Home / Browse projects / Bengaluru Urban, Karnataka / Assetz Muse & Maison
Assetz Muse & Maison
RG-KA-90727 · RERA PRM/KA/RERA/1251/310/PR/040526/008618 · Last updated on RERA Karnataka portal: 13 Oct 2026
Source: official RERA Karnataka filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
Saved.
Assetz Muse & Maison is a Residential/Group Housing project by Assetz Private Limited in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/310/PR/040526/008618 on 4 May 2026. Possession is promised by 31 Mar 2030. 12 of the 128 units on this registration are recorded sold or booked, and 1 of 18 construction stages are filed complete.
At a glance
Project
- NameAssetz Muse & Maison
- TypeResidential/Group Housing
- Location
- Bengaluru South
- Bengaluru Urban
- 560099
- Pincode560099
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1251/310/PR/040526/008618
- ReraGenie IDRG-KA-90727
Builder
- NameAssetz Private Limited
- Entity typeCompany
- CINU45201KA2018PTC114159
- GSTIN29AARCA0497M1ZV
- Authorized SignatoryAkshay Kishore Dewani
- CeoAkshay Kishore Dewani
- DirectorsAkshay Kishore Dewani, Sunil Kumar Pareek, Ben Salmon, Jagannath Laxman Shetty
- Project HeadNandakumar P S
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on4 May 2026
- Promised completion31 Mar 2030
- Revised completionNone
- Buildings1 building record
- Documents filed122 files
Current status
Figures as on 13 Oct 2026, this project's latest RERA Karnataka filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| TOWER A | - | - | - | 128 | 0 | 128 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 13 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
1 of 18 construction stages are filed complete. The stage furthest along is Foundation footing work, at 40%.
Building: 10% average across the applicable activities
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | 100% |
| Foundation footing work | 40% |
| Upto Plinth Level | 10% |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | 0% |
| Retaining wall (All types) | 30% |
| RCC or MS Framed structure | 0% |
| Masonry Construction | 0% |
| Plastering inside , outside & Ceiling | 0% |
| Joinery: Doors, Windows, Ventilators etc | 0% |
| Basic work of Water supply, Sanitary and Electrification | 0% |
| Dadoing, Skirting, Flooring, Tiles work (All types) | 0% |
| Railing and Grill fixing | 0% |
| Electrification, Water supply and Sanitary Finishing | 0% |
| Painting | 0% |
| Fire prevention and fire fighting fitting and fixture with network | 0% |
| Weather Proof work(tile,concrete) | 0% |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Elevation work | 0% |
| Internal and External work including landscapes as per sanctioned drawings | 0% |
Progress on shared amenities40
As on 13 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | 0% |
| Sewage and Drainage System | Yes | 0% |
| Water conservation/rain water harvesting/recharge of ground water | Yes | 0% |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Solid waste management and disposal | Yes | 0% |
| Emergency Evacuation services | Yes | 0% |
| Internal Roads & Footpaths | Yes | 0% |
| Electricity supply transformer and substation | Yes | 0% |
| Storm water drains | Yes | 0% |
| Use of renewable energy | Yes | 0% |
| Sewage Treatment Plant (STP) | Yes | 0% |
| Parks & Tree planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Electricity | Yes | 0% |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | 0% |
| Club House | Yes | 0% |
| Community Hall | Yes | 0% |
| Outdoor Sports facility | Yes | 0% |
| Indoor Sports facility | Yes | 0% |
| Swimming Pool | Yes | 0% |
| Gym | Yes | 0% |
| Parks | Yes | 0% |
| Power Backup | Yes | 0% |
| Piped Gas | No | Not applicable |
| Water and Sanitation | Yes | 0% |
| Air Conditioning | Yes | 0% |
| Staircases | Yes | 0% |
| Lifts | Yes | 0% |
| Corridor/Lobbies | Yes | 0% |
| Fire escapes | Yes | 0% |
| Common entrance and exit for the building/common portico/foyer/verandah | Yes | 0% |
| Basement | Yes | 0% |
| Terrace | Yes | 0% |
| Outer Wall | Yes | 0% |
| Open parking areas | Yes | 0% |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | Yes | 0% |
| Common storage spaces | No | Not applicable |
Land and ownership1
