Home / Browse projects / Anand, Gujarat / BHAILALBHAI COMMERCIAL BUILDING

Valid until 28 Feb 2025 Commercial project

BHAILALBHAI COMMERCIAL BUILDING

By KRISHNA DEVELOPERS

RG-GJ-43065 · RERA PR/GJ/ANAND/ANAND/Others/CAA08677/280621 · Last updated on GujRERA portal: 7 Apr 2022

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Feb 2025Possession promisedno revision filed
0 of 8Construction stages donefurthest along: Excavation, 50%
51 of 59Units unsoldnot recorded sold or booked
Jump to the 41 documents Report an error

BHAILALBHAI COMMERCIAL BUILDING is a Commercial project by KRISHNA DEVELOPERS in Anand, Gujarat, registered with GujRERA as PR/GJ/ANAND/ANAND/Others/CAA08677/280621 on 28 Jun 2021. Possession is promised by 28 Feb 2025. 8 of the 59 units on this registration are recorded sold or booked, and 0 of 8 construction stages are filed complete.

At a glance

Project

  • NameBHAILALBHAI COMMERCIAL BUILDING
  • TypeCommercial
  • Location
    • OPP SHREE KRISHNA HOSPITAL
    • ANAND SOJITRA ROAD
    • Anand
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/ANAND/ANAND/Others/CAA08677/280621
  • ReraGenie IDRG-GJ-43065

Builder

  • NameKRISHNA DEVELOPERS
  • Entity typePARTNERSHIP FIRM
  • Other registrations29 more →

Key dates

this monthRegisteredJun 2021PromisedFeb 2025

Key facts

Registration and timeline

  • StatusValid until 28 Feb 2025
  • Registered on28 Jun 2021
  • Promised completion28 Feb 2025
  • Revised completionNone
  • Buildings1 building record
  • Documents filed41 files

Current status

14%8 of 59 units booked
22.5%Of the estimated cost spent so far

Figures as on 7 Apr 2022, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A+B---05959

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 7 Apr 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 8 construction stages are filed complete. The stage furthest along is Excavation, at 50%.

A+B: 17% average across the applicable activities

ActivityProgress
Excavation50%
Podiums (if any)Not applicable
Plinth50%
Stilt FloorNot applicable
Slabs of Super Structure35%
Internal walls, internal plaster, floorings, doors and windows within flats3%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%

Progress on shared amenities19

As on 7 Apr 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes0%
Water supplyYes0%
Sewerage (chamber, lines, septic tank, STP)Yes0%
Storm water drainsYes0%
Landscaping and tree plantingYes0%
Street lightingNoNot applicable
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area869 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 4.89 cr
Cost incurredRs 1.10 cr
Spent of the estimate22.52%
BuildingWingEstimatedIncurred
A+BNARs 4.89 crRs 1.10 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectJAYRAJ VAGHELA
EngineerVIKASH PRAJAPATI

Documents filed41

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/ANAND/ANAND/Others/CAA08677/280621 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)7 Apr 2022
Engineer's certificate (Form 2)7 Apr 2022
Engineer's certificate annexure7 Apr 2022
Accountant's certificate (Form 3)7 Apr 2022
Site photograph, A+B7 Apr 2022
RERA registration certificate28 Jun 2021
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Anand

14%of this project is bookeddistrict median 57%
17%of Anand projects moved their completion datethis one has not

Computed across the 310+ Anand projects on ReraGenie, from their own filings.

Keep BHAILALBHAI COMMERCIAL BUILDING on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Anand310+ in Anand

2 kmBHAILALBHAI COMMERCIAL BOther 48Dot size: filed unitsN

Filed coordinates, straight-line distance. 48 registered projects within 2 km.

Builder: KRISHNA DEVELOPERS

KRISHNA DEVELOPERS has 30 registrations on GujRERA, including SHRIMAD AFFORD and THE KRISHNA CITY. Read the full track record. See more projects on the Anand district page.

Frequently asked questions

What are my rights if BHAILALBHAI COMMERCIAL BUILDING is delayed beyond 28 Feb 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of BHAILALBHAI COMMERCIAL BUILDING?

The registered promoter entity is KRISHNA DEVELOPERS, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in BHAILALBHAI COMMERCIAL BUILDING?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at BHAILALBHAI COMMERCIAL BUILDING?

The professionals named in the filing: Architect: JAYRAJ VAGHELA; Engineer: VIKASH PRAJAPATI. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in BHAILALBHAI COMMERCIAL BUILDING?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About BHAILALBHAI COMMERCIAL BUILDING. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save BHAILALBHAI COMMERCIAL BUILDING to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.