BHUMI RESIDENCY
RG-GJ-66278 · RERA PR/GJ/VADODARA/VADODARA/Others/RAA02694/EX1/310721 · Last updated on GujRERA portal: 20 Jun 2022
Source: official GujRERA filing
Red flags
- Completion date moved by 12 months
- 1 extension taken
Clear
- Separate project account declared
Saved.
BHUMI RESIDENCY is a Residential/Group Housing project by SHREE VALLABH ENTERPRISE in Vadodara, Gujarat, registered with GujRERA as PR/GJ/VADODARA/VADODARA/Others/RAA02694/EX1/310721 on 18 May 2018. Possession is promised by 30 Jun 2022. The completion date has moved by 12 months from the original filing. 55 of the 87 units on this registration are recorded sold or booked, and 120 of 120 construction stages are filed complete.
At a glance
Project
- NameBHUMI RESIDENCY
- TypeResidential/Group Housing
- Location
- BHUMI RESIDENCY
- OPP. DREAM RESIDENCY
- MANEJA CROSSROAD
- MANEJA
- Maneja
- Vadodara
- 390013
- Pincode390013
- MapView location on Google Maps (as filed on RERA)
- RERA no.PR/GJ/VADODARA/VADODARA/Others/RAA02694/EX1/310721
- ReraGenie IDRG-GJ-66278
Builder
- NameSHREE VALLABH ENTERPRISE
- Entity typePARTNERSHIP FIRM
- Other registrations1 more →
Key dates
Key facts
Registration and timeline
- StatusValid until 30 Jun 2022
- Registered on18 May 2018
- Promised completion30 Jun 2022
- Revised completionRevised to 30 Jun 2022 (originally 30 Jun 2021)
- Buildings24 building records
- Documents filed61 files
Current status
Figures as on 20 Jun 2022, this project's latest GujRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Plot 2 | - | - | - | 1 | 0 | 1 |
| Plot 3 to 4 | - | - | - | 2 | 0 | 2 |
| Plot 5 to 9 | - | - | - | 5 | 0 | 5 |
| Plot 10 | - | - | - | 1 | 0 | 1 |
| Plot 11 | - | - | - | 1 | 0 | 1 |
| Plot 12 to 19 | - | - | - | 8 | 0 | 8 |
| Plot 20 | - | - | - | 1 | 0 | 1 |
| Plot 21 | - | - | - | 1 | 0 | 1 |
| Plot 22 to 31 | - | - | - | 10 | 0 | 10 |
| Plot 32 | - | - | - | 1 | 0 | 1 |
| Plot 33 | - | - | - | 1 | 0 | 1 |
| Plot 34 to 42 | - | - | - | 9 | 0 | 9 |
| Plot 43 | - | - | - | 1 | 0 | 1 |
| Plot 44 | - | - | - | 1 | 0 | 1 |
| Plot 45 to 55 | - | - | - | 11 | 0 | 11 |
| Plot 56 | - | - | - | 1 | 0 | 1 |
| Plot 57 | - | - | - | 1 | 0 | 1 |
| Plot 58 to 65 | - | - | - | 8 | 0 | 8 |
| Plot 66 to 67 | - | - | - | 2 | 0 | 2 |
| Plot 68 to 75 | - | - | - | 8 | 0 | 8 |
| Plot 76 | - | - | - | 1 | 0 | 1 |
| Plot 77 to 78 | - | - | - | 2 | 0 | 2 |
| Plot 79 to 87 | - | - | - | 9 | 0 | 9 |
| Plot 1 | - | - | - | 1 | 0 | 1 |
The full filing
Everything below is from the project's own GujRERA filing, free to read.
Construction progress by building20
As on 20 Jun 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection. The count above covers all 24 buildings; the table lists the first 20.
120 of 120 construction stages are filed complete across 24 buildings.
