Home / Browse projects / Bengaluru Urban, Karnataka / Assetz Trees & Tandem -Tower B
Assetz Trees & Tandem -Tower B
By Infraedge Management Services Pvt Ltd
RG-KA-68516 · RERA PRM/KA/RERA/1251/308/PR/280325/007636
Source: official RERA Karnataka filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- Completion date never moved
Saved.
Assetz Trees & Tandem -Tower B is a Residential/Group Housing project by Infraedge Management Services Pvt Ltd in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/308/PR/280325/007636 on 28 Mar 2025. Possession is promised by 31 Aug 2029.
At a glance
Project
- NameAssetz Trees & Tandem -Tower B
- TypeResidential/Group Housing
- Location
- Anekal
- Bengaluru Urban
- 560099
- Pincode560099
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1251/308/PR/280325/007636
- ReraGenie IDRG-KA-68516
Builder
- NameInfraedge Management Services Pvt Ltd
- Entity typeCompany
- CINU74900KA2014PTC077898
- GSTIN29AADCI7236G1ZF
- Authorized SignatoryPankaj Kumar Bajaj
- CeoAkshay Kishore Dewani
- DirectorsPankaj Kumar Bajaj, Sanjay Sudhakar Torgal
- Project HeadNandakumar P S
- Other registrations1 more →
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on28 Mar 2025
- Promised completion31 Aug 2029
- Revised completionNone
- Buildings1 building record
- Documents filed47 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| TOWER-B | - | - | - | 182 | 0 | 182 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
Building:
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | - |
| Foundation footing work | - |
| Upto Plinth Level | - |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | - |
| Retaining wall (All types) | - |
| RCC or MS Framed structure | - |
| Masonry Construction | - |
| Plastering inside , outside & Ceiling | - |
| Joinery: Doors, Windows, Ventilators etc | - |
| Basic work of Water supply, Sanitary and Electrification | - |
| Dadoing, Skirting, Flooring, Tiles work (All types) | - |
| Railing and Grill fixing | - |
| Electrification, Water supply and Sanitary Finishing | - |
| Painting | - |
| Fire prevention and fire fighting fitting and fixture with network | - |
| Weather Proof work(tile,concrete) | - |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Elevation work | - |
| Internal and External work including landscapes as per sanctioned drawings | - |
Progress on shared amenities40
Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | - |
| Sewage and Drainage System | Yes | - |
| Water conservation/rain water harvesting/recharge of ground water | Yes | - |
| Energy management | Yes | - |
| Fire protection and fire safety requirements | Yes | - |
| Solid waste management and disposal | Yes | - |
| Emergency Evacuation services | Yes | - |
| Internal Roads & Footpaths | Yes | - |
| Electricity supply transformer and substation | Yes | - |
| Storm water drains | Yes | - |
| Use of renewable energy | No | Not applicable |
| Sewage Treatment Plant (STP) | Yes | - |
| Parks & Tree planting | Yes | - |
| Street Lighting | Yes | - |
| Electricity | Yes | - |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | - |
| Club House | Yes | - |
| Community Hall | Yes | - |
| Outdoor Sports facility | Yes | - |
| Indoor Sports facility | Yes | - |
| Swimming Pool | Yes | - |
| Gym | Yes | - |
| Parks | Yes | - |
| Power Backup | Yes | - |
| Piped Gas | No | Not applicable |
| Water and Sanitation | Yes | - |
| Air Conditioning | Yes | - |
| Staircases | Yes | - |
| Lifts | Yes | - |
| Corridor/Lobbies | Yes | - |
| Fire escapes | Yes | - |
| Common entrance and exit for the building/common portico/foyer/verandah | Yes | - |
| Basement | Yes | - |
| Terrace | Yes | - |
| Outer Wall | Yes | - |
| Open parking areas | Yes | - |
| Provision for lodging of management staff and security staff | Yes | - |
| Water conservation and renewable energy | Yes | - |
| Common storage spaces | No | Not applicable |
Land and ownership5
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Satish Kumar Dalmiya | - | - |
| Satish Kumar Dalmiya | - | - |
| Satish Kumar Dalmiya | - | - |
| Satish Kumar Dalmiya | - | - |
| Satish Kumar Dalmiya | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 151.22 cr | - |
| On-site expenditure-Site Overhead | Rs 11.27 cr | - |
| Approval | Rs 11.14 cr | - |
| Principal sum and interest payable to financial institutions-Non Banking financial institution (NBFC) | Rs 8.84 cr | - |
