ADARSH ROSEWOOD

By Akarsh Residence Pvt Ltd

RG-KA-21952 · RERA PRM/KA/RERA/1251/446/PR/311224/007335 · Last updated on RERA Karnataka portal: 15 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • Litigation declared, 1 case

Clear

  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Dec 2027Possession promisedno revision filed
0 of 16Construction stages donefurthest along: Earth work and other leveling..., 99%
94 of 118Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 264 documents Report an error

ADARSH ROSEWOOD is a Residential/Group Housing project by Akarsh Residence Pvt Ltd in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/311224/007335 on 31 Dec 2024. Possession is promised by 31 Dec 2027. 24 of the 118 units on this registration are recorded sold or booked, and 0 of 16 construction stages are filed complete.

At a glance

Project

  • NameADARSH ROSEWOOD
  • TypeResidential/Group Housing
  • Location
    • Bengaluru East
    • Bengaluru Urban
    • 560103
  • Pincode560103
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/446/PR/311224/007335
  • ReraGenie IDRG-KA-21952

Builder

  • NameAkarsh Residence Pvt Ltd
  • Entity typeCompany
  • CINU45201KA2009PTC051265
  • GSTIN29AAICA0191P1Z7
  • Authorized SignatoryB M Jayeshankar
  • Chief Managing DirectorB M Jayeshankar
  • DirectorsB M Jayeshankar, BM Karunesh, Sudha Shanker
  • Project HeadK B Shivamurthy
  • Other registrations2 more →
  • Declared earlier projects1 →

Key dates

this monthRegisteredDec 2024PromisedDec 2027

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on31 Dec 2024
  • Promised completion31 Dec 2027
  • Revised completionNone
  • Buildings5 building records
  • Documents filed264 files

Current status

20%24 of 118 units booked
9.3%Of the estimated cost spent so far

Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Block A---18018
BLock B---20020
BLock C---40040
Block D---40040
Block E---404

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 16 construction stages are filed complete. The stage furthest along is Earth work and other leveling preparation work, at 99%.

Building: 14% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work99%
Foundation footing work90%
Upto Plinth Level0%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)0%
Retaining wall (All types)0%
RCC or MS Framed structure40%
Masonry Construction0%
Plastering inside , outside & Ceiling0%
Joinery: Doors, Windows, Ventilators etc0%
Basic work of Water supply, Sanitary and Electrification0%
Dadoing, Skirting, Flooring, Tiles work (All types)0%
Railing and Grill fixing0%
Electrification, Water supply and Sanitary Finishing0%
Painting0%
Fire prevention and fire fighting fitting and fixture with network0%
Weather Proof work(tile,concrete)Not applicable
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation workNot applicable
Internal and External work including landscapes as per sanctioned drawings0%

Progress on shared amenities40

As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes0%
Sewage and Drainage SystemYes0%
Water conservation/rain water harvesting/recharge of ground waterYes0%
Energy managementYes0%
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalYes0%
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsYes0%
Electricity supply transformer and substationYes0%
Storm water drainsYes0%
Use of renewable energyYes0%
Sewage Treatment Plant (STP)Yes0%
Parks & Tree plantingYes0%
Street LightingYes0%
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes0%
Club HouseYes0%
Community HallYes0%
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityYes0%
Swimming PoolYes0%
GymYes0%
ParksNoNot applicable
Power BackupYes0%
Piped GasNoNot applicable
Water and SanitationYes0%
Air ConditioningYes0%
StaircasesYes0%
LiftsYes0%
Corridor/LobbiesYes0%
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahYes0%
BasementYes0%
TerraceYes0%
Outer WallYes0%
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes0%
Common storage spacesNoNot applicable

Land and ownership6

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area7,064 sq m
Named landowners6
LandownerVillageDistrict
S.Sunil Kumar Karwa--
R.Anuradha--
S.Sunil Kumar Karwa--
R.Anuradha--
S.Sunil Kumar Karwa--
R.Anuradha--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 116.06 cr
Cost incurredRs 10.76 cr
Spent of the estimate9.27%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 94.56 crRs 8.82 cr
Principal sum and interest payable to financial institutions-Non Banking financial institution (NBFC)Rs 10.00 cr-
On-site expenditure-Salaries of workersRs 5.72 crRs 1.39 cr
On-site expenditure-Site OverheadRs 2.26 crRs 52.96 lakh
On-site expenditure-Consultants FeesRs 2.18 cr-
On-site expenditure-Cost Of Services(Water, Electricity, Sewage)Rs 1.33 crRs 1.16 lakh
RERA FEERs 70,649-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVISHWARADHYA R E
EngineerRajesh M H
Chartered AccountantMahesh B S

Litigation declared1

CaseCourtStatus
RFA No. 1075/2019 C/w RFA1555/2019, RFA 1404/19RFA1405/19High Court of karnataka & City Civil Court at Bangalore-