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| H C Narayana Reddy | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 92.13 cr | Rs 11.18 cr |
| Principal sum and interest payable to financial institutions-Non Banking financial institution (NBFC) | Rs 10.00 cr | - |
| On-site expenditure-Site Overhead | Rs 6.25 cr | - |
| Approvals | Rs 6.05 cr | Rs 4.88 cr |
| On-site expenditure-Consultants Fees | Rs 1.42 cr | Rs 94.76 lakh |
Certifying professionals and partners3
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | SHARAD MAITHEL |
| Engineer | Rajesh Shirakol |
| Chartered Accountant | Y S Shetty & Company |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed122
As listed on the registration, under the names the promoter filed them with; the newest 80 of 122 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/310/PR/040526/008618 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form -4 Chartered Accountant - Assetz Muse & Maison.pdf | 13 Oct 2026 |
| Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Form 5 Gattahalli 30-09-2026-signed.pdf | 13 Oct 2026 |
| Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form -6, Engineer (QU) Assetz Muse & Maison.pdf | 13 Oct 2026 |
| Q2 2026-27 Water supply and sewage board | 13 Oct 2026 |
| Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres) | 13 Oct 2026 |
| Q2 2026-27 KSPCB- MOEF (Above 50 Acres) | 13 Oct 2026 |
| Q2 2026-27 KPTCL- BESCOM | 13 Oct 2026 |
| Q2 2026-27 Fire and Safety | 13 Oct 2026 |
| Q2 2026-27 Airport Authority of India | 13 Oct 2026 |
| Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form -4 Chartered Accountant - Assetz Muse & Maison.pdf | 15 Jul 2026 |
| Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form-05 Architect 08-07-2026.pdf | 15 Jul 2026 |
| Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form 6 -Engineer certificate.pdf | 15 Jul 2026 |
| Q1 2026-27 Water supply and sewage board | 15 Jul 2026 |
| Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres) | 15 Jul 2026 |
| Q1 2026-27 KSPCB- MOEF (Above 50 Acres) | 15 Jul 2026 |
| Q1 2026-27 KPTCL- BESCOM | 15 Jul 2026 |
| Q1 2026-27 Fire and Safety | 15 Jul 2026 |
| Q1 2026-27 Airport Authority of India | 15 Jul 2026 |
| Building LicenseFile: Annexure 1-Building License.pdf | 29 Apr 2026 |
| SANCTIONED DRAWINGS AND ALL FLOORS PLANFile: Annexure 2- SANCTIONED DRAWINGS AND ALL FLOORS PLAN.pdf | 29 Apr 2026 |
| Commencement CertificateFile: Annexure 3-Commencement Certificate.pdf | 29 Apr 2026 |
| APPROVED SECTIONAL DRAWINGSFile: Annexure 5-APPROVED SECTIONAL DRAWINGS.pdf | 29 Apr 2026 |
| Allotement Letter With Possession DateFile: Annexure 6-Allotement Letter With Possession Date.pdf | 29 Apr 2026 |
| Airport NOCFile: Annexure 7-Airport NOC.pdf | 29 Apr 2026 |
| HAL Noc AffidavitFile: Annexure 8-HAL Noc Affidavit.pdf | 29 Apr 2026 |
| Water NOC-Gram PanchayatFile: Annexure 9- Water NOC-Gram Panchayat.pdf | 29 Apr 2026 |
| SITE PLANFile: Annexure 10-SITE PLAN.pdf | 29 Apr 2026 |
| BASEMENT FLOOR PLANFile: Annexure 11-BASEMENT FLOOR PLAN.pdf | 29 Apr 2026 |
| GROUND FLOOR PLANFile: Annexure 12-GROUND FLOOR PLAN.pdf | 29 Apr 2026 |
| FIRST FLOOR PLANFile: Annexure 13- FIRST FLOOR PLAN.pdf | 29 Apr 2026 |
| TYPICAL 2nd to 16 th FLOOR PLANFile: Annexure 14- TYPICAL 2nd to 16 th FLOOR PLAN.pdf | 29 Apr 2026 |
| TERRACE FLOOR PLANFile: Annexure 15-TERRACE FLOOR PLAN.pdf | 29 Apr 2026 |
| SECTIONFile: Annexure 16-SECTION.pdf | 29 Apr 2026 |
| ELEVATIONFile: Annexure 17-ELEVATION.pdf | 29 Apr 2026 |
| Clarification regarding Violation of Section 3(1)File: Annexure 2-Clarification regarding Violation of Section 3(1).pdf | 20 Mar 2026 |
| Sources of FundFile: Annexure 3-Sources of Fund.pdf | 20 Mar 2026 |
| MRFile: Annexure 4-MR.pdf | 20 Mar 2026 |
| Defect free EC from 1-04-2004File: Annexure 5-Defect free EC from 1-04-2004.pdf | 20 Mar 2026 |
| Non-Litigation AffidavitFile: Annexure 6-Non-Litigation Affidavit.pdf | 20 Mar 2026 |
| Single Plot PlanFile: Annexure 7-Single Plot Plan.pdf | 20 Mar 2026 |
| Single Plot OrderFile: Annexure 8-Single Plot Order.pdf | 20 Mar 2026 |
| ADLR SKETCHFile: Annexure 10-ADLR SKETCH.pdf | 20 Mar 2026 |
| Demarcation land -Google MapFile: Annexure 11-Demarcation land -Google Map.pdf | 20 Mar 2026 |
