Valid until 30 Apr 2028 Mixed Development project

DARSHANAM KING SQUARE

By DARSHANAM SMART SPACES

RG-GJ-86021 · RERA PR/GJ/VADODARA/VADODARA/Others/MAA10389/040722 · Last updated on GujRERA portal: 19 Jan 2026

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Apr 2028Possession promisedno revision filed
4 of 9Construction stages donefurthest along: Internal walls, 50%
147 of 299Units unsoldnot recorded sold or booked
Jump to the 42 documents Report an error

DARSHANAM KING SQUARE is a Mixed Development project by DARSHANAM SMART SPACES in Vadodara, Gujarat, registered with GujRERA as PR/GJ/VADODARA/VADODARA/Others/MAA10389/040722 on 4 Jul 2022. Possession is promised by 30 Apr 2028. 152 of the 299 units on this registration are recorded sold or booked, and 4 of 9 construction stages are filed complete.

At a glance

Project

  • NameDARSHANAM KING SQUARE
  • TypeMixed Development
  • Location
    • DARSHANAM KING SQUARE
    • NR DARSHANAM CLUBLIFE
    • 30 MTR YASH COMPLEX ROAD
    • GOTRI MAIN ROAD
    • NEW GOTRI
    • Vadodara
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/VADODARA/VADODARA/Others/MAA10389/040722
  • ReraGenie IDRG-GJ-86021

Builder

  • NameDARSHANAM SMART SPACES
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredJul 2022PromisedApr 2028

Key facts

Registration and timeline

  • StatusValid until 30 Apr 2028
  • Registered on4 Jul 2022
  • Promised completion30 Apr 2028
  • Revised completionNone
  • Buildings1 building record
  • Documents filed42 files

Current status

51%152 of 299 units booked
70.0%Of the estimated cost spent so far

Figures as on 19 Jan 2026, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ABCDEFG---140159299

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 19 Jan 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 9 construction stages are filed complete. The stage furthest along is Internal walls, at 50%.

ABCDEFG: 64% average across the applicable activities

ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats50%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing50%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing25%

Progress on shared amenities19

As on 19 Jan 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes20%
Water supplyYes0%
Sewerage (chamber, lines, septic tank, STP)Yes0%
Storm water drainsNoNot applicable
Landscaping and tree plantingYes0%
Street lightingYes0%
Community buildingsYes35%
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Fire fightingYes0%
Drinking water facilitiesYes0%
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes0%
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area8,802 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 70.00 cr
Cost incurredRs 49.00 cr
Spent of the estimate70.0%
BuildingWingEstimatedIncurred
ABCDEFGNARs 70.00 crRs 49.00 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDesign Studio Associates
EngineerASHOK SHAH & ASSOCIATES

Documents filed42

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VADODARA/VADODARA/Others/MAA10389/040722 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Engineer's certificate (Form 2)19 Jan 2026
Engineer's certificate annexure19 Jan 2026
Accountant's certificate (Form 3)19 Jan 2026
Architect's certificate (Form 1)16 Jan 2026
Site photograph, ABCDEFG16 Jan 2026
RERA registration certificate4 Jul 2022
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Proforma sale deed-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Vadodara

51%of this project is bookeddistrict median 70%
23%of Vadodara projects moved their completion datethis one has not

Computed across the 2,900+ Vadodara projects on ReraGenie, from their own filings.

Keep DARSHANAM KING SQUARE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Vadodara2,900+ in Vadodara

2 kmDARSHANAM KING SQUAREOther 151Dot size: filed unitsN

Filed coordinates, straight-line distance. 151 registered projects within 2 km.

Builder: DARSHANAM SMART SPACES

DARSHANAM SMART SPACES has 1 registration on GujRERA, including DARSHANAM KING SQUARE. Read the full track record. See more projects on the Vadodara district page.

Frequently asked questions

What are my rights if DARSHANAM KING SQUARE is delayed beyond 30 Apr 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of DARSHANAM KING SQUARE?

The registered promoter entity is DARSHANAM SMART SPACES, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in DARSHANAM KING SQUARE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at DARSHANAM KING SQUARE?

The professionals named in the filing: Architect: Design Studio Associates; Engineer: ASHOK SHAH & ASSOCIATES. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in DARSHANAM KING SQUARE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About DARSHANAM KING SQUARE. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save DARSHANAM KING SQUARE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.