Home / Browse projects / Vadodara, Gujarat / Angel Elysian

Valid until 25 Jan 2027 Residential/Group Housing project

Angel Elysian

By ANGEL INFRABUILD

RG-GJ-53432 · RERA PR/GJ/VADODARA/VADODARA/Others/RAA10582/EX1/111225/250126 · Last updated on GujRERA portal: 3 Dec 2025

Source: official GujRERA filing

Red flags

  • Completion date moved by 21 months
  • 2 extensions taken

Clear

  • Nothing verified clear yet
Jan 2027Possession promisedmoved 21 months from the original
5 of 9Construction stages donefurthest along: Internal walls, 60%
14 of 14Units unsoldnot recorded sold or booked
Jump to the 41 documents Report an error

Angel Elysian is a Residential/Group Housing project by ANGEL INFRABUILD in Vadodara, Gujarat, registered with GujRERA as PR/GJ/VADODARA/VADODARA/Others/RAA10582/EX1/111225/250126 on 24 Aug 2022. Possession is promised by 25 Jan 2027. The completion date has moved by 21 months from the original filing. 0 of the 14 units on this registration are recorded sold or booked, and 5 of 9 construction stages are filed complete.

At a glance

Project

  • NameAngel Elysian
  • TypeResidential/Group Housing
  • Location
    • Angel Elysian
    • Nr. Greenfield 2
    • 24 Mtr TP Road
    • Bhayli TP 2
    • Bhayli
    • Vadodara
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/VADODARA/VADODARA/Others/RAA10582/EX1/111225/250126
  • ReraGenie IDRG-GJ-53432

Builder

  • NameANGEL INFRABUILD
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredAug 2022First promiseApr 2025Revised toJan 2027

Key facts

Registration and timeline

  • StatusValid until 25 Jan 2027
  • Registered on24 Aug 2022
  • Promised completion25 Jan 2027
  • Revised completionRevised to 25 Jan 2027 (originally 25 Apr 2025)
  • Buildings1 building record
  • Documents filed41 files

Current status

0%0 of 14 units booked
55.5%Of the estimated cost spent so far

Figures as on 3 Dec 2025, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---0014

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 3 Dec 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 9 construction stages are filed complete. The stage furthest along is Internal walls, at 60%.

A: 73% average across the applicable activities

ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats60%
Sanitary fittings within the flats50%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing50%

Progress on shared amenities19

As on 3 Dec 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes0%
Water supplyYes50%
Sewerage (chamber, lines, septic tank, STP)Yes50%
Storm water drainsYes0%
Landscaping and tree plantingYes0%
Street lightingYes0%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes0%
Energy managementYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Fire fightingYes0%
Drinking water facilitiesYes0%
Emergency evacuationNoNot applicable
Use of renewable energyYes0%
SecurityYes0%
Letter boxYes0%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area879 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 9.50 cr
Cost incurredRs 5.27 cr
Spent of the estimate55.47%
BuildingWingEstimatedIncurred
ANARs 9.50 crRs 5.27 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAshwinkumar R Patel
EngineerAashutosh Anilchandra Desai

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/VADODARA/VADODARA/Others/RAA10582/EX1/111225/250126Applied Aug 2025; approved Dec 2025
ExtensionApplied Sep 2026; no approval date filed

Documents filed41

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VADODARA/VADODARA/Others/RAA10582/EX1/111225/250126 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)3 Dec 2025
Architect's certificate (Form 1)1 Dec 2025
Engineer's certificate (Form 2)1 Dec 2025
Engineer's certificate annexure1 Dec 2025
Site photograph, A1 Dec 2025
RERA registration certificate24 Aug 2022
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Vadodara

0%of this project is bookeddistrict median 70%
23%of Vadodara projects moved their completion datethis one moved by 21 months

Computed across the 2,900+ Vadodara projects on ReraGenie, from their own filings.

Keep Angel Elysian on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Vadodara2,900+ in Vadodara

2 kmAngel ElysianOther 374Dot size: filed unitsN

Filed coordinates, straight-line distance. 374 registered projects within 2 km.

Builder: ANGEL INFRABUILD

ANGEL INFRABUILD has 1 registration on GujRERA, including Angel Elysian. Read the full track record. See more projects on the Vadodara district page.

Frequently asked questions

What are my rights if Angel Elysian is delayed beyond 25 Jan 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of Angel Elysian?

The registered promoter entity is ANGEL INFRABUILD, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in Angel Elysian?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Angel Elysian?

The professionals named in the filing: Architect: Ashwinkumar R Patel; Engineer: Aashutosh Anilchandra Desai. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Angel Elysian?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Angel Elysian. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Angel Elysian to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.