Home / Browse projects / Chitradurga, Karnataka / 1248 DU's AHP Project in Hiriyur CMC
1248 DU's AHP Project in Hiriyur CMC
By CMC Hiriyur
RG-KA-58640 · RERA PRM/KA/RERA/1256/329/PR/161122/005454 · Last updated on RERA Karnataka portal: 8 Nov 2022
Source: official RERA Karnataka filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
Saved.
1248 DU's AHP Project in Hiriyur CMC is a Residential/Group Housing project by CMC Hiriyur in Chitradurga, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1256/329/PR/161122/005454 on 16 Nov 2022. Possession is promised by 28 Mar 2025.
At a glance
Project
- Name1248 DU's AHP Project in Hiriyur CMC
- TypeResidential/Group Housing
- Location
- Hiriyur
- Chitradurga
- 577598
- Pincode577598
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1256/329/PR/161122/005454
- ReraGenie IDRG-KA-58640
Builder
- NameCMC Hiriyur
- Entity typeRajiv Gandhi Housing Corporation Limited
- Authorized SignatoryUmesh D
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on16 Nov 2022
- Promised completion28 Mar 2025
- Revised completionNone
- Buildings1 building record
- Documents filed78 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Block 1 | - | - | - | 12 | 0 | 12 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 8 Nov 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
Building:
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | - |
| Foundation footing work | - |
| Upto Plinth Level | - |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | - |
| Retaining wall (All types) | - |
| RCC or MS Framed structure | - |
| Masonry Construction | - |
| Plastering inside , outside & Ceiling | - |
| Joinery: Doors, Windows, Ventilators etc | - |
| Basic work of Water supply, Sanitary and Electrification | - |
| Dadoing, Skirting, Flooring, Tiles work (All types) | - |
| Railing and Grill fixing | - |
| Electrification, Water supply and Sanitary Finishing | - |
| Painting | - |
| Fire prevention and fire fighting fitting and fixture with network | Not applicable |
| Weather Proof work(tile,concrete) | Not applicable |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Elevation work | - |
| Internal and External work including landscapes as per sanctioned drawings | - |
Progress on shared amenities30
As on 8 Nov 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | - |
| Sewage and Drainage System | Yes | - |
| Water conservation/rain water harvesting/recharge of ground water | Yes | - |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Solid waste management and disposal | Yes | - |
| Emergency Evacuation services | Yes | - |
| Internal Roads & Footpaths | Yes | - |
| Electricity supply transformer and substation | Yes | - |
| Storm water drains | Yes | - |
| Use of renewable energy | Yes | - |
| Sewage Treatment Plant (STP) | Yes | - |
| Parks & Tree planting | Yes | - |
| Street Lighting | Yes | - |
| Electricity | Yes | - |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | No | Not applicable |
| Club House | No | Not applicable |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | No | Not applicable |
| Swimming Pool | No | Not applicable |
| Gym | No | Not applicable |
| Parks | No | Not applicable |
| Power Backup | No | Not applicable |
| Piped Gas | No | Not applicable |
| Water and Sanitation | No | Not applicable |
| Air Conditioning | No | Not applicable |
| Staircases | Yes | - |
| Lifts | No | Not applicable |
Land and ownership1
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Rajiv Gandhi Housing Corporation Bangalore | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 83.97 cr | - |
Certifying professionals and partners3
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Chetana Consortium G H Basavaraj |
| Engineer | Rangaswamiah |
| Chartered Accountant | Maveric Holdings and Investment Pvt Ltd |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed78
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1256/329/PR/161122/005454 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| planFile: drwaing 1248 tp.jpg | 8 Nov 2022 |
| NOC from GP and TP etterFile: NOC and TP letter 1248 hyr.pdf | 8 Nov 2022 |
| work orderFile: RGHCL 1248 WO.pdf | 8 Nov 2022 |
