ReraGenieLog inGet a buyer report

Home / Browse projects / Vadodara, Gujarat / ASHWAMEGH AVENUE

Valid until 15 May 2025 Mixed Development project

ASHWAMEGH AVENUE

By VAMA DEVELOPERS

RG-GJ-70441 · RERA PR/GJ/VADODARA/VADODARA/Others/MAA04253/EX2/EX3/180924/150525 · Last updated on GujRERA portal: 22 Oct 2024

Source: official GujRERA filing

Red flags

  • Completion date moved by 35 months
  • 3 extensions taken

Clear

  • Nothing verified clear yet
May 2025Possession promisedmoved 35 months from the original
24 of 27Construction stages doneacross 3 buildings; furthest along: Stilt Floor, 0%
64 of 136Units unsoldnot recorded sold or booked
Jump to the 40 documents Report an error

ASHWAMEGH AVENUE is a Mixed Development project by VAMA DEVELOPERS in Vadodara, Gujarat, registered with GujRERA as PR/GJ/VADODARA/VADODARA/Others/MAA04253/EX2/EX3/180924/150525 on 6 Dec 2018. Possession is promised by 15 May 2025. The completion date has moved by 35 months from the original filing. 72 of the 136 units on this registration are recorded sold or booked, and 24 of 27 construction stages are filed complete.

At a glance

Project

  • NameASHWAMEGH AVENUE
  • TypeMixed Development
  • Location
    • NR PRIYA CINEMA
    • BHAYLI
    • BHAYLI VASNA
    • Bhayali
    • Vadodara
    • 391101
  • Pincode391101
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/VADODARA/VADODARA/Others/MAA04253/EX2/EX3/180924/150525
  • ReraGenie IDRG-GJ-70441

Builder

  • NameVAMA DEVELOPERS
  • Entity typePARTNERSHIP FIRM
  • Other registrations1 more →

Key dates

this monthRegisteredDec 2018First promiseJun 2022Revised toMay 2025

Key facts

Registration and timeline

  • StatusValid until 15 May 2025
  • Registered on6 Dec 2018
  • Promised completion15 May 2025
  • Revised completionRevised to 15 May 2025 (originally 30 Jun 2022)
  • Buildings3 building records
  • Documents filed40 files

Current status

53%72 of 136 units booked
100.0%Of the estimated cost spent so far

Figures as on 22 Oct 2024, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---07878
B---30030
C---161228

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building3

As on 22 Oct 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

24 of 27 construction stages are filed complete across 3 buildings. The stage furthest along is Stilt Floor, at 0%.

A89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
B89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
C89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 22 Oct 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsYes100%
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationNoNot applicable
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,904 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 7.36 cr
Cost incurredRs 7.36 cr
Spent of the estimate100.0%
BuildingWingEstimatedIncurred
ANARs 2.45 crRs 2.45 cr
BNARs 2.45 crRs 2.45 cr
CNARs 2.45 crRs 2.45 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRUCHIR SHETH
EngineerZARNA ASSOCIATES

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/VADODARA/VADODARA/Others/MAA04253/EX1/270722Applied Jun 2022; approved Jul 2022
PR/GJ/VADODARA/VADODARA/Others/MAA04253/EX2/210624/150524Applied Oct 2023; approved Jun 2024
PR/GJ/VADODARA/VADODARA/Others/MAA04253/EX2/EX3/180924/150525Applied Aug 2024; approved Sep 2024

Documents filed40

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VADODARA/VADODARA/Others/MAA04253/EX2/EX3/180924/150525 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)22 Oct 2024
Engineer's certificate (Form 2)18 Oct 2024
Engineer's certificate annexure18 Oct 2024
Architect's certificate (Form 1)17 Oct 2024
Site photograph, A15 Oct 2024
Site photograph, B15 Oct 2024
Site photograph, C15 Oct 2024
RERA registration certificate6 Dec 2018
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Vadodara

53%of this project is bookeddistrict median 70%
23%of Vadodara projects moved their completion datethis one moved by 35 months

Computed across the 2,900+ Vadodara projects on ReraGenie, from their own filings.

Keep ASHWAMEGH AVENUE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bhayali ,2,900+ in Vadodara

2 kmASHWAMEGH AVENUEOther 348Dot size: filed unitsN

Filed coordinates, straight-line distance. 348 registered projects within 2 km.

Builder: VAMA DEVELOPERS

VAMA DEVELOPERS has 2 registrations on GujRERA, including ASHWAMEGH AVENUE and 7X SPARSH VILLA. Read the full track record. See more projects on the Vadodara district page.

Frequently asked questions

What are my rights if ASHWAMEGH AVENUE is delayed beyond 15 May 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of ASHWAMEGH AVENUE?

The registered promoter entity is VAMA DEVELOPERS, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in ASHWAMEGH AVENUE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at ASHWAMEGH AVENUE?

The professionals named in the filing: Architect: RUCHIR SHETH; Engineer: ZARNA ASSOCIATES. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ASHWAMEGH AVENUE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ASHWAMEGH AVENUE. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ASHWAMEGH AVENUE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.