Plot 2100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | Not applicable |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | Not applicable |
Plot 3 to 4100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | Not applicable |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | Not applicable |
Plot 5 to 9100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | Not applicable |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | Not applicable |
Plot 10100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | Not applicable |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | Not applicable |
Plot 11100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | Not applicable |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | Not applicable |
Plot 12 to 19100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | Not applicable |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | Not applicable |
Plot 20100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | Not applicable |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | Not applicable |
Plot 21100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | Not applicable |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | Not applicable |
Plot 22 to 31100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | Not applicable |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | Not applicable |
Plot 32100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | Not applicable |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | Not applicable |
Plot 33100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | Not applicable |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | Not applicable |
Plot 34 to 42100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | Not applicable |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | Not applicable |
Plot 43100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | Not applicable |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | Not applicable |
Plot 44100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | Not applicable |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | Not applicable |
Plot 45 to 55100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | Not applicable |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | Not applicable |
Plot 56100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | Not applicable |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | Not applicable |
Plot 57100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | Not applicable |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | Not applicable |
Plot 58 to 65100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | Not applicable |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | Not applicable |
Plot 66 to 67100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | Not applicable |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | Not applicable |
Plot 68 to 75100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | Not applicable |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | Not applicable |
Progress on shared amenities19
As on 20 Jun 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal roads and footpaths | Yes | 100% |
| Water supply | Yes | 100% |
| Sewerage (chamber, lines, septic tank, STP) | Yes | 100% |
| Storm water drains | Yes | 100% |
| Landscaping and tree planting | Yes | 100% |
| Street lighting | Yes | 100% |
| Community buildings | Yes | 92% |
| Treatment and disposal of sewage and sullage water | Yes | 100% |
| Solid waste management and disposal | No | Not applicable |
| Water conservation, rain water harvesting | No | Not applicable |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Fire fighting | No | Not applicable |
| Drinking water facilities | No | Not applicable |
| Emergency evacuation | No | Not applicable |
| Use of renewable energy | No | Not applicable |
| Security | No | Not applicable |
| Letter box | Yes | 100% |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Plot 1 | NA | Rs 29.22 lakh | Rs 28.73 lakh |
| Plot 2 | NA | Rs 29.22 lakh | Rs 28.73 lakh |
| Plot 3 to 4 | NA | Rs 29.22 lakh | Rs 28.73 lakh |
| Plot 5 to 9 | NA | Rs 29.22 lakh | Rs 28.73 lakh |
| Plot 10 | NA | Rs 29.22 lakh | Rs 28.73 lakh |
| Plot 11 | NA | Rs 29.22 lakh | Rs 28.73 lakh |
| Plot 12 to 19 | NA | Rs 29.22 lakh | Rs 28.73 lakh |
| Plot 20 | NA | Rs 29.22 lakh | Rs 28.73 lakh |