| CDP MAPFile: Annexure 12-CDP MAP.pdf | 20 Mar 2026 |
| Village MapFile: Annexure 13-Village Map.pdf | 20 Mar 2026 |
| KSPCB NOCFile: Annexure 14-KSPCB.pdf | 20 Mar 2026 |
| Clarification Registration of ProjectFile: Annexure 17-Clarification Registration of Project.pdf | 20 Mar 2026 |
| Details of Facilities ProvidedFile: Annexure 18-Details of Facilities Provided.pdf | 20 Mar 2026 |
| Self Attested Engineer Licence and AdharFile: Annexure 19-Self Attested Engineer Licence and Adhar.pdf | 20 Mar 2026 |
| Self Attested engineer and Adhar who signed form 3File: Annexure 20-Self Attested engineer and Adhar who signed form 3.pdf | 20 Mar 2026 |
| Structural Stability CertificateFile: Annexure 21-Structural Stability Certificate.pdf | 20 Mar 2026 |
| Project SpecificationFile: Annexure 22-Project Specification.pdf | 20 Mar 2026 |
| Agreement to saleFile: Annexure 23-ATS.pdf | 20 Mar 2026 |
| Allotement Letter with annexure AFile: Annexure 24-Allotement Letter with annexure A.pdf | 20 Mar 2026 |
| Water-Gram PanchayatFile: Annexure 25-Water-Gram Panchayat.pdf | 20 Mar 2026 |
| SEIAA NOCFile: Annexure 26-SEIAA NOC.pdf | 20 Mar 2026 |
| AAI NOCFile: Annexure 27-AAI NOC.pdf | 20 Mar 2026 |
| Breif Estimation of CostFile: Annexure 28-Breif Estimation of Cost.pdf | 20 Mar 2026 |
| Sanction Drawing - STP DetailFile: Annexure 29-Sanction Drawing - STP Detail.pdf | 20 Mar 2026 |
| Land Cost CalculationFile: Annexure 30-Land Cost Calculation.pdf | 20 Mar 2026 |
| RTC, survey 173/2 | - |
| Mutation, survey 173/2 | - |
| Encumbrance Certificate, survey 173/2 | - |
| Conversion/Alienation Order, survey 173/2 | - |
| Sale/Title/Gift Deed, survey 173/2 | - |
| JDA, survey 173/2 | - |
| Khatha, survey 173/2 | - |
| Registration CertificateFile: Annexure 1-COI.pdf | - |
| Memorandum of AssociationFile: Annexure 15-Memorandam Of Association.pdf | - |
| Article of AssociationFile: Annexure 16-Articles of Association.pdf | - |
| GST CertificateFile: Annexure 3-GST Certificate.pdf | - |
| Organization StructureFile: Annexure 14-Org Structure.pdf | - |
| Certificate issued by CA Form 1File: Annexure 59-Form-1 CA Certificate.pdf | - |
| Certificate issued by Architect Form 2File: Annexure 61-Architect Certificate.pdf | - |
| Certificate issued by Engineer Form 3File: Annexure 60-Form 3- Engineer Certificate.pdf | - |
| Project Chartered Accountant | - |
| Project Engineer | - |
| Project Architect | - |
| AffidavitFile: Annexure 49-Non-Litigation Affidavit.pdf | - |
| Balance Sheet 2024 - 2025File: Annexure 70c-BS 24-25.pdf | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Urban
Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.
Keep Assetz Muse & Maison on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Urban4,100+ in Bengaluru Urban
Filed coordinates, straight-line distance. 43 registered projects within 2 km.
Adarsh Welkin Park Phase 2
Akarshak Realty Private Limited
Adarsh Welkin Park Phase 1
Akarshak Realty Private Limited
Nambiar District 25 Phase 1
Nambiar EnsembleResidential Projects LLP
CASAGRAND VIVACITY
CASA GRANDE GARDEN CITY BUILDERS PVT LTD
Mahendra Solterra Aarya Phase-2
Mahendra Homes Private Limited
SIGNATURE SPLENDOR
SIGNATURE DWELLINGS PRIVATE LIMITED
See every Bengaluru Urban project, with the district possession charts
Builder: Assetz Private Limited
Assetz Private Limited has 1 registration on RERA Karnataka, including Assetz Muse & Maison. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.
Frequently asked questions
What are my rights if Assetz Muse & Maison is delayed beyond 31 Mar 2030?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of Assetz Muse & Maison?
The registered promoter entity is Assetz Private Limited, a company as per the filing. Its CIN U45201KA2018PTC114159 and GSTIN 29AARCA0497M1ZV can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in Assetz Muse & Maison?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at Assetz Muse & Maison?
The professionals named in the filing: Architect: SHARAD MAITHEL; Engineer: Rajesh Shirakol; Chartered Accountant: Y S Shetty & Company. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Assetz Muse & Maison?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback