ReraGenieLog inGet a buyer report

Home / Browse projects / Vadodara, Gujarat / DARBAR ELECON

Valid until 30 Jun 2024 Residential/Group Housing project

DARBAR ELECON

By DARBAR ENTERPRISE

RG-GJ-34752 · RERA PR/GJ/VADODARA/VADODARA/Others/RAA05108/200319 · Last updated on GujRERA portal: 9 Apr 2024

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Jun 2024Possession promisedno revision filed
55 of 108Construction stages doneacross 12 buildings; furthest along: External plumbing and external plaster, 97%
5 of 86Units unsoldnot recorded sold or booked
Jump to the 52 documents Report an error

DARBAR ELECON is a Residential/Group Housing project by DARBAR ENTERPRISE in Vadodara, Gujarat, registered with GujRERA as PR/GJ/VADODARA/VADODARA/Others/RAA05108/200319 on 20 Mar 2019. Possession is promised by 30 Jun 2024. 81 of the 86 units on this registration are recorded sold or booked, and 55 of 108 construction stages are filed complete.

At a glance

Project

  • NameDARBAR ELECON
  • TypeResidential/Group Housing
  • Location
    • OLD S.A. 74/2
    • BLOCK NO. 64
    • PLOT NO 166 TO 312
    • HETAMPURA
    • Hetampura
    • Vadodara
    • 390004
  • Pincode390004
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/VADODARA/VADODARA/Others/RAA05108/200319
  • ReraGenie IDRG-GJ-34752

Builder

  • NameDARBAR ENTERPRISE
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredMar 2019PromisedJun 2024

Key facts

Registration and timeline

  • StatusValid until 30 Jun 2024
  • Registered on20 Mar 2019
  • Promised completion30 Jun 2024
  • Revised completionNone
  • Buildings12 building records
  • Documents filed52 files

Current status

94%81 of 86 units booked
98.8%Of the estimated cost spent so far

Figures as on 9 Apr 2024, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
C1---26026
1 & 2---101
3 & 4---101
5 & 6---101
7 & 8---101
9, 10, 11---101
OWNER---101
A---707
A1---707
B---404
B1---202
C---34034

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building12

As on 9 Apr 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

55 of 108 construction stages are filed complete across 12 buildings. The stage furthest along is External plumbing and external plaster, at 97%.

C166%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing97%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
1 & 266%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing97%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
3 & 466%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing97%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
5 & 666%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing97%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
7 & 866%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing97%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
9, 10, 1166%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing97%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
OWNER0%
ActivityProgress
Excavation0%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
A66%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing97%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
A166%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing97%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
B66%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing97%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
B166%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing97%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
C66%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing97%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%

Progress on shared amenities19

As on 9 Apr 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes80%
Water supplyYes80%
Sewerage (chamber, lines, septic tank, STP)Yes95%
Storm water drainsYes90%
Landscaping and tree plantingYes80%
Street lightingYes90%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalYes75%
Water conservation, rain water harvestingYes75%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area10,132 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 5.20 cr
Cost incurredRs 5.14 cr
Spent of the estimate98.84%
BuildingWingEstimatedIncurred
CNARs 2.06 crRs 2.06 cr
C1NARs 1.57 crRs 1.57 cr
ANARs 42.36 lakhRs 42.36 lakh
A1NARs 42.36 lakhRs 42.36 lakh
BNARs 24.21 lakhRs 24.21 lakh
B1NARs 12.10 lakhRs 12.10 lakh
1 & 2NARs 6.05 lakhRs 6.05 lakh
3 & 4NARs 6.05 lakhRs 6.05 lakh
5 & 6NARs 6.05 lakhRs 6.05 lakh
7 & 8NARs 6.05 lakhRs 6.05 lakh
9, 10, 11NARs 6.05 lakhRs 6.05 lakh
OWNERNARs 6.05 lakh-

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectP. D. AKRUWALA
EngineerCHINTAN R PATEL

Documents filed52

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VADODARA/VADODARA/Others/RAA05108/200319 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)9 Apr 2024
Architect's certificate (Form 1)5 Apr 2024
Engineer's certificate (Form 2)5 Apr 2024
Engineer's certificate annexure5 Apr 2024
Site photograph, C14 Apr 2024
Site photograph, 1 & 24 Apr 2024
Site photograph, 3 & 44 Apr 2024
Site photograph, 5 & 64 Apr 2024
Site photograph, 7 & 84 Apr 2024
Site photograph, 9, 10, 114 Apr 2024
Site photograph, OWNER4 Apr 2024
Site photograph, A4 Apr 2024
Site photograph, A14 Apr 2024
Site photograph, B4 Apr 2024
Site photograph, B14 Apr 2024
Site photograph, C4 Apr 2024
RERA registration certificate20 Mar 2019
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Vadodara

94%of this project is bookeddistrict median 70%
23%of Vadodara projects moved their completion datethis one has not

Computed across the 2,900+ Vadodara projects on ReraGenie, from their own filings.

Keep DARBAR ELECON on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Hetampura2,900+ in Vadodara

Builder: DARBAR ENTERPRISE

DARBAR ENTERPRISE has 1 registration on GujRERA, including DARBAR ELECON. Read the full track record. See more projects on the Vadodara district page.

Frequently asked questions

What are my rights if DARBAR ELECON is delayed beyond 30 Jun 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of DARBAR ELECON?

The registered promoter entity is DARBAR ENTERPRISE, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in DARBAR ELECON?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at DARBAR ELECON?

The professionals named in the filing: Architect: P. D. AKRUWALA; Engineer: CHINTAN R PATEL. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in DARBAR ELECON?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About DARBAR ELECON. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save DARBAR ELECON to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.