| Plot 21 | NA | Rs 29.22 lakh | Rs 28.73 lakh |
| Plot 22 to 31 | NA | Rs 29.22 lakh | Rs 28.73 lakh |
| Plot 32 | NA | Rs 29.22 lakh | Rs 28.73 lakh |
| Plot 33 | NA | Rs 29.22 lakh | Rs 28.73 lakh |
Certifying professionals and partners1
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | NITIN S KAPADI |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Documents filed61
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VADODARA/VADODARA/Others/RAA02694/EX1/310721 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Accountant's certificate (Form 3) | 20 Jun 2022 |
| Architect's certificate (Form 1) | 18 Jun 2022 |
| Engineer's certificate (Form 2) | 18 Jun 2022 |
| Engineer's certificate annexure | 18 Jun 2022 |
| Site photograph, Plot 2 | 18 Jun 2022 |
| Site photograph, Plot 3 to 4 | 18 Jun 2022 |
| Site photograph, Plot 5 to 9 | 18 Jun 2022 |
| Site photograph, Plot 10 | 18 Jun 2022 |
| Site photograph, Plot 11 | 18 Jun 2022 |
| Site photograph, Plot 12 to 19 | 18 Jun 2022 |
| Site photograph, Plot 20 | 18 Jun 2022 |
| Site photograph, Plot 21 | 18 Jun 2022 |
| Site photograph, Plot 22 to 31 | 18 Jun 2022 |
| Site photograph, Plot 32 | 18 Jun 2022 |
| Site photograph, Plot 33 | 18 Jun 2022 |
| Site photograph, Plot 34 to 42 | 18 Jun 2022 |
| Site photograph, Plot 43 | 18 Jun 2022 |
| Site photograph, Plot 44 | 18 Jun 2022 |
| Site photograph, Plot 45 to 55 | 18 Jun 2022 |
| Site photograph, Plot 56 | 18 Jun 2022 |
| Site photograph, Plot 57 | 18 Jun 2022 |
| Site photograph, Plot 58 to 65 | 18 Jun 2022 |
| Site photograph, Plot 66 to 67 | 18 Jun 2022 |
| Site photograph, Plot 68 to 75 | 18 Jun 2022 |
| Site photograph, Plot 76 | 18 Jun 2022 |
| Site photograph, Plot 77 to 78 | 18 Jun 2022 |
| Site photograph, Plot 79 to 87 | 18 Jun 2022 |
| Site photograph, Plot 1 | 18 Jun 2022 |
| RERA registration certificate | 18 May 2018 |
| Proforma agreement for sale | - |
| Auditor's report (1 of 3) | - |
| Auditor's report (2 of 3) | - |
| Auditor's report (3 of 3) | - |
| Income tax return (1 of 3) | - |
| Income tax return (2 of 3) | - |
| Income tax return (3 of 3) | - |
| Project specific document | - |
| Directors' report (1 of 3) | - |
| Directors' report (2 of 3) | - |
| Directors' report (3 of 3) | - |
| Commencement certificate | - |
| Approved sanctioned plan | - |
| Approved layout plan | - |
| Agreement | - |
| Land location | - |
| Encumbrance certificate | - |
| Area development document | - |
| Proforma allotment letter | - |
| Brochure | - |
| Project related document | - |
| Declaration in Form B | - |
| Project photograph | - |
| Audited balance sheet (1 of 3) | - |
| Audited balance sheet (2 of 3) | - |
| Audited balance sheet (3 of 3) | - |
| Audited profit and loss statement (1 of 3) | - |
| Audited profit and loss statement (2 of 3) | - |
| Audited profit and loss statement (3 of 3) | - |
| Cash flow statement (1 of 3) | - |
| Cash flow statement (2 of 3) | - |
| Cash flow statement (3 of 3) | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Vadodara
Computed across the 2,900+ Vadodara projects on ReraGenie, from their own filings.
Keep BHUMI RESIDENCY on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Maneja2,900+ in Vadodara
Filed coordinates, straight-line distance. 46 registered projects within 2 km.
OMKAAR HEIGHTS
DEETYA CONSTRUCTION
CORNER POINT
MAHAVIR CORPORATION
BAKERI SWARA
BAKERI URBAN DEVELOPMENT PVT. LTD.
GOKUL DUPLEX
GOKUL DEVELOPERS
Aatmiya Heritage
Aatmiya Developers
KISHAN ICON
AMBICA CORPORATION
See every Vadodara project, with the district possession charts
Builder: SHREE VALLABH ENTERPRISE
SHREE VALLABH ENTERPRISE has 2 registrations on GujRERA, including BHUMI RESIDENCY and DEVGRAM INDUSTRIAL PARISAR. Read the full track record. See more projects on the Vadodara district page.
Frequently asked questions
What are my rights if BHUMI RESIDENCY is delayed beyond 30 Jun 2022?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.
How do I verify and contact the developer of BHUMI RESIDENCY?
The registered promoter entity is SHREE VALLABH ENTERPRISE, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.
Is my payment protected in BHUMI RESIDENCY?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at BHUMI RESIDENCY?
The professionals named in the filing: Architect: NITIN S KAPADI. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in BHUMI RESIDENCY?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.