Home / Browse projects / Davangere, Karnataka / DHIRAAN BAKKESHWARA RESIDENCY

Registration approved No litigation declared Residential/Group Housing project

DHIRAAN BAKKESHWARA RESIDENCY

By DHIRAAN PROPERTIES

RG-KA-28166 · RERA PRM/KA/RERA/1258/404/PR/210924/007057 · Last updated on RERA Karnataka portal: 8 Jul 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Aug 2026Possession promisedno revision filed
16 of 16Construction stages doneevery applicable stage filed complete
22 of 24Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 133 documents Report an error

DHIRAAN BAKKESHWARA RESIDENCY is a Residential/Group Housing project by DHIRAAN PROPERTIES in Davangere, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1258/404/PR/210924/007057 on 21 Sep 2024. Possession is promised by 31 Aug 2026. 2 of the 24 units on this registration are recorded sold or booked, and 16 of 16 construction stages are filed complete.

At a glance

Project

  • NameDHIRAAN BAKKESHWARA RESIDENCY
  • TypeResidential/Group Housing
  • Location
    • Davanagere
    • Davangere
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1258/404/PR/210924/007057
  • ReraGenie IDRG-KA-28166

Builder

  • NameDHIRAAN PROPERTIES
  • Entity typePartnership Firm
  • GSTIN29AARFD9254E1ZY
  • Authorized SignatorySURESH B S

Key dates

this monthRegisteredSep 2024PromisedAug 2026

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on21 Sep 2024
  • Promised completion31 Aug 2026
  • Revised completionNone
  • Buildings1 building record
  • Documents filed133 files

Current status

8%2 of 24 units booked
76.7%Of the estimated cost spent so far

Figures as on 8 Jul 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Building---24024

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 8 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

16 of 16 construction stages are filed complete.

Building: 100% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
Retaining wall (All types)Not applicable
RCC or MS Framed structure100%
Masonry Construction100%
Plastering inside , outside & Ceiling100%
Joinery: Doors, Windows, Ventilators etc100%
Basic work of Water supply, Sanitary and Electrification100%
Dadoing, Skirting, Flooring, Tiles work (All types)100%
Railing and Grill fixing100%
Electrification, Water supply and Sanitary Finishing100%
Painting100%
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)100%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work100%
Internal and External work including landscapes as per sanctioned drawings100%

Progress on shared amenities40

As on 8 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes100%
Sewage and Drainage SystemYes100%
Water conservation/rain water harvesting/recharge of ground waterYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalYes100%
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsNoNot applicable
Electricity supply transformer and substationYes100%
Storm water drainsYes100%
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes100%
Parks & Tree plantingYes100%
Street LightingNoNot applicable
ElectricityYes100%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes100%
Club HouseNoNot applicable
Community HallYes100%
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupYes100%
Piped GasNoNot applicable
Water and SanitationYes100%
Air ConditioningNoNot applicable
StaircasesYes100%
LiftsYes100%
Corridor/LobbiesYes100%
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahYes100%
BasementNoNot applicable
TerraceYes100%
Outer WallYes100%
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffYes100%
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership2

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Named landowners2
LandownerVillageDistrict
Pavithra S K--
S B Murugesh--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 6.60 cr
Cost incurredRs 5.06 cr
Spent of the estimate76.69%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 5.95 crRs 5.06 cr
Payment of taxesRs 34.00 lakh-
On-site expenditure-Site OverheadRs 25.00 lakh-
On-site expenditure-Consultants FeesRs 6.00 lakh-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSrimathi J Adiga
EngineerVishnu Kumar
Chartered AccountantMahaveer Bhansali Jain

