RG-KA-14811 · RERA PRM/KA/RERA/1251/309/PR/230326/008545 · Last updated on RERA Karnataka portal: 15 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Dec 2030Possession promisedno revision filed
0 of 16Construction stages donefurthest along: Earth work and other leveling..., 95%
2 of 416Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 121 documents Report an error

Brigade Lumina is a Residential/Group Housing project by Brigade Enterprises Ltd in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/309/PR/230326/008545 on 23 Mar 2026. Possession is promised by 31 Dec 2030. 414 of the 416 units on this registration are recorded sold or booked, and 0 of 16 construction stages are filed complete.

At a glance

Project

  • NameBrigade Lumina
  • TypeResidential/Group Housing
  • Location
    • Bengaluru North
    • Bengaluru Urban
    • 560073
  • Pincode560073
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/309/PR/230326/008545
  • ReraGenie IDRG-KA-14811

Builder

  • NameBrigade Enterprises Ltd
  • Entity typeCompany
  • CINL85110KA1995PLC019126
  • GSTIN29AAACB7459F1ZI
  • Authorized SignatoryMr. Viswa Prathap Desu
  • Managing DirectorPavitra Shankar
  • DirectorsMr. M. R. Jaishankar, Ms. Pavitra Shankar, Ms. Nirupa Shankar, Mr. Roshin Mathew, Mr. Amar Mysore, Mr. Pradyumna Krishna Kumar, Ms. Lakshmi Venkatachalam, Mr. Pradeep Kumar Panja, Dr. Venkatesh Panchapagesan, Mr. Velloor Venkatakrishnan Ranganathan, Mr. Abraham Stephanos, Ms. Padmaja Chunduru
  • Project HeadSrinivasa N
  • Other registrations45 more →
  • No longer live1 withdrawn or revoked
  • Declared earlier projects67 →

Key dates

this monthRegisteredMar 2026PromisedDec 2030

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on23 Mar 2026
  • Promised completion31 Dec 2030
  • Revised completionNone
  • Buildings3 building records
  • Documents filed121 files

Current status

100%414 of 416 units booked
4.9%Of the estimated cost spent so far

Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TOWER - A---1540154
TOWER - B---1460146
TOWER - C---1160116

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 16 construction stages are filed complete. The stage furthest along is Earth work and other leveling preparation work, at 95%.

Building: 10% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work95%
Foundation footing work65%
Upto Plinth Level0%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)0%
Retaining wall (All types)Not applicable
RCC or MS Framed structure3%
Masonry Construction0%
Plastering inside , outside & Ceiling0%
Joinery: Doors, Windows, Ventilators etc0%
Basic work of Water supply, Sanitary and Electrification0%
Dadoing, Skirting, Flooring, Tiles work (All types)0%
Railing and Grill fixing0%
Electrification, Water supply and Sanitary Finishing0%
Painting0%
Fire prevention and fire fighting fitting and fixture with network0%
Weather Proof work(tile,concrete)0%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation workNot applicable
Internal and External work including landscapes as per sanctioned drawings0%

Progress on shared amenities38

As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes0%
Sewage and Drainage SystemYes0%
Water conservation/rain water harvesting/recharge of ground waterYes5%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes0%
Solid waste management and disposalYes2%
Emergency Evacuation servicesYes0%
Internal Roads & FootpathsNoNot applicable
Electricity supply transformer and substationNoNot applicable
Storm water drainsYes0%
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes0%
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupYes0%
Piped GasNoNot applicable
Water and SanitationYes0%
Air ConditioningNoNot applicable
StaircasesYes0%
LiftsYes0%
Corridor/LobbiesYes0%
Fire escapesYes0%
Common entrance and exit for the building/common portico/foyer/verandahYes0%
BasementYes15%
TerraceYes0%
Outer WallYes0%
Open parking areasYes0%
Provision for lodging of management staff and security staffNoNot applicable

Land and ownership9

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area16,076 sq m
Named landowners9
LandownerVillageDistrict
K. R. BALASUBRAMANIAM--
K. R. UMESHBABU--
K. R. HARINATH--
K. R. BALAUBRAMANIAM,--
K. R. UMESHBABU--
K. R. HARINATH--
K. R. BALASUBRAMANIAM--
K. R. UMESHBABU--
K. R. HARINATH--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 271.88 cr
Cost incurredRs 13.44 cr
Spent of the estimate4.94%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 206.61 crRs 10.54 cr
Payment of taxesRs 37.79 crRs 2.16 lakh
On-site expenditure-Site OverheadRs 14.88 crRs 1.86 cr
Principal sum and interest payable to financial institutions-Scheduled BanksRs 9.00 crRs 89.99 lakh
On-site expenditure-Consultants FeesRs 3.60 crRs 3.23 lakh
On-site expenditure-Salaries of workers-Rs 8.07 lakh
Payment of cess-Rs 12,342
Payment of Premiums-Rs 14,006

Certifying professionals and partners4

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectV. NARASIMHAN
EngineerBalasubramaniam MN
EngineerH P Yogesh
Chartered AccountantR. Srinivasan

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed121

As listed on the registration, under the names the promoter filed them with; the newest 80 of 121 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/309/PR/230326/008545 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Brigade Lumina - Form 4 - Q2.pdf15 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Brigade Lumina - Form 5 - Q2.pdf15 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Brigade Lumina- Form 6 - Q2.pdf15 Oct 2026
Q2 2026-27 Water supply and sewage board15 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Oct 2026
Q2 2026-27 KSPCB- MOEF (Above 50 Acres)15 Oct 2026
Q2 2026-27 KPTCL- BESCOM15 Oct 2026
Q2 2026-27 Fire and Safety15 Oct 2026
Q2 2026-27 Airport Authority of India15 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Brigade Lumina - Form 4 - Q1.pdf15 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Brigade Lumina - Form 5 - Q1.pdf15 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Brigade Lumina - Form 6 - Q1.pdf15 Jul 2026
Q1 2026-27 Water supply and sewage board15 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Jul 2026
Q1 2026-27 KSPCB- MOEF (Above 50 Acres)15 Jul 2026
Q1 2026-27 KPTCL- BESCOM15 Jul 2026
Q1 2026-27 Fire and Safety15 Jul 2026
Q1 2026-27 Airport Authority of India15 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Brigade Lumina - Form 4 - Q4.pdf15 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Brigade Lumina - Form 5 - Q4.pdf15 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Brigade Lumina - Form 6 - Q4.pdf15 Apr 2026
Q4 2025-26 Water supply and sewage board15 Apr 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)15 Apr 2026
Q4 2025-26 KSPCB- MOEF (Above 50 Acres)15 Apr 2026
Q4 2025-26 KPTCL- BESCOM15 Apr 2026
Q4 2025-26 Fire and Safety15 Apr 2026
Q4 2025-26 Airport Authority of India15 Apr 2026
Agreement to SellFile: Lumina Agreement for Sale Updated.pdf23 Mar 2026
ADLR SketchFile: ADLR Sketch.jpg23 Mar 2026
KSPCB NOCFile: Brigade Lumina - KSPCB.pdf23 Mar 2026
Reply to the QueriesFile: Brigade Lumina - Reply to the Queries.pdf23 Mar 2026
Amenities Details DeclarationFile: Amenities Declaration.pdf23 Mar 2026
RTC, survey 38/2B-
Mutation, survey 38/2B-
Encumbrance Certificate, survey 38/2B-
Conversion/Alienation Order, survey 38/2B-
Sale/Title/Gift Deed, survey 38/2B-
JDA, survey 38/2B-
Khatha, survey 38/2B-
RTC, survey 38/2A-
Mutation, survey 38/2A-
Encumbrance Certificate, survey 38/2A-
Conversion/Alienation Order, survey 38/2A-
Sale/Title/Gift Deed, survey 38/2A-
JDA, survey 38/2A-
Khatha, survey 38/2A-
RTC, survey 46/2-
Mutation, survey 46/2-
Encumbrance Certificate, survey 46/2-
Conversion/Alienation Order, survey 46/2-
Sale/Title/Gift Deed, survey 46/2-
JDA, survey 46/2-
Khatha, survey 46/2-
Registration CertificateFile: Certificate of Incorporation - BEL copy.pdf-
Memorandum of AssociationFile: MOA and AOA - BEL.pdf-
Article of AssociationFile: MOA and AOA - BEL.pdf-
GST CertificateFile: GST - BEL - Bangalore.PDF-
Organization StructureFile: Organogram.pdf-
Certificate issued by CA Form 1File: Brigade Lumina - Form 1.pdf-
Certificate issued by Architect Form 2File: Brigade Lumina - Form 2.pdf-
Certificate issued by Engineer Form 3File: Brigade Lumina - Form 3.pdf-
Project Chartered Accountant-
Project Engineer-
Project Engineer-
Project Architect-
AffidavitFile: Brigade Lumina - No Litigation.pdf-
Balance Sheet 2024 - 2025File: Balance Sheet - 2024-25.pdf-
Balance Sheet 2023 - 2024File: Balance Sheet - 2023-24.pdf-
Balance Sheet 2022 - 2023File: Balance Sheet - 2022-23.pdf-
Audited Profit and Loss Statement 2024 - 2025File: Profit and Loss - 2024-25.pdf-
Audited Profit and Loss Statement 2023 - 2024File: Profit and Loss Account - 2023-24.pdf-
Audited Profit and Loss Statement 2022 - 2023File: Profit and Loss - 2022-23.pdf-
Income Tax Return Acknowledgement 2024 - 2025File: ITRV - 2024-25.pdf-
Income Tax Return Acknowledgement 2023 - 2024File: ITRV - 2023-24.pdf-
Income Tax Return Acknowledgement 2022 - 2023File: BEL_ITR ack_FY 21-22.pdf-
Director's Report 2024 - 2025File: Board's Report - 2024-25 - Compressed.pdf-
Director's Report 2023 - 2024File: Board Report - 2023-24.pdf-
Director's Report 2022 - 2023File: Directors Report - 2022-23.pdf-
Cash Flow Statement 2024 - 2025File: Cash Flow Statement - 2024-25.pdf-
Cash Flow Statement 2023 - 2024File: Cash Flow Statement - 2023-24.pdf-

How this compares with Bengaluru Urban

100%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Brigade Lumina on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmBrigade LuminaOther 11Dot size: filed unitsN

Filed coordinates, straight-line distance. 11 registered projects within 2 km.

Builder: Brigade Enterprises Ltd

Brigade Enterprises Ltd has 46 registrations on RERA Karnataka, including Brigade Oasis - Phase 1 and Brigade Atmosphere- Phase 1. Its filings declare 67 earlier projects, 41 of them declared completed. Litigation is declared on 10 of its registrations. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Brigade Lumina is delayed beyond 31 Dec 2030?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Brigade Lumina?

The registered promoter entity is Brigade Enterprises Ltd, a company as per the filing. Its CIN L85110KA1995PLC019126 and GSTIN 29AAACB7459F1ZI can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Brigade Lumina?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Brigade Lumina?

The professionals named in the filing: Architect: V. NARASIMHAN; Engineer: Balasubramaniam MN; Engineer: H P Yogesh; Chartered Accountant: R. Srinivasan. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Brigade Lumina?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Brigade Lumina. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Brigade Lumina to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.