Home / Developers / Viraj Properties (Now known as Viraj Properties & Real Estate Pvt Ltd) - Amogh Construction JV
Viraj Properties (Now known as Viraj Properties & Real Estate Pvt Ltd) - Amogh Construction JV: RERA track record
Others ยท attribution by exact filing name, entity resolution in progress
Viraj Properties (Now known as Viraj Properties & Real Estate Pvt Ltd) - Amogh Construction JV has 2 registrations in this build, including Siddhachal - A4 and Siddhachal - A1. Its filings disclose 10 earlier MahaRERA projects: 9 of 10 past projects completed on time. Litigation is declared on 1 of its registrations.
Projects in this build
| Project | Location | Units | Booked | Status |
|---|---|---|---|---|
| Siddhachal - A4 | Pune, Maharashtra | - | - | Completed |
| Siddhachal - A1 | Pune, Maharashtra | 40 | 62% | Registered |
Past projects, as disclosed in RERA filings
| Project | Promised completion | Actual completion | Delivery |
|---|---|---|---|
| Paritosh | 11 Aug 2003 | 11 Aug 2003 | On time |
| Kumar Padmaja | 4 Dec 2003 | 4 Dec 2003 | On time |
| Kumar Point | 17 Sep 2011 | 17 Sep 2011 | On time |
| Kumar Prerana | 23 Sep 2011 | 23 Sep 2011 | On time |
| Kumar Parisar | 13 Oct 2011 | 13 Oct 2011 | On time |
| Swapnapurti | 18 May 2013 | 18 May 2013 | On time |
| Kumar Shridhar | 12 Feb 2014 | 12 Feb 2014 | On time |
| Siddhachal - A2 and A3 | 28 Sep 2016 | 28 Sep 2016 | On time |
| Kumar Shiloh | 20 Oct 2018 | 20 Oct 2018 | On time |
| Siddhachal - A4 P52100018775 | 30 Dec 2023 | 18 Jul 2024 | +7 months |
Frequently asked questions
How do I verify Viraj Properties (Now known as Viraj Properties & Real Estate Pvt Ltd) - Amogh Construction JV as a legal entity before signing?
Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.
How should I use this delivery record when booking with Viraj Properties (Now known as Viraj Properties & Real Estate Pvt Ltd) - Amogh Construction JV?
Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.
Does the declared litigation make Viraj Properties (Now known as Viraj Properties & Real Estate Pvt Ltd) - Amogh Construction JV unsafe to buy from?
Not by itself. Litigation on a registration ranges from a boundary dispute to an allottee case about delay; what matters is the case type, which court or forum, and whether it touches the land title of the project you are buying. The case list is in each project's filed documents. Treat litigation as a question to resolve in writing before booking, not as a verdict either way.
Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.