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed133

As listed on the registration, under the names the promoter filed them with; the newest 80 of 133 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1258/404/PR/210924/007057 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form - 4, CA rera QR - DB - Jun26.pdf8 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form 5, Q1,2026-27, Dhiraan Bakkeshwara Residency.pdf8 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: FORM-6 BAKKESHWARA DHIRAAN 30-06-2026.pdf8 Jul 2026
Q1 2026-27 Water supply and sewage board8 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)8 Jul 2026
Q1 2026-27 KPTCL- BESCOM8 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form - 4, CA rera QR - DB - Mar26 signed.pdf10 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form5, Q4,2025-26,Dhiraan Bakkeshwara Residency.pdf10 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: FORM-6 BAKKESHWARA DHIRAAN 31-03-2026.pdf10 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: FORM-4 BAKKESHWARA DHIRAAN 31-12-2025.pdf13 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: FORM-5 BAKKESHWARA DHIRAAN 31-12-2025.pdf13 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: FORM-6 BAKKESHWARA DHIRAAN 31-12-2025.pdf13 Jan 2026
Source of Funds with supporting docsFile: 1 Source of Funds with supporting docs.pdf23 Aug 2024
Financials FY 2023-24File: 1 Financials FY 2023-24.pdf15 Jul 2024
Clarification on FinancialsFile: 2 Clarification on Financials.pdf15 Jul 2024
Bank affidavit UpdatedFile: 3 Bank affidavit Updated.pdf15 Jul 2024
Source of Funds with supporting docsFile: 4 Source of Funds with supporting docs.pdf15 Jul 2024
RTC Sy No 150-2A3File: 5 RTC Sy No 150-2A3.pdf15 Jul 2024
RTC Sy No 150-2B1File: 6 RTC Sy No 150-2B1.pdf15 Jul 2024
MR Sy No 150-2B1File: 7 MR Sy No 150-2B1.pdf15 Jul 2024
CONVERSION ORDER - ALNSR-88 AND 89-03-04File: 8 CONVERSION ORDER - ALNSR-88 AND 89-03-04.pdf15 Jul 2024
Title Deed CERTIFIED COPY DOC 1569-67-68File: 5 Title Deed CERTIFIED COPY DOC 1569-67-68.pdf15 Jul 2024
Title Deed CERTIFIED COPY DOC- 4408-66-67File: 5 Title Deed CERTIFIED COPY DOC- 4408-66-67.pdf15 Jul 2024
Title Deed GIFT DEED- 6524-2021-22File: 5 Title Deed GIFT DEED- 6524-2021-22.pdf15 Jul 2024
Title Deed PARTITION DEED - DVG-1-17170-2012-13 - DT 16-3-2013File: 5 Title Deed PARTITION DEED - DVG-1-6858-2013-14 - DT 24-7-2013.pdf15 Jul 2024
Title Deed PARTITION DEED - DVG-1-6858-2013-14 - DT 24-7-2013File: 5 Title Deed PARTITION DEED - DVG-1-17170-2012-13 - DT 16-3-2013.pdf15 Jul 2024
Title Deed REVISED AREA GIFT DEED - DVG-1-03780-2007-08File: 5 Title Deed REVISED AREA GIFT DEED - DVG-1-03780-2007-08.pdf15 Jul 2024
Title Deed VIBHAGA PATRA - DVG-1-02879-2007-08File: 5 Title Deed VIBHAGA PATRA - DVG-1-02879-2007-08.pdf15 Jul 2024
Ec 2004 -2024File: 9 Ec 2004 -2024.pdf15 Jul 2024
COPY OF ENDORSEMENT - NO 217-13-14 SITE 41 TO 50File: COPY OF ENDORSEMENT - NO 217-13-14 SITE 41 TO 50.pdf15 Jul 2024
ENDORSEMENT OF COMBINING SITES ORDER - CR-20-2012-13 DT 20-02-2013File: ENDORSEMENT OF COMBINING SITES ORDER - CR-20-2012-13 DT 20-02-2013.pdf15 Jul 2024
Single Plot Order and PlanFile: Single Plot Order and Plan.pdf15 Jul 2024
Area Statement CertificateFile: 1 Area Statement Certificate.pdf15 Jul 2024
Bakkeshwara CDP DemarcationFile: 2 Bakkeshwara CDP Demarcation.pdf15 Jul 2024
Village Map DemarcationFile: 3 Village Map Demarcation.pdf15 Jul 2024
Clarification on KSPCB NOCFile: 4 Clarification on KSPCB NOC.pdf15 Jul 2024
SANCTION PLANFile: 5 SANCTION PLAN.pdf15 Jul 2024
Form-6 BAKKESHWARA DHIRAANFile: 6 Form-6 BAKKESHWARA DHIRAAN.pdf15 Jul 2024
Davanagere GuidelinesFile: 7 Davanagere Guidelines.pdf15 Jul 2024
KHATHA ExtractFile: KHATHA Extract.pdf15 Jul 2024
Registration CertificateFile: Firm Reg cert - Dhiraan.jpeg-
Partnership DeedFile: DHIRAAN PROPERTIES - PARTNERSHIP DEED.pdf-
Partner Details-
Partner Details-
Certificate issued by CA Form 1File: Form-1 CA Certificate.pdf-
Certificate issued by Architect Form 2File: Form-2 Architect Certificate.pdf-
Certificate issued by Engineer Form 3File: Form-3 Engineer Certificate.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: Non Litigation Affidavit.pdf-
Certificate from Chartered AccountFile: Form-1 CA Certificate.pdf-
Balance Sheet 2022 - 2023File: Clarification on Financials.pdf-
Balance Sheet 2021 - 2022File: Clarification on Financials.pdf-
Balance Sheet 2020 - 2021File: Clarification on Financials.pdf-
Audited Profit and Loss Statement 2022 - 2023File: Clarification on Financials.pdf-
Audited Profit and Loss Statement 2021 - 2022File: Clarification on Financials.pdf-
Audited Profit and Loss Statement 2020 - 2021File: Clarification on Financials.pdf-
Income Tax Return Acknowledgement 2022 - 2023File: Clarification on Financials.pdf-
Income Tax Return Acknowledgement 2021 - 2022File: Clarification on Financials.pdf-
Income Tax Return Acknowledgement 2020 - 2021File: Clarification on Financials.pdf-
BUILDING LICENCE - BAKKESHWARA-
BESCOM NOC - with fee receipt-
WATER NOC - BAKKESHWARA-
SANCTION PLAN-
Project Specification-
SANCTION PLAN-
Project Specification-
SANCTION PLAN-
Not Avaialable-
STRUCTURAL STABILITY CERTIFICATE- DBR-
Legal Report-
JDA-
Proforma Agreement of Sale - DBR-
Proforma Allotment Letter-DBR-
Form B Affidavit-
Section 3(1) Affidavit-
JD affidavit cum declaration-
BESCOM NOC - with fee receipt-
WATER NOC - BAKKESHWARA-