| On-site expenditure-Consultants Fees | Rs 2.16 cr | - |
Certifying professionals and partners3
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | SANDEEP RAJENDRAN |
| Engineer | B E Pruthviraja |
| Chartered Accountant | Y S Shetty & Company |
Documents filed47
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/308/PR/280325/007636 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| RTC, survey Sy No. 29/3 | - |
| Mutation, survey Sy No. 29/3 | - |
| Encumbrance Certificate, survey Sy No. 29/3 | - |
| Conversion/Alienation Order, survey Sy No. 29/3 | - |
| Sale/Title/Gift Deed, survey Sy No. 29/3 | - |
| JDA, survey Sy No. 29/3 | - |
| Khatha, survey Sy No. 29/3 | - |
| RTC, survey Sy No. 31/1 | - |
| Mutation, survey Sy No. 31/1 | - |
| Encumbrance Certificate, survey Sy No. 31/1 | - |
| Conversion/Alienation Order, survey Sy No. 31/1 | - |
| Sale/Title/Gift Deed, survey Sy No. 31/1 | - |
| JDA, survey Sy No. 31/1 | - |
| Khatha, survey Sy No. 31/1 | - |
| RTC, survey Sy No.31/2 | - |
| Mutation, survey Sy No.31/2 | - |
| Encumbrance Certificate, survey Sy No.31/2 | - |
| Conversion/Alienation Order, survey Sy No.31/2 | - |
| Sale/Title/Gift Deed, survey Sy No.31/2 | - |
| JDA, survey Sy No.31/2 | - |
| Khatha, survey Sy No.31/2 | - |
| RTC, survey 32/1 | - |
| Mutation, survey 32/1 | - |
| Encumbrance Certificate, survey 32/1 | - |
| Conversion/Alienation Order, survey 32/1 | - |
| Sale/Title/Gift Deed, survey 32/1 | - |
| JDA, survey 32/1 | - |
| Khatha, survey 32/1 | - |
| RTC, survey 32/2 | - |
| Mutation, survey 32/2 | - |
| Encumbrance Certificate, survey 32/2 | - |
| Conversion/Alienation Order, survey 32/2 | - |
| Sale/Title/Gift Deed, survey 32/2 | - |
| JDA, survey 32/2 | - |
| Khatha, survey 32/2 | - |
| Registration CertificateFile: Annexure 1-Certificate of Incorporation.PDF | - |
| Memorandum of AssociationFile: Annexure 15- Articles of Association.pdf | - |
| Article of AssociationFile: Annexure 16-MOM.PDF | - |
| GST CertificateFile: Annexure 3-GST Certificate.pdf | - |
| Organization StructureFile: Annexure 14-Org Structure.pdf | - |
| Certificate issued by CA Form 1File: Assetz Trees & Tandem.pdf | - |
| Certificate issued by Architect Form 2File: Assetz Trees & Tandem.pdf | - |
| Certificate issued by Engineer Form 3File: Assetz Trees & Tandem.pdf | - |
| Project Chartered Accountant | - |
| Project Engineer | - |
| Project Architect | - |
| AffidavitFile: Annexure 49-Non Litigation affidavit.pdf | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Urban
Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.
Keep Assetz Trees & Tandem -Tower B on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Urban4,100+ in Bengaluru Urban
Filed coordinates, straight-line distance. 23 registered projects within 2 km.
Adarsh Welkin Park Phase 2
Akarshak Realty Private Limited
Adarsh Welkin Park Phase 1
Akarshak Realty Private Limited
Nambiar District 25 Phase 1
Nambiar EnsembleResidential Projects LLP
CASAGRAND VIVACITY
CASA GRANDE GARDEN CITY BUILDERS PVT LTD
Mahendra Solterra Aarya Phase-2
Mahendra Homes Private Limited
SIGNATURE SPLENDOR
SIGNATURE DWELLINGS PRIVATE LIMITED
See every Bengaluru Urban project, with the district possession charts
Builder: Infraedge Management Services Pvt Ltd
Infraedge Management Services Pvt Ltd has 2 registrations on RERA Karnataka, including Assetz Trees & Tandem -Tower A and Assetz Trees & Tandem -Tower B. Its filings disclose no earlier RERA Karnataka projects. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Bengaluru Urban district page.
Frequently asked questions
What are my rights if Assetz Trees & Tandem -Tower B is delayed beyond 31 Aug 2029?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of Assetz Trees & Tandem -Tower B?
The registered promoter entity is Infraedge Management Services Pvt Ltd, a company as per the filing. Its CIN U74900KA2014PTC077898 and GSTIN 29AADCI7236G1ZF can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in Assetz Trees & Tandem -Tower B?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at Assetz Trees & Tandem -Tower B?
The professionals named in the filing: Architect: SANDEEP RAJENDRAN; Engineer: B E Pruthviraja; Chartered Accountant: Y S Shetty & Company. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Assetz Trees & Tandem -Tower B?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback