Home / Browse projects / Vadodara, Gujarat / CRYSTAL PRAMUKH COMMERCIAL HUB

Valid until 31 Mar 2028 Commercial project

CRYSTAL PRAMUKH COMMERCIAL HUB

By KEYA BUILDTECH LLP

RG-GJ-74628 · RERA PR/GJ/VADODARA/VADODARA/Others/CAA11558/060423 · Last updated on GujRERA portal: 6 Apr 2023

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
  • Separate project account declared
Mar 2028Possession promisedno revision filed
2 of 8Construction stages donefurthest along: Slabs of Super Structure, 90%
92 of 245Units unsoldnot recorded sold or booked
Jump to the 41 documents Report an error

CRYSTAL PRAMUKH COMMERCIAL HUB is a Commercial project by KEYA BUILDTECH LLP in Vadodara, Gujarat, registered with GujRERA as PR/GJ/VADODARA/VADODARA/Others/CAA11558/060423 on 6 Apr 2023. Possession is promised by 31 Mar 2028. 153 of the 245 units on this registration are recorded sold or booked, and 2 of 8 construction stages are filed complete.

At a glance

Project

  • NameCRYSTAL PRAMUKH COMMERCIAL HUB
  • TypeCommercial
  • Location
    • SR 175/1
    • 175/3 & 183
    • TP-5
    • FP-294 & 295
    • OPP INDIAN PETROL PUMP
    • NEAR KHODIAR CROSSING
    • NEW VIP ROAD
    • Vadodara
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/VADODARA/VADODARA/Others/CAA11558/060423
  • ReraGenie IDRG-GJ-74628

Builder

  • NameKEYA BUILDTECH LLP
  • Entity typeLIMITED LIABILITY PARTNERSHIP FIRM

Key dates

this monthRegisteredApr 2023PromisedMar 2028

Key facts

Registration and timeline

  • StatusValid until 31 Mar 2028
  • Registered on6 Apr 2023
  • Promised completion31 Mar 2028
  • Revised completionNone
  • Buildings1 building record
  • Documents filed41 files

Current status

62%153 of 245 units booked
82.9%Of the estimated cost spent so far

Figures as on 6 Apr 2023, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
COMMERCIAL---0238245

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 6 Apr 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

2 of 8 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 90%.

COMMERCIAL: 65% average across the applicable activities

ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure90%
Internal walls, internal plaster, floorings, doors and windows within flats75%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks85%
External plumbing and external plaster, elevation, completion of terraces with waterproofing70%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%

Progress on shared amenities19

As on 6 Apr 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsNoNot applicable
Water supplyYes0%
Sewerage (chamber, lines, septic tank, STP)Yes0%
Storm water drainsYes0%
Landscaping and tree plantingNoNot applicable
Street lightingYes0%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Fire fightingYes0%
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes0%
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area6,625 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 34.99 cr
Cost incurredRs 28.99 cr
Spent of the estimate82.87%
BuildingWingEstimatedIncurred
COMMERCIALNARs 34.99 crRs 28.99 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMR. HARSH PRAFULKUMAR PANDYA
EngineerCHETAN KAMBAD

Documents filed41

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VADODARA/VADODARA/Others/CAA11558/060423 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
RERA registration certificate6 Apr 2023
Engineer's certificate (Form 2)29 Mar 2023
Engineer's certificate annexure29 Mar 2023
Accountant's certificate (Form 3)3 Mar 2023
Architect's certificate (Form 1)2 Mar 2023
Site photograph, COMMERCIAL2 Mar 2023
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Vadodara

62%of this project is bookeddistrict median 70%
23%of Vadodara projects moved their completion datethis one has not

Computed across the 2,900+ Vadodara projects on ReraGenie, from their own filings.

Keep CRYSTAL PRAMUKH COMMERCIAL HUB on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Vadodara2,900+ in Vadodara

2 kmCRYSTAL PRAMUKH COMMERCIOther 111Dot size: filed unitsN

Filed coordinates, straight-line distance. 111 registered projects within 2 km.

Builder: KEYA BUILDTECH LLP

KEYA BUILDTECH LLP has 1 registration on GujRERA, including CRYSTAL PRAMUKH COMMERCIAL HUB. Read the full track record. See more projects on the Vadodara district page.

Frequently asked questions

What are my rights if CRYSTAL PRAMUKH COMMERCIAL HUB is delayed beyond 31 Mar 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of CRYSTAL PRAMUKH COMMERCIAL HUB?

The registered promoter entity is KEYA BUILDTECH LLP, a limited liability partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in CRYSTAL PRAMUKH COMMERCIAL HUB?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at CRYSTAL PRAMUKH COMMERCIAL HUB?

The professionals named in the filing: Architect: MR. HARSH PRAFULKUMAR PANDYA; Engineer: CHETAN KAMBAD. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in CRYSTAL PRAMUKH COMMERCIAL HUB?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About CRYSTAL PRAMUKH COMMERCIAL HUB. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save CRYSTAL PRAMUKH COMMERCIAL HUB to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.