ReraGenieLog inGet a buyer report

Home / Browse projects / Bengaluru Urban, Karnataka / Around The Life

Registration approved No litigation declared Residential/Group Housing project

Around The Life

By Keya Homes Pvt Ltd

RG-KA-98167 · RERA PRM/KA/RERA/1251/446/PR/020822/005125 · Last updated on RERA Karnataka portal: 26 Jul 2022

Source: official RERA Karnataka filing

Red flags

  • 1 complaint at RERA Karnataka

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
Jun 2025Possession promisedno revision filed
1Complaints at RERA Karnatakaon this registration
Jump to the 105 documents Report an error

Around The Life is a Residential/Group Housing project by Keya Homes Pvt Ltd in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/020822/005125 on 2 Aug 2022. Possession is promised by 30 Jun 2025. 1 complaint is on record with the regulator.

At a glance

Project

  • NameAround The Life
  • TypeResidential/Group Housing
  • Location
    • Bengaluru East
    • Bengaluru Urban
    • 560067
  • Pincode560067
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/446/PR/020822/005125
  • ReraGenie IDRG-KA-98167

Builder

  • NameKeya Homes Pvt Ltd
  • Entity typeCompany
  • CINU70109KA2013PTC068958
  • GSTIN29AAFCK1456Q1ZW
  • Authorized SignatoryDinesh Kejriwal
  • HodNayan Mookim
  • DirectorsDinesh Kejriwal, Bipin Ram Agarwal
  • Project HeadNayan Mookim
  • Other registrations2 more →
  • Declared earlier projects2 →

Key dates

this monthRegisteredAug 2022PromisedJun 2025

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on2 Aug 2022
  • Promised completion30 Jun 2025
  • Revised completionNone
  • Buildings3 building records
  • Documents filed105 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tower A---1920192
Tower B---1380138
Tower C---1380138

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 26 Jul 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja work-
Fire prevention and fire fighting fitting and fixture with network-
Weather Proof work(tile,concrete)-
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities41

As on 26 Jul 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsYes-
Sewage and Drainage SystemYes-
Parks & Tree plantingYes-
Street LightingYes-
Provision for community buildings and for treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalYes-
Water conservationYes-
Energy managementYes-
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesYes-
Electricity supply transformer and substationYes-
Emergency Evacuation servicesNoNot applicable
Storm water drainsYes-
Use of renewable energyYes-
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseYes-
Community HallYes-
Outdoor Sports facilityYes-
Indoor Sports facilityYes-
Swimming PoolYes-
GymYes-
ParksNoNot applicable
Power BackupYes-
GasYes-
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorNoNot applicable
Fire escapesNoNot applicable
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes-

Land and ownership3

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area18,918 sq m
Named landowners3
LandownerVillageDistrict
B. L. Kodanda Ramaiah--
B.L.Anand Kumar.--
B L Girish Kumar--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 224.30 cr
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 157.01 cr-
On-site expenditure-Salaries of workersRs 44.86 cr-
On-site expenditure-Consultants FeesRs 11.21 cr-
On-site expenditure-Site OverheadRs 7.85 cr-
On-site expenditure-Cost Of Services(Water, Electricity, Sewage)Rs 3.36 cr-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectUrban Frame Pvt Ltd
EngineerAEC Nexgen Consultancy LLP
Chartered AccountantR J M J & Associates