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed264

As listed on the registration, under the names the promoter filed them with; the newest 80 of 264 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/311224/007335 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Rosewood.pdf15 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Rosewood.pdf15 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Rosewood.pdf15 Oct 2026
Q2 2026-27 Water supply and sewage board15 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Oct 2026
Q2 2026-27 KSPCB- MOEF (Above 50 Acres)15 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Rose Wood_.pdf15 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Rose wood.pdf15 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Rosewood.pdf15 Jul 2026
Q1 2026-27 Water supply and sewage board15 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Jul 2026
Q1 2026-27 KSPCB- MOEF (Above 50 Acres)15 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Rosewood_.pdf15 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Rosewood.pdf15 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Rosewood.pdf15 Apr 2026
Q4 2025-26 Water supply and sewage board15 Apr 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)15 Apr 2026
Q4 2025-26 KSPCB- MOEF (Above 50 Acres)15 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: CA Rosewood_merged.pdf30 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Rosewood.pdf30 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Rosewood.pdf30 Jan 2026
Q3 2025-26 Water supply and sewage board30 Jan 2026
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)30 Jan 2026
Q3 2025-26 KSPCB- MOEF (Above 50 Acres)30 Jan 2026
Director's report - 2023-24File: Akarsh Residence - 2023-24.pdf11 Dec 2024
AKRPL fy 2023-24File: AKRPL fy 2023-24.pdf11 Dec 2024
Sources of fundFile: Akarsh Residence Statement.pdf11 Dec 2024
RFA 1555/2019File: Undertaking - Cum - Indemnity Bond.pdf11 Dec 2024
Akarsh Residence StatementFile: Akarsh Residence Statement.pdf27 Nov 2024
Undertaking - Cum - Indemnity BondFile: Undertaking - Cum - Indemnity Bond.pdf27 Nov 2024
98-2 2024-25 RTCFile: 98-2 2024-25.pdf27 Nov 2024
98-3 2024-25 RTCFile: 98-3 2024-25.pdf27 Nov 2024
98-5 2024-25 RTCFile: 98-5 2024-25.pdf27 Nov 2024
AAKARBANDHFile: AAKARBANDH.pdf27 Nov 2024
ADARSH ROSE WOOD - BUILDING SANCTION PLANFile: ADARSH ROSE WOOD - BUILDING SANCTION PLAN.pdf27 Nov 2024
BBMP_Building licence 22-04 -2024File: BBMP_Building licence 22-04 -2024.pdf27 Nov 2024
CANCELLATION DEED DATED 26 06 2018-DOC NO 2844-2018-19 - SY 98-2File: CANCELLATION DEED DATED 26 06 2018-DOC NO 2844-2018-19 - SY 98-2.pdf27 Nov 2024
CONVERSION ORDER DATED 02-04-2008 - SY NO 98-2File: CONVERSION ORDER DATED 02-04-2008 - SY NO 98-2.pdf27 Nov 2024
CONVERSION ORDER DATED 27 -03- 2004 - SY NO 98File: CONVERSION ORDER DATED 27 -03- 2004 - SY NO 98.pdf27 Nov 2024
FAMILY TREE OF GOPALA REDDYFile: FAMILY TREE OF GOPALA REDDY.pdf27 Nov 2024
FAMILY TREE OF INDRASHEKAR REDDYFile: FAMILY TREE OF INDRASHEKAR REDDY.pdf27 Nov 2024
FAMILY TREE OF SUNIL KUMARFile: FAMILY TREE OF SUNIL KUMAR.pdf27 Nov 2024
GIFT DEED DOC NO 2856-2018-19 - SY NO 98-5File: GIFT DEED DOC NO 2856-2018-19 - SY NO 98-5.pdf27 Nov 2024
GPA DATED 29 06 2018 DOC NO 203-18-19 - SY NO 98-3File: GPA DATED 29 06 2018 DOC NO 203-18-19 - SY NO 98-3.pdf27 Nov 2024
INTIMATION LETTER DATED 29-08-2006 - SY NO 98-2File: INTIMATION LETTER DATED 29-08-2006 - SY NO 98-2.pdf27 Nov 2024
JDA DATED 13-03-2006 DOC NO 19150-05-06- SY NO 98-2File: JDA DATED 13-03-2006 DOC NO 19150-05-06- SY NO 98-2.pdf27 Nov 2024
JDA DATED 29 06 2018 - DOC NO 2867-18-19 - SY NO 98File: JDA DATED 29 06 2018 - DOC NO 2867-18-19 - SY NO 98.pdf27 Nov 2024
KHATHA CERTIFICATE & EXTRACT -ANURADHA & SUNIL KUMAR - SY NO 98-2File: KHATHA CERTIFICATE & EXTRACT -ANURADHA & SUNIL KUMAR - SY NO 98-2.pdf27 Nov 2024
L R F [B E] 72-05-06 DATED 17- 02-2006File: L R F [B E] 72-05-06 DATED 17- 02-2006.pdf27 Nov 2024
MR NO 5-89-90File: MR NO 5-89-90.pdf27 Nov 2024
MR NO 41-94-95File: MR NO 41-94-95.pdf27 Nov 2024
MR NO 46-94-95 & 47-94-95File: MR NO 46-94-95 & 47-94-95.pdf27 Nov 2024
MR NO 49-94-95File: MR NO 49-94-95.pdf27 Nov 2024
MR NO 88-2005-06-1File: MR NO 88-2005-06-1.pdf27 Nov 2024
MR NO 88-2005-06-2File: MR NO 88-2005-06-2.pdf27 Nov 2024
MR NO 88-2005-06-3File: MR NO 88-2005-06-3.pdf27 Nov 2024
MR NO 88-2005-06-4File: MR NO 88-2005-06-4.pdf27 Nov 2024
MR NO 99-2004-05File: MR NO 99-2004-05.pdf27 Nov 2024
OM RECEIPTFile: OM RECEIPT.pdf27 Nov 2024
PANCHAYATH PARIKATHU dated 10-08-1982 (Incomplete)File: PANCHAYATH PARIKATHU dated 10-08-1982 (Incomplete).pdf27 Nov 2024
POA DATED 13-03-2006 DOC NO 1133-05-06- SY NO 98-2File: POA DATED 13-03-2006 DOC NO 1133-05-06- SY NO 98-2.pdf27 Nov 2024
POA DATED 13-03-2006File: POA DATED 13-03-2006.pdf27 Nov 2024
RECTIFICATION DEED DOC NO 6883-2005-06-New NO 98-5File: RECTIFICATION DEED DOC NO 6883-2005-06-New NO 98-5.pdf27 Nov 2024
SALE AGREEMENT DATED 13-03-2006 DOC NO 19162-005-06 - SY NO 98File: SALE AGREEMENT DATED 13-03-2006 DOC NO 19162-005-06 - SY NO 98.pdf27 Nov 2024
SALE DEED DOC NO 914-2013-14 - SY NO 98-2File: SALE DEED DOC NO 914-2013-14 - SY NO 98-2.pdf27 Nov 2024
SALE DEED DOC NO 13097-2004-05 - SY NO 98File: SALE DEED DOC NO 13097-2004-05 - SY NO 98.pdf27 Nov 2024
SALE DEED DOC NO 3620-05-06 - SY NO 98File: SALE DEED DOC NO 3620-05-06 - SY NO 98.pdf27 Nov 2024
Sale deed Doc No 7848File: Sale deed Doc No 7848.pdf27 Nov 2024
Sale Deed Doc No 7852File: Sale Deed Doc No 7852.pdf27 Nov 2024
SALE DEED DOC NO 7882-94-95File: SALE DEED DOC NO 7882-94-95.pdf27 Nov 2024
SALE DEED DOC NO 13106-2004-05 - SY NO 98File: SALE DEED DOC NO 13106-2004-05 - SY NO 98.pdf27 Nov 2024
SALE DEED DOC NO 13107-2004-05 - SY NO 98File: SALE DEED DOC NO 13107-2004-05 - SY NO 98.pdf27 Nov 2024
SURVEY DOCUMENTSFile: SURVEY DOCUMENTS.pdf27 Nov 2024
Tax Receipt - 2024-25File: Tax Receipt - 2024-25.pdf27 Nov 2024
Amenities & common area calculationFile: Amenities & common area calculation.pdf27 Nov 2024
AFFIDAVIT -File: AFFIDAVIT - CORRECTION DONE.pdf27 Nov 2024
BWSSB NOC Fee payment receiptFile: BWSSB NOC Fee payment receipt.pdf27 Nov 2024
1-1 AKRPL BS FY 23-24File: 1-1 AKRPL BS FY 23-24.pdf14 Oct 2024
1-2 Mahesh BS Certificate of MembershipFile: 1-2 Mahesh BS Certificate of Membership.pdf14 Oct 2024
1-3 Collection from AllotteesFile: 1-3 Collection from Allottees.pdf14 Oct 2024

How this compares with Bengaluru Urban

20%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep ADARSH ROSEWOOD on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmADARSH ROSEWOODOther 24Dot size: filed unitsN

Filed coordinates, straight-line distance. 24 registered projects within 2 km.

Builder: Akarsh Residence Pvt Ltd

Akarsh Residence Pvt Ltd has 3 registrations on RERA Karnataka, including Adarsh Palm Retreat Mayberry-Phase 1 and Adarsh Palm Retreat -Phase 3 Part B. Its filings declare 1 earlier project, none of them declared completed. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if ADARSH ROSEWOOD is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of ADARSH ROSEWOOD?

The registered promoter entity is Akarsh Residence Pvt Ltd, a company as per the filing. Its CIN U45201KA2009PTC051265 and GSTIN 29AAICA0191P1Z7 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in ADARSH ROSEWOOD?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at ADARSH ROSEWOOD?

The professionals named in the filing: Architect: VISHWARADHYA R E; Engineer: Rajesh M H; Chartered Accountant: Mahesh B S. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ADARSH ROSEWOOD?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; how the declared litigation on this registration affects your risk; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ADARSH ROSEWOOD. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ADARSH ROSEWOOD to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.