- Completion date moved by 9 months
- 1 extension taken
Clear
- No complaints on record
- Separate project account declared
Saved.
Avanti Nagar is a Plotted Development project by Bhaskar Hegde Kageri in Uttara Kannada, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1274/352/PR/190921/002901 on 21 Sep 2019. Possession is promised by 6 Dec 2024. The completion date has moved by 9 months from the original filing.
At a glance
Project
- NameAvanti Nagar
- TypePlotted Development
- Location
- Sirsi
- Uttara Kannada
- PincodeNot stated
- RERA no.PRM/KA/RERA/1274/352/PR/190921/002901
- ReraGenie IDRG-KA-42183
Builder
- NameBhaskar Hegde Kageri
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on21 Sep 2019
- Promised completion6 Dec 2024
- Revised completionRevised to 6 Dec 2024 (originally 6 Mar 2024)
- BuildingsNot stated in filing
- Documents filed65 files
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
No reason recorded in the filing
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed65
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1274/352/PR/190921/002901 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| IMG_0001 | - |
| Town planning approval | - |
| map | - |
| IMG_0001 | - |
| IMG_0001 | - |
| Sale Deed & RTC | - |
| IMG_0001 | - |
| Area Development Plan | - |
| IMG_0001 | - |
| IMG_0001 | - |
| NA order | - |
| Project Specifications | - |
| EC | - |
| Bond | - |
| JBA Declaration | - |
| MUTATION ENTRY | - |
| IMG_0001 | - |
| NA order | - |
| NA order | - |
| PollutionControl Board NOC | - |
| Hescom NOC | - |
| PollutionControl Board NOC | - |
| IMG_0001 | - |
| IMG_0001 | - |
| IMG_0001 | - |
| matter | - |
| Balance Sheet 2017 - 2018File: Balance Sheet 2019.pdf | - |
| Balance Sheet 2016 - 2017File: Balance Sheet 2018.pdf | - |
| Balance Sheet 2015 - 2016File: Balance Sheet 2017.pdf | - |
| Audited Profit and Loss Statement 2017 - 2018File: Self declaration.pdf | - |
| Audited Profit and Loss Statement 2016 - 2017File: Self declaration.pdf | - |
| Audited Profit and Loss Statement 2015 - 2016File: Self declaration.pdf | - |
| Director's Report 2017 - 2018File: Self declaration.pdf | - |
| Director's Report 2016 - 2017File: Self declaration.pdf | - |
| Director's Report 2015 - 2016File: Self declaration.pdf | - |
| Cash Flow Statement 2017 - 2018File: Self declaration.pdf | - |
| Cash Flow Statement 2016 - 2017File: Self declaration.pdf | - |
| Auditor's Report 2017 - 2018File: Self declaration.pdf | - |
| Auditor's Report 2016 - 2017File: Self declaration.pdf | - |
| Auditor's Report 2015 - 2016File: Self declaration.pdf | - |
| Income Tax Return Acknowledgement 2017 - 2018File: IT Return 19-20.pdf | - |
| Income Tax Return Acknowledgement 2016 - 2017File: IT Return 18-19.pdf | - |
| Income Tax Return Acknowledgement 2015 - 2016File: I T Declaration 2017-18.pdf | - |
| Form-B | - |
| Prospectus/BrochureFile: Avanti Nagar Broucher.docx | - |
| Advertisement Copy 1File: Avanti Nagar Advert.docx | - |
| Plot Excel SheetFile: Site Rera.xlsx | - |
| Loan raised documentFile: Form 4 C CA.pdf | - |
| Final plan technical sanction LetterFile: Area Development Plan_1565769591847.pdf | - |
| Final layout plan sanctionedFile: Area Development Plan_1565769591847.pdf | - |
| Completion CertificateFile: 3_Completion Certificate.pdf | - |
| Site release order Copies(1st,2nd phase and final release order)File: 4 Reeleas Order.pdf | - |
| Relinquishment deed executed handed over detailsFile: 5 Relinquishment.pdf | - |
| Certificate issued by P.W.D/ Panchayath Raj/Urban Local Bodies for completion of RoadFile: 6 Road & Drain.jpeg | - |
| Certificate issued by the Karnataka Urban Water supplyFile: 7 Watter supply.jpeg | - |
| Certificate issued by the concerned power supply(ESCOM'S)File: 10KSBPC Consent.jpeg | - |
| Certificate issued by Horticulture/Forest departmentFile: 4 Reeleas Order.pdf | - |
| Certificate issued by KSPCB, consent for operation of STP plantFile: 10KSBPC Consent.jpeg | - |
| Whether the structures,civic amenities and other services handed over to local authority for maintenanceFile: 3_Completion Certificate.pdf | - |
| Brief description of Water supply and Underground drainage worksFile: Discpr.pdf | - |
| Whether the transformer has been erected within layout and copy of power sanctioned to the layout issued by ESFile: 8 Hescom completion.jpeg | - |
| Chartered Accountant Certificate (Form-4)File: Form-4-small.pdf | - |
| Architect's Certificate (Form-5)File: AR.pdf | - |
| Engineer's Certificate (Form-6)File: CE.pdf | - |
| Affidavit from Promoter for completing project as per advertisement published in brochure and as per project sFile: Affadavit.pdf | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Uttara Kannada
Computed across the 100+ Uttara Kannada projects on ReraGenie, from their own filings.
Keep Avanti Nagar on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Uttara Kannada100+ in Uttara Kannada
Signature Apartment
VASANT CONSTRUCTIONS PRIVATE LIMITED
Nisarga Vastu City
MUNAF MOHAMMED SAB LANDAKANALLI
AL MARJAAN RESIDENCY
BRIGHT DEVELOPERS
Parijaat
Padmanabh Realtors
ASIYA BUSINESS PARK
ASIYA DEVELOPERS
ABHIMAN RESIDENCY AND COMMERCIAL COMPLEX
KALLUR DEVELOPERS
See every Uttara Kannada project, with the district possession charts
Builder: Bhaskar Hegde Kageri
Bhaskar Hegde Kageri has 1 registration on RERA Karnataka, including Avanti Nagar. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Uttara Kannada district page.
Frequently asked questions
What are my rights if Avanti Nagar is delayed beyond 6 Dec 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of Avanti Nagar?
The registered promoter entity is Bhaskar Hegde Kageri. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in Avanti Nagar?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
What should I check before booking in Avanti Nagar?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback