ReraGenieLog inGet a buyer report

Home / Browse projects / Vadodara, Gujarat / AL KABEER BUNGALOWS

Valid until 31 Dec 2027 Residential/Group Housing project

AL KABEER BUNGALOWS

By PERFECT DEVELOPERS

RG-GJ-93661 · RERA PR/GJ/VADODARA/VADODARA/Others/RAA11101/311222 · Last updated on GujRERA portal: 1 Oct 2024

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Dec 2027Possession promisedno revision filed
0 of 9Construction stages donefurthest along: Excavation, 90%
11 of 43Units unsoldnot recorded sold or booked
Jump to the 38 documents Report an error

AL KABEER BUNGALOWS is a Residential/Group Housing project by PERFECT DEVELOPERS in Vadodara, Gujarat, registered with GujRERA as PR/GJ/VADODARA/VADODARA/Others/RAA11101/311222 on 31 Dec 2022. Possession is promised by 31 Dec 2027. 32 of the 43 units on this registration are recorded sold or booked, and 0 of 9 construction stages are filed complete.

At a glance

Project

  • NameAL KABEER BUNGALOWS
  • TypeResidential/Group Housing
  • Location
    • RS NO 313/1 313/2 313/3 FP NO 63
    • TP NO 26 AT VILL TANDALJA
    • Vadodara
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/VADODARA/VADODARA/Others/RAA11101/311222
  • ReraGenie IDRG-GJ-93661

Builder

  • NamePERFECT DEVELOPERS
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredDec 2022PromisedDec 2027

Key facts

Registration and timeline

  • StatusValid until 31 Dec 2027
  • Registered on31 Dec 2022
  • Promised completion31 Dec 2027
  • Revised completionNone
  • Buildings1 building record
  • Documents filed38 files

Current status

74%32 of 43 units booked
77.3%Of the estimated cost spent so far

Figures as on 1 Oct 2024, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
RESIDENTIAL UNIT 1-43---43043

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 1 Oct 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 9 construction stages are filed complete. The stage furthest along is Excavation, at 90%.

RESIDENTIAL UNIT 1-43: 73% average across the applicable activities

ActivityProgress
Excavation90%
Podiums (if any)Not applicable
Plinth85%
Stilt Floor70%
Slabs of Super Structure86%
Internal walls, internal plaster, floorings, doors and windows within flats86%
Sanitary fittings within the flats70%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks86%
External plumbing and external plaster, elevation, completion of terraces with waterproofing15%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing70%

Progress on shared amenities23

As on 1 Oct 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes20%
Water supplyYes35%
Sewerage (chamber, lines, septic tank, STP)Yes35%
Storm water drainsYes35%
Landscaping and tree plantingNoNot applicable
Street lightingYes30%
Community buildingsYes0%
Treatment and disposal of sewage and sullage waterYes0%
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Fire fightingNoNot applicable
Drinking water facilitiesYes0%
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes0%
Letter boxNoNot applicable
Compound wallYes35%
Plinth protectionYes75%
Water tankYes75%
Other requirementsYes50%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area11,292 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 10.35 cr
Cost incurredRs 8.00 cr
Spent of the estimate77.29%
BuildingWingEstimatedIncurred
RESIDENTIAL UNIT 1-43NARs 10.35 crRs 8.00 cr

Documents filed38

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VADODARA/VADODARA/Others/RAA11101/311222 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Engineer's certificate (Form 2)1 Oct 2024
Engineer's certificate annexure1 Oct 2024
RERA registration certificate31 Dec 2022
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Vadodara

74%of this project is bookeddistrict median 70%
23%of Vadodara projects moved their completion datethis one has not

Computed across the 2,900+ Vadodara projects on ReraGenie, from their own filings.

Keep AL KABEER BUNGALOWS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Vadodara2,900+ in Vadodara

2 kmAL KABEER BUNGALOWSOther 387Dot size: filed unitsN

Filed coordinates, straight-line distance. 387 registered projects within 2 km.

Builder: PERFECT DEVELOPERS

PERFECT DEVELOPERS has 1 registration on GujRERA, including AL KABEER BUNGALOWS. Read the full track record. See more projects on the Vadodara district page.

Frequently asked questions

What are my rights if AL KABEER BUNGALOWS is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of AL KABEER BUNGALOWS?

The registered promoter entity is PERFECT DEVELOPERS, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in AL KABEER BUNGALOWS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

What should I check before booking in AL KABEER BUNGALOWS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About AL KABEER BUNGALOWS. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save AL KABEER BUNGALOWS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.