| RTC, survey 35 | - |
| Mutation, survey 35 | - |
| Encumbrance Certificate, survey 35 | - |
| Conversion/Alienation Order, survey 35 | - |
| Khatha, survey 35 | - |
| Registration CertificateFile: Hiriyur GST.jpg | - |
| GST Certificate | - |
| Certificate issued by CA Form 1File: 1248 Mevric.jpg | - |
| Certificate issued by Architect Form 2File: Chetana Consortium Udyam Registration Certificate.pdf | - |
| Certificate issued by Engineer Form 3File: Chetana Consortium Udyam Registration Certificate.pdf | - |
| Project Chartered Accountant | - |
| Project Engineer | - |
| Project Architect | - |
| AffidavitFile: F Hiriyur 20 acre 1248 DU's.pdf | - |
| Certificate from Chartered AccountFile: 1248 Mevric.jpg | - |
| Balance Sheet 2020 - 2021File: Chetana Consortium - GST Regi Certificate.pdf | - |
| Balance Sheet 2019 - 2020File: 1248 Mevric.jpg | - |
| Balance Sheet 2018 - 2019File: 1248 Mevric.jpg | - |
| Audited Profit and Loss Statement 2020 - 2021File: Chetana Consortium - GST Regi Certificate.pdf | - |
| Audited Profit and Loss Statement 2019 - 2020File: 1248 Mevric.jpg | - |
| Audited Profit and Loss Statement 2018 - 2019File: 1248 Mevric.jpg | - |
| Director's Report 2019 - 2020File: 1248 Mevric.jpg | - |
| Director's Report 2018 - 2019File: 1248 Mevric.jpg | - |
| Cash Flow Statement 2020 - 2021File: Chetana Consortium Udyam Registration Certificate.pdf | - |
| Cash Flow Statement 2019 - 2020File: 1248 Mevric.jpg | - |
| Auditor's Report 2020 - 2021File: 1248 Mevric.jpg | - |
| Auditor's Report 2019 - 2020File: 1248 Mevric.jpg | - |
| Auditor's Report 2018 - 2019File: 1248 Mevric.jpg | - |
| Income Tax Return Acknowledgement 2020 - 2021File: Chetana Consortium - GST Regi Certificate.pdf | - |
| Income Tax Return Acknowledgement 2019 - 2020File: 1248 Mevric.jpg | - |
| Income Tax Return Acknowledgement 2018 - 2019File: 1248 Mevric.jpg | - |
| WO 1248 | - |
| hiri adress | - |
| hiri adress | - |
| Approved plan | - |
| Approved plan | - |
| Approved plan | - |
| drawing plan | - |
| structural plan | - |
| floor plan | - |
| drawing plan | - |
| structural plan | - |
| Chetana Consortium - GST Regi Certificate | - |
| drawing plan | - |
| Approved plan | - |
| floor plan | - |
| drawing plan | - |
| RGHCL | - |
| floor plan | - |
| RGHCL | - |
| hiri com sign | - |
| WO 1248 | - |
| WO 1248 | - |
| hiri com sign | - |
| hiri adress | - |
| hiri com sign | - |
| hiri adress | - |
| hiri adress | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| WO 1248 | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Chitradurga
Computed across the 34 Chitradurga projects on ReraGenie, from their own filings.
Keep 1248 DU's AHP Project in Hiriyur CMC on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Chitradurga34 in Chitradurga
Hiriyur 624 dus
Hiriyur CMC
Construction of 1001 DU’s (G+2) in Sy no.22 Me
CMC Chitradurga
COMPOSITE HOUSING SCHEME AT CHALLAKERE
ASSISTANT EXECUTIVE ENGINEER
COMPOSITE HOUSING SCHEME AT KUDAPURA-NAYAKANAH
ASSISTANT EXECUTIVE ENGINEER
CONSTRUCTION OF 1127 GF UNITS IN CHALLAKERE TO
KSDB
CONSTRUCTION OF 327 GF UNITS IN HOLALKERE TOWN
KSDB
See every Chitradurga project, with the district possession charts
Builder: CMC Hiriyur
CMC Hiriyur has 1 registration on RERA Karnataka, including 1248 DU's AHP Project in Hiriyur CMC. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Chitradurga district page.
Frequently asked questions
What are my rights if 1248 DU's AHP Project in Hiriyur CMC is delayed beyond 28 Mar 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of 1248 DU's AHP Project in Hiriyur CMC?
The registered promoter entity is CMC Hiriyur, a rajiv gandhi housing corporation limited as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in 1248 DU's AHP Project in Hiriyur CMC?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at 1248 DU's AHP Project in Hiriyur CMC?
The professionals named in the filing: Architect: Chetana Consortium G H Basavaraj; Engineer: Rangaswamiah; Chartered Accountant: Maveric Holdings and Investment Pvt Ltd. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in 1248 DU's AHP Project in Hiriyur CMC?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback