Home / Browse projects / Vadodara, Gujarat / Anaya Eternity

Valid until 30 Jan 2028 Residential/Group Housing project

Anaya Eternity

By ANAYA REALTY

RG-GJ-51777 · RERA PR/GJ/VADODARA/VADODARA/Vadodara Urban Development Authority/RAA12517/A1R/250624/300927 · Last updated on GujRERA portal: 24 Aug 2024

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Jan 2028Possession promisedno revision filed
1 of 9Construction stages donefurthest along: Plinth, 80%
10 of 13Units unsoldnot recorded sold or booked
Jump to the 41 documents Report an error

Anaya Eternity is a Residential/Group Housing project by ANAYA REALTY in Vadodara, Gujarat, registered with GujRERA as PR/GJ/VADODARA/VADODARA/Vadodara Urban Development Authority/RAA12517/A1R/250624/300927 on 23 Oct 2023. Possession is promised by 30 Jan 2028. 3 of the 13 units on this registration are recorded sold or booked, and 1 of 9 construction stages are filed complete.

At a glance

Project

  • NameAnaya Eternity
  • TypeResidential/Group Housing
  • Location
    • FP 108
    • Besides Lavanya Bunglows
    • Behind Taksh Galaxy Mall
    • Ankhol
    • Ankhol
    • Vadodara
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/VADODARA/VADODARA/Vadodara Urban Development Authority/RAA12517/A1R/250624/300927
  • ReraGenie IDRG-GJ-51777

Builder

  • NameANAYA REALTY
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredOct 2023PromisedJan 2028

Key facts

Registration and timeline

  • StatusValid until 30 Jan 2028
  • Registered on23 Oct 2023
  • Promised completion30 Jan 2028
  • Revised completionNone
  • Buildings1 building record
  • Documents filed41 files

Current status

23%3 of 13 units booked
21.0%Of the estimated cost spent so far

Figures as on 24 Aug 2024, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Resi ( Total - 13 Unit )---13013

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 24 Aug 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

1 of 9 construction stages are filed complete. The stage furthest along is Plinth, at 80%.

Resi ( Total - 13 Unit ): 36% average across the applicable activities

ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth80%
Stilt Floor15%
Slabs of Super Structure33%
Internal walls, internal plaster, floorings, doors and windows within flats33%
Sanitary fittings within the flats15%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks33%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing15%

Progress on shared amenities23

As on 24 Aug 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes0%
Water supplyYes0%
Sewerage (chamber, lines, septic tank, STP)NoNot applicable
Storm water drainsYes0%
Landscaping and tree plantingYes0%
Street lightingYes0%
Community buildingsYes0%
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalYes0%
Water conservation, rain water harvestingYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Fire fightingNoNot applicable
Drinking water facilitiesYes0%
Emergency evacuationNoNot applicable
Use of renewable energyYes0%
SecurityYes0%
Letter boxNoNot applicable
Compound wallYes0%
Plinth protectionYes0%
Water tankYes0%
Other requirementsYes0%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,732 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 4.00 cr
Cost incurredRs 84.00 lakh
Spent of the estimate21.01%
BuildingWingEstimatedIncurred
Resi ( Total - 13 Unit )NARs 4.00 crRs 84.00 lakh

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectTaniya Naranbhai Patel
EngineerVINUBHAI RATILAL PATEL

Documents filed41

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VADODARA/VADODARA/Vadodara Urban Development Authority/RAA12517/A1R/250624/300927 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Engineer's certificate (Form 2)24 Aug 2024
Engineer's certificate annexure24 Aug 2024
RERA registration certificate23 Oct 2023
Alteration certificate-
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Drainage affidavit-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Approved building or plotting plan-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Proforma sale deed-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Vadodara

23%of this project is bookeddistrict median 70%
23%of Vadodara projects moved their completion datethis one has not

Computed across the 2,900+ Vadodara projects on ReraGenie, from their own filings.

Keep Anaya Eternity on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Ankhol2,900+ in Vadodara

2 kmAnaya EternityOther 162Dot size: filed unitsN

Filed coordinates, straight-line distance. 162 registered projects within 2 km.

Builder: ANAYA REALTY

ANAYA REALTY has 1 registration on GujRERA, including Anaya Eternity. Read the full track record. See more projects on the Vadodara district page.

Frequently asked questions

What are my rights if Anaya Eternity is delayed beyond 30 Jan 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of Anaya Eternity?

The registered promoter entity is ANAYA REALTY, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in Anaya Eternity?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Anaya Eternity?

The professionals named in the filing: Architect: Taniya Naranbhai Patel; Engineer: VINUBHAI RATILAL PATEL. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Anaya Eternity?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Anaya Eternity. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Anaya Eternity to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.