How this compares with Davangere

8%of this project is bookeddistrict median 14%
9%of Davangere projects moved their completion datethis one has not
0%of Davangere registrations are shown as withdrawn or revokedthis one is not

Computed across the 41 Davangere projects on ReraGenie, from their own filings.

Keep DHIRAAN BAKKESHWARA RESIDENCY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Davangere41 in Davangere

Builder: DHIRAAN PROPERTIES

DHIRAAN PROPERTIES has 1 registration on RERA Karnataka, including DHIRAAN BAKKESHWARA RESIDENCY. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Davangere district page.

Frequently asked questions

What are my rights if DHIRAAN BAKKESHWARA RESIDENCY is delayed beyond 31 Aug 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of DHIRAAN BAKKESHWARA RESIDENCY?

The registered promoter entity is DHIRAAN PROPERTIES, a partnership firm as per the filing. Its GSTIN 29AARFD9254E1ZY can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in DHIRAAN BAKKESHWARA RESIDENCY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at DHIRAAN BAKKESHWARA RESIDENCY?

The professionals named in the filing: Architect: Srimathi J Adiga; Engineer: Vishnu Kumar; Chartered Accountant: Mahaveer Bhansali Jain. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in DHIRAAN BAKKESHWARA RESIDENCY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About DHIRAAN BAKKESHWARA RESIDENCY. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save DHIRAAN BAKKESHWARA RESIDENCY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.