
TYPE E0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Podiums (if any) | Not applicable |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 0% |
| Sanitary fittings within the flats | 0% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 0% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 0% |
Progress on shared amenities19
As on 28 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal roads and footpaths | Yes | 0% |
| Water supply | Yes | 0% |
| Sewerage (chamber, lines, septic tank, STP) | Yes | 0% |
| Storm water drains | Yes | 0% |
| Landscaping and tree planting | Yes | 0% |
| Street lighting | Yes | 0% |
| Community buildings | No | Not applicable |
| Treatment and disposal of sewage and sullage water | Yes | 0% |
| Solid waste management and disposal | Yes | 0% |
| Water conservation, rain water harvesting | Yes | 0% |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Fire fighting | No | Not applicable |
| Drinking water facilities | Yes | 0% |
| Emergency evacuation | No | Not applicable |
| Use of renewable energy | No | Not applicable |
| Security | Yes | 0% |
| Letter box | No | Not applicable |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| TYPE D | NA | Rs 1.89 cr | Rs 87.00 lakh |
| TYPE B | NA | Rs 1.66 cr | - |
| TYPE C | NA | Rs 25.83 lakh | - |
| TYPE A | NA | Rs 24.25 lakh | Rs 9.37 lakh |
| TYPE F | NA | Rs 23.07 lakh | - |
| TYPE E | NA | Rs 21.50 lakh | - |
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | SHRENIK RAJENDRAKUMAR SONI |
| Engineer | TARANG KARSHANBHAI GALANI |
Documents filed38
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VADODARA/VADODARA/Vadodara Municipal Corporation/RAA16065/041125/311230 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Engineer's certificate (Form 2) | 28 May 2026 |
| Engineer's certificate annexure | 28 May 2026 |
| Accountant's certificate (Form 3) | 28 May 2026 |
| Architect's certificate (Form 1) | 23 Apr 2026 |
| Site photograph, TYPE B | 21 Apr 2026 |
| Site photograph, TYPE A | 21 Apr 2026 |
| Site photograph, TYPE D | 21 Apr 2026 |
| Site photograph, TYPE C | 21 Apr 2026 |
| Site photograph, TYPE F | 21 Apr 2026 |
| Site photograph, TYPE E | 21 Apr 2026 |
| RERA registration certificate | 4 Nov 2025 |
| Proforma agreement for sale | - |
| Auditor's report (3 of 3) | - |
| Income tax return (3 of 3) | - |
| Project specific document | - |
| Drainage affidavit | - |
| Directors' report (3 of 3) | - |
| Approved sanctioned plan | - |
| Approved layout plan | - |
| Agreement | - |
| Land location | - |
| Encumbrance certificate | - |
| Area development document | - |
| Proforma allotment letter | - |
| Brochure | - |
| Declaration in Form B | - |
| Approved building or plotting plan | - |
| NOCs from authorities | - |
| Title clearance certificate | - |
| Title report | - |
| Property card | - |
| Statutory document | - |
| Other document | - |
| Project photograph | - |
| Proforma sale deed | - |
| Audited balance sheet (3 of 3) | - |
| Audited profit and loss statement (3 of 3) | - |
| Cash flow statement (3 of 3) | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Vadodara
Computed across the 2,900+ Vadodara projects on ReraGenie, from their own filings.
Keep DREAM 19 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near KAPURAI2,900+ in Vadodara
Filed coordinates, straight-line distance. 173 registered projects within 2 km.
AKSHAR CITY
AKSHAR BUILDERS
THE GOKULESH CITY
Gokulesh Infra
THE KRISHNA CITY
KRISHNA DEVELOPERS
Eastern Arcade
Maniratnadevelopers
KUBER CITY
KUBER HEIGHTS
ANANTA SHUBHLAXMI
SHUBHLAXMI HOMES
See every Vadodara project, with the district possession charts
Builder: DREAM BUILDCON
DREAM BUILDCON has 2 registrations on GujRERA, including I HOME and DREAM 19. Read the full track record. See more projects on the Vadodara district page.
Frequently asked questions
What are my rights if DREAM 19 is delayed beyond 30 Apr 2031?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.
How do I verify and contact the developer of DREAM 19?
The registered promoter entity is DREAM BUILDCON, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.
Is my payment protected in DREAM 19?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at DREAM 19?
The professionals named in the filing: Architect: SHRENIK RAJENDRAKUMAR SONI; Engineer: TARANG KARSHANBHAI GALANI. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in DREAM 19?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.