Home / Browse projects / Anand, Gujarat / ASTITVA SANKUL

Valid until 30 Nov 2026 Residential/Group Housing project

ASTITVA SANKUL

By DINESHBHAI ASHABHAI PATEL PROPRIETOR OF ASTITVA SANKUL

RG-GJ-99687 · RERA PR/GJ/ANAND/ANAND/Others/RAA07809/EX1/EX3/061026/301126 · Last updated on GujRERA portal: 25 Sep 2026

Source: official GujRERA filing

Red flags

  • Completion date moved by 40 months
  • 3 extensions taken

Clear

  • Nothing verified clear yet
Nov 2026Possession promisedmoved 40 months from the original
14 of 27Construction stages doneacross 3 buildings; furthest along: Internal walls, 80%
16 of 35Units unsoldnot recorded sold or booked
Jump to the 43 documents Report an error

ASTITVA SANKUL is a Residential/Group Housing project by DINESHBHAI ASHABHAI PATEL PROPRIETOR OF ASTITVA SANKUL in Anand, Gujarat, registered with GujRERA as PR/GJ/ANAND/ANAND/Others/RAA07809/EX1/EX3/061026/301126 on 21 Dec 2020. Possession is promised by 30 Nov 2026. The completion date has moved by 40 months from the original filing. 19 of the 35 units on this registration are recorded sold or booked, and 14 of 27 construction stages are filed complete.

At a glance

Project

  • NameASTITVA SANKUL
  • TypeResidential/Group Housing
  • Location
    • B/H KHODIYAR MANDIR
    • KARAMSAD
    • Karamsad
    • Anand
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/ANAND/ANAND/Others/RAA07809/EX1/EX3/061026/301126
  • ReraGenie IDRG-GJ-99687

Builder

  • NameDINESHBHAI ASHABHAI PATEL PROPRIETOR OF ASTITVA SANKUL
  • Entity typeIndividual/Propritorship

Key dates

this monthRegisteredDec 2020First promiseJul 2023Revised toNov 2026

Key facts

Registration and timeline

  • StatusValid until 30 Nov 2026
  • Registered on21 Dec 2020
  • Promised completion30 Nov 2026
  • Revised completionRevised to 30 Nov 2026 (originally 31 Jul 2023)
  • Buildings3 building records
  • Documents filed43 files

Current status

54%19 of 35 units booked
90.3%Of the estimated cost spent so far

Figures as on 25 Sep 2026, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TYPE A---10010
TYPE B---18018
TYPE C---707

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building3

As on 25 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

14 of 27 construction stages are filed complete across 3 buildings. The stage furthest along is Internal walls, at 80%.

TYPE A78%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats80%
Sanitary fittings within the flats80%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing80%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing80%
TYPE B89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
TYPE C75%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats75%
Sanitary fittings within the flats75%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks75%
External plumbing and external plaster, elevation, completion of terraces with waterproofing75%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing75%

Progress on shared amenities19

As on 25 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsNoNot applicable
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsYes100%
Treatment and disposal of sewage and sullage waterYes100%
Solid waste management and disposalYes100%
Water conservation, rain water harvestingNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area6,272 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 10.56 cr
Cost incurredRs 9.54 cr
Spent of the estimate90.33%
BuildingWingEstimatedIncurred
TYPE ANARs 3.52 crRs 3.06 cr
TYPE BNARs 3.52 crRs 3.52 cr
TYPE CNARs 3.52 crRs 2.96 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPRIYANKA B GAJJAR
EngineerMITESH H DAVE

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/ANAND/ANAND/Others/RAA07809/EX1/300324/310724Applied Jul 2023; approved Mar 2024
PR/GJ/ANAND/ANAND/Others/RAA07809/EX1/EX2/140725/310725Applied Aug 2024; approved Jul 2025
PR/GJ/ANAND/ANAND/Others/RAA07809/EX1/EX3/061026/301126Applied Oct 2025; approved Oct 2026

Documents filed43

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/ANAND/ANAND/Others/RAA07809/EX1/EX3/061026/301126 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)25 Sep 2026
Engineer's certificate (Form 2)25 Sep 2026
Engineer's certificate annexure25 Sep 2026
Accountant's certificate (Form 3)25 Sep 2026
Site photograph, TYPE A25 Sep 2026
Site photograph, TYPE B25 Sep 2026
Site photograph, TYPE C25 Sep 2026
RERA registration certificate21 Dec 2020
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Anand

54%of this project is bookeddistrict median 57%
17%of Anand projects moved their completion datethis one moved by 40 months

Computed across the 310+ Anand projects on ReraGenie, from their own filings.

Keep ASTITVA SANKUL on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Karamsad310+ in Anand

2 kmASTITVA SANKULOther 83Dot size: filed unitsN

Filed coordinates, straight-line distance. 83 registered projects within 2 km.

Builder: DINESHBHAI ASHABHAI PATEL PROPRIETOR OF ASTITVA SANKUL

DINESHBHAI ASHABHAI PATEL PROPRIETOR OF ASTITVA SANKUL has 1 registration on GujRERA, including ASTITVA SANKUL. Read the full track record. See more projects on the Anand district page.

Frequently asked questions

What are my rights if ASTITVA SANKUL is delayed beyond 30 Nov 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of ASTITVA SANKUL?

The registered promoter entity is DINESHBHAI ASHABHAI PATEL PROPRIETOR OF ASTITVA SANKUL, an individual/propritorship as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in ASTITVA SANKUL?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at ASTITVA SANKUL?

The professionals named in the filing: Architect: PRIYANKA B GAJJAR; Engineer: MITESH H DAVE. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ASTITVA SANKUL?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ASTITVA SANKUL. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ASTITVA SANKUL to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.