Complaints filed with RERA Karnataka1

Case no.ComplainantRespondentFiled
00964/2025-Keya Homes Pvt Ltd23/07/2025

Documents filed105

As listed on the registration, under the names the promoter filed them with; the newest 80 of 105 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/020822/005125 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Once again Cost details are not updated properly in the project detail page as well as in cost detaiFile: KHPL-Form 2 revised certificate.pdf26 Jul 2022
In the uploaded letter issued by BWSSB, states that the "BWSSB comes beyond BBMP Limits. Prior approFile: 72 Water Letter Panchayat.pdf26 Jul 2022
Upload Relinquishment deed for the road widening Area.File: 01 A.pdf18 Jul 2022
Upload Relinquishment deed for the road widening Area.File: 01 B.pdf18 Jul 2022
Upload Commencement CertificateFile: 02.pdf18 Jul 2022
Upload Building License.File: 03.pdf18 Jul 2022
Uploaded copy of request letter written to BWSSB instead of NC. Therefore Please upload the BWSSB NOFile: 05.pdf18 Jul 2022
Uploaded the STP location plan. Please upload the STP design drawing as per the KSPCB guidelines.File: 06.pdf18 Jul 2022
The validity of uploaded BESCOM NOC is lapsed. Therefore Please upload the renewed NOC issued by BESFile: 07.pdf18 Jul 2022
Reply Letter - Keya HomesFile: RERA LETTER.pdf18 Jul 2022
Chartered accountant certificate in prescribed format form-01File: 1.pdf7 Jul 2022
need notrazied joint affidavit cum decalartion in rera prescribed format with all landowner’s signFile: 2.pdf7 Jul 2022
need title deed to b c lakshamaiah for syno 90File: 4.pdf7 Jul 2022
Need to upload the certified copy obtained by the concerned Sub-registrar regarding value of the proFile: 5.pdf7 Jul 2022
Need notarized non-litigation affidavit with respect the property regarding land acquisition, courtFile: 6.pdf7 Jul 2022
Upload the Extract of master plan Showing the Buffer line for the abutting NALAFile: 8.pdf7 Jul 2022
Upload Building License.File: 10.pdf7 Jul 2022
Please upload the Estimated cost of construction certified by the Engineer, accordingly, update theFile: 15.pdf7 Jul 2022
Please upload the signed copy of the project specification comprising with the project name and addrFile: 16.pdf7 Jul 2022
Please mention the project name and address/Ack. number and upload the section 3(1) notarized affidaFile: 17.pdf7 Jul 2022
Please upload the BWSSB NOC along with the copy of fee paid receipt towards NOC.File: 18.pdf7 Jul 2022
Please upload the copy of fee receipt paid toward power supply NOC.File: 19.pdf7 Jul 2022
Provision of STP in the project is to be clarified by the promoter along with the supporting STP desFile: 20.pdf7 Jul 2022
CDP PlanFile: 21.pdf7 Jul 2022
RTC, survey 90-
Mutation, survey 90-
Encumbrance Certificate, survey 90-
Conversion/Alienation Order, survey 90-
Sale/Title/Gift Deed, survey 90-
JDA, survey 90-
Khatha, survey 90-
Registration CertificateFile: A 1.pdf-
Organization StructureFile: A 11.pdf-
Certificate issued by CA Form 1File: CA Certificate ATL.pdf-
Certificate issued by Architect Form 2File: Architect Revised.pdf-
Certificate issued by Engineer Form 3File: AEC NEXGEN-KH-ATL-RERA -Q3-2023-24-FORM6.pdf-
TDR Purchase Deed / Sale DeedFile: 02 ATL TDR.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: A 45.pdf-
Certificate from Chartered AccountFile: CA Certificate ATL.pdf-
Certificate from Chartered AccountFile: CA Certificate ATL.pdf-
Balance Sheet 2020 - 2021File: A 60A.pdf-
Balance Sheet 2019 - 2020File: A 60B.pdf-
Balance Sheet 2018 - 2019File: A 60C.pdf-
Audited Profit and Loss Statement 2020 - 2021File: A 61A.pdf-
Audited Profit and Loss Statement 2019 - 2020File: A 61B.pdf-
Audited Profit and Loss Statement 2018 - 2019File: A 61C.pdf-
Director's Report 2020 - 2021File: A 62A.pdf-
Director's Report 2019 - 2020File: A 62B.pdf-
Director's Report 2018 - 2019File: A 62C.pdf-
Cash Flow Statement 2020 - 2021File: A 63A.pdf-
Cash Flow Statement 2019 - 2020File: A 63B.pdf-
Auditor's Report 2020 - 2021File: A 64A.pdf-
Auditor's Report 2019 - 2020File: A 64B.pdf-
Auditor's Report 2018 - 2019File: A 64C.pdf-
Income Tax Return Acknowledgement 2020 - 2021File: A 65A.pdf-
Income Tax Return Acknowledgement 2019 - 2020File: A 65B.pdf-
Income Tax Return Acknowledgement 2018 - 2019File: A 65C.pdf-
A 70-
A 71-
A 74-
A 75-
A 76-
A 78-
A 79-
A 86-
A 87-
A 89-
A 90-
A 91-
A 92-
A 93-
A 97-
A 98-
A 99-
A 100-
A 101-
Already registered project ongoing detailsFile: Project Ongoing Details.pdf-

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 not delivered by the promised date1 declared completed, no finish date filed
ProjectLocationStatusPromisedDelivered
Life By The Lake3JR4+5M5, Near Pyramid Banksia, Jakkur Lake Road, Nehru Nagar, Yelahanka, Agrahara, Bengaluru, Karnataka 560064OngoingJun 2022Not delivered
The Green TerracesThe Green Terraces, Smondoville Road, 1, Neotown, Electronic City, Bengaluru, Karnataka 560100Completed-No date filed

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Around The Life on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmAround The LifeOther 24Dot size: filed unitsN

Filed coordinates, straight-line distance. 24 registered projects within 2 km.

Builder: Keya Homes Pvt Ltd

keya homes pvt ltd has 3 registrations on RERA Karnataka, including The green terraces and Life By The Lake. Its filings declare 2 earlier projects, 1 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Around The Life is delayed beyond 30 Jun 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Around The Life?

The registered promoter entity is Keya Homes Pvt Ltd, a company as per the filing. Its CIN U70109KA2013PTC068958 and GSTIN 29AAFCK1456Q1ZW can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Around The Life?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Around The Life?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

Who certifies construction progress at Around The Life?

The professionals named in the filing: Architect: Urban Frame Pvt Ltd; Engineer: AEC Nexgen Consultancy LLP; Chartered Accountant: R J M J & Associates. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Around The Life?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Around The Life. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Around The Life to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.