Home / Browse projects / Kalaburagi, Karnataka / Bee Nest Residency
Bee Nest Residency
By VHF Builders
RG-KA-56898 · RERA PRM/KA/RERA/1263/419/PR/210219/003914 · Last updated on RERA Karnataka portal: 12 Dec 2020
Source: official RERA Karnataka filing
Red flags
- No red flags in this filing
Clear
- No complaints on record
- Completion date never moved
- Separate project account declared
Saved.
Bee Nest Residency is a Residential/Group Housing project by VHF Builders in Kalaburagi, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1263/419/PR/210219/003914 on 19 Feb 2021. Possession is promised by 31 Oct 2022.
At a glance
Project
- NameBee Nest Residency
- TypeResidential/Group Housing
- Location
- Kalaburagi
- PincodeNot stated
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1263/419/PR/210219/003914
- ReraGenie IDRG-KA-56898
Builder
- NameVHF Builders
- Entity typeProprietorship Firm
- Authorized SignatoryMohammad Vilayath Ali
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on19 Feb 2021
- Promised completion31 Oct 2022
- Revised completionNone
- Buildings1 building record
- Documents filed78 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| BEE NEST RESIDENCY | - | - | - | 18 | 0 | 18 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 12 Dec 2020, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
Building:
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | - |
| Foundation footing work | - |
| Retaining wall (All types) | - |
| Plinth level Beam | - |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | - |
| RCC or MS Framed structure | - |
| Masonry construction: Bricks, Concrete blocks etc | - |
| Plastering inside , outside & Ceiling | - |
| Joinery: Doors, Windows, Ventilators etc | - |
| Basic work of Water supply, Sanitary and Electrification | - |
| Dadoing, Skirting, Flooring, Tiles work (All types) | - |
| Railing and Grill fixing | - |
| Electrification, Water supply and Sanitary Finishing | - |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | - |
| Fire prevention and fire fighting fitting and fixture with network | - |
| Weather Proof work(tile,concrete) | - |
| Painting | - |
| Elevation work | - |
| Internal and External work including landscapes as per santioned drawings | - |
Progress on shared amenities41
As on 12 Dec 2020, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | - |
| Internal Roads & Footpaths | Yes | - |
| Sewage and Drainage System | Yes | - |
| Parks & Tree planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Provision for community buildings and for treatment and disposal of sewage and sullage water | Yes | - |
| Solid waste management and disposal | Yes | - |
| Water conservation | No | Not applicable |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Education/Health/Other public amenities | No | Not applicable |
| Electricity supply transformer and substation | Yes | - |
| Emergency Evacuation services | No | Not applicable |
| Storm water drains | No | Not applicable |
| Use of renewable energy | No | Not applicable |
| Water conservation/rain water harvesting/recharge of ground water | Yes | - |
| Electricity | Yes | - |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | - |
| Club House | No | Not applicable |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | No | Not applicable |
| Swimming Pool | No | Not applicable |
| Gym | No | Not applicable |
| Parks | No | Not applicable |
| Power Backup | No | Not applicable |
| Gas | No | Not applicable |
| Water and Sanitation | Yes | - |
| Air Conditioning And incerntion | No | Not applicable |
| Staircases | Yes | - |
| Lifts | Yes | - |
| Staircases and Lift lobbies, corridor,lobbies, corridor | Yes | - |
| Fire escapes | No | Not applicable |
| Common entrance and exit for the building / common portico/foyer/verandah | Yes | - |
| Basement | Yes | - |
| Terrace | Yes | - |
| Outer Wall | No | Not applicable |
| Open parking areas and common storage spaces | Yes | - |
| Provision for lodging of management staff and security staff | Yes | - |
| Water conservation and renewable energy | No | Not applicable |
Land and ownership1
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Mohammad Vilayath Ali | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed78
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1263/419/PR/210219/003914 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Bank Account StatementFile: Account Statement.pdf | 12 Dec 2020 |
| Encumbrance CertificateFile: EC Gift Deed Mateen Z.pdf | 12 Dec 2020 |
| Encumbrance CertificateFile: Ec Shaheen Begum.pdf | 12 Dec 2020 |
| Encumbrance CertificateFile: EC FORM 15 (1).pdf | 12 Dec 2020 |
| Bank Account as per RERA CircularFile: Bank Account.pdf | 5 Dec 2020 |
| Visible PlanFile: Bee Nest Approved Plan.pdf | 5 Dec 2020 |
| Financial Statement for the year 2018-19 and 2019-20File: Letter FOR UDIN.pdf | 5 Dec 2020 |
| Four individual Title Documents for an extent 534 square meters (Gift Deed and Three Sale Deeds)File: Title Deeds for 534 sq. mtrs.pdf | 5 Dec 2020 |
| Encumbrance CertificateFile: EC FORM 15 (1).pdf | 5 Dec 2020 |
| CertificateFile: VHF MUNCIPAL LICENCE.pdf | - |
| MAHANAGAR PALIKA Permission Letter From BEE NEST-min | - |
| PLAN APPROVED COPY -min | - |
| PLAN APPROVED COPY -min | - |
| Proforma Allotment letter | - |
| Model Form of Agreement to Sale-converted (4) | - |
| Sale Deed from Hissam | - |
| PLAN APPROVED COPY -min | - |
| PLAN APPROVED COPY -min | - |
| Proforma Allotment letter | - |
| VHF RERA Broucher Letter | - |
| VHF RERA Specifications | - |
| E C till 17 11 2020 | - |
| Affidivate Undersection 3 of 1-min | - |
| letter of Joint Affidivate-compressed | - |
| Khata Certificate-min | - |
| Letter for D A and Power of Attorney-compressed | - |
| NA order Copy of Sy 27 Badepur | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Letter for verious NOC | - |
| Letter for verious NOC | - |
| Letter for verious NOC | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Letter for verious NOC | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| PLAN APPROVED COPY -min | - |
| PLAN APPROVED COPY -min | - |
| letter of change of land-compressed | - |
| Unnamed document | - |
| Balance Sheet 2019 - 2020File: Balalce sheet 2019-2020-min.pdf | - |
| Balance Sheet 2018 - 2019File: Balalce sheet 2018-2019-min.pdf | - |
| Balance Sheet 2017 - 2018File: Balalce sheet 2017-2018-min.pdf | - |
| Audited Profit and Loss Statement 2019 - 2020File: Profit Loss Account 2019-2020-min.pdf | - |
| Audited Profit and Loss Statement 2018 - 2019File: Profit Loss Account 2018-2019-min.pdf | - |
| Audited Profit and Loss Statement 2017 - 2018File: Prifir Loss account 2017-2018-min.pdf | - |
| Director's Report 2019 - 2020File: Letter for Director report and auditor report-compressed (1).pdf | - |
| Director's Report 2018 - 2019File: Letter for Director report and auditor report-compressed (1).pdf | - |
| Director's Report 2017 - 2018File: Letter for Director report and auditor report-compressed (1).pdf | - |
| Cash Flow Statement 2019 - 2020File: Cash flow statement-min.pdf | - |
| Cash Flow Statement 2018 - 2019File: Cash flow statement-min.pdf | - |
| Auditor's Report 2019 - 2020File: Letter for Director report and auditor report-compressed (1).pdf | - |
| Auditor's Report 2018 - 2019File: Letter for Director report and auditor report-compressed (1).pdf | - |
| Auditor's Report 2017 - 2018File: Letter for Director report and auditor report-compressed (1).pdf | - |
| Income Tax Return Acknowledgement 2019 - 2020File: ITR acknowledgment 2019-2020-min.pdf | - |
| Income Tax Return Acknowledgement 2018 - 2019File: Balalce sheet 2018-2019-min.pdf | - |
| Income Tax Return Acknowledgement 2017 - 2018File: Balalce sheet 2017-2018-min.pdf | - |
| Affidivate cum Decleration-compressed | - |
| Prospectus/BrochureFile: Brochure BeeNest.jpeg | - |
| Advertisement Copy 1File: Advertisment BeeNest.jpeg | - |
| Tower Excel SheetFile: PRM_KA_RERA_1263_419_PR_210219_003914.xlsx | - |
| Occupancy CertificateFile: Occupancy Certificate Issued By the Planning Authority.pdf | - |
| Architect certificate for having completed the work(in format no 5)File: Architect certificate for having completed the work in format no 5.pdf | - |
| Chartered Accountant certificate for having completed the work(in format no 4)File: Chartered Accountant certificate for having completed the work in format no 4.pdf | - |
| Affidavit cum declaration from promoter for having completed the project as per specification and as per adverFile: Affidavit Cum Decleration for Complition.pdf | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Kalaburagi
Computed across the 210+ Kalaburagi projects on ReraGenie, from their own filings.
Keep Bee Nest Residency on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Kalaburagi210+ in Kalaburagi
Filed coordinates, straight-line distance. 6 registered projects within 2 km.
Kashi Kamal Gruh Yojana
M G Associates
BHARAT PRIDE PARK WING A & B
Bharat Dall and Oil Industries
BHARAT PRIDE PARK WING C & D
BHARAT DALL AND OIL INDUSTRIES
Kashikamal Phase 2
M.G. ASSOCIATES
G.V RAGHOJI ARCADE
M/s. R R BUILDERS AND DEVELOPERS
English County
Mahalaxmi Builder And developers
See every Kalaburagi project, with the district possession charts
Builder: VHF Builders
VHF Builders has 1 registration on RERA Karnataka, including Bee Nest Residency. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Kalaburagi district page.
Frequently asked questions
What are my rights if Bee Nest Residency is delayed beyond 31 Oct 2022?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of Bee Nest Residency?
The registered promoter entity is VHF Builders, a proprietorship firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in Bee Nest Residency?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
What should I check before booking in Bee Nest Residency?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback