VIKAS VILAS BHALGAT: RERA track record
GSTIN 27AAUPB3631J1ZK · Individual · attribution by exact filing name, entity resolution in progress
VIKAS VILAS BHALGAT has 9 registrations on MahaRERA, including KUBER KUNJBAN and KUBER IMPERIA. Its filings disclose 7 earlier MahaRERA projects: declares 4 of 4 past projects completed on time.
Projects by this developer
Showing all 9 projects.
Largest first, by the unit count in the filing.
| Project | Location | Units | Booked | Registered | Status |
|---|---|---|---|---|---|
| THE VANTAGE A, B, C & DPR1260002601066 | WAKAD, Pune, 411057 | 96 | 0% | 7 Jul 2026 | Registered |
| KUBER ANTONIA A WINGP52100056209 | WAKAD, Pune, 411057 | 79 | 14% | 21 May 2024 | Registered |
| KUBER ANTONIAP52100035197 | WAKAD, Pune, 411057 | 60 | 95% | 10 May 2022 | Registration lapsed |
| KUBER ANTONIA C WINGP52100053142 | NEXT TO HOTEL TIPTOP, Pune, 411057 | 60 | 88% | 17 Oct 2023 | Completed |
| KUBER PROPERTIES KUBER ANTONIA BPR1260002501797 | wakad, Pune, 411057 | 40 | 0% | 16 Dec 2025 | Registered |
| THE VANTAGE EPC1260002600820 | Wakad, Pune, 411057 | 6 | 0% | 17 Jun 2026 | Registered |
| KUBER IMPERIAP52100016321 | WAKAD, Pune, 411057 | - | - | 3 May 2018 | Registration lapsed |
| KUBER KUNJBANP52100001616 | Pune (M Corp.), Pune, 411004 | - | - | 29 Jul 2017 | Completed |
| KUBER MUDRA MEADOWSP52100077821 | MANCHAR, Pune, 410503 | - | - | 7 Nov 2024 | Registered |
What this promoter declares as its own experience
VIKAS VILAS BHALGAT declares experience on 7 earlier projects. 6 of them carry a registration number we could match on MahaRERA, all under this promoter's own name.
6 of these declarations can be compared with the dates those projects' own registrations hold. On 1, the date given as the original completion date is the REVISED deadline that project carries after an extension rather than its original one. That changes the arithmetic on 1 of the 3 completions recorded here as on time: measured against the original deadline the register itself holds, that one was finished after it. A completion date is also recorded against 2 registrations MahaRERA does not show as completed. A registration lapses when a promoter files neither a completion nor an extension, so that can mean the completion was never filed rather than that the project was not finished.
From the promoter experience table each promoter files with MahaRERA, matched to the register by registration number. A declaration naming another promoter's project is a claim of involvement, and involvement takes several shapes: a parent and its project company, one firm re-registering under a second name, or a joint venture between two separate developers. We publish the claim as filed and do not treat it as proof that the entities are one builder.
Past projects, as disclosed in RERA filings
| Project | Promised completion | Actual completion | Delivery |
|---|---|---|---|
| KUBER MADHUKOSH | 18 Jun 2014 | 18 Jun 2014 | On time |
| KUBER KUNJBAN P52100001616 | 25 Jul 2019 | 18 Jul 2018 | On time |
| KUBER IMPERIA P52100016321 | 24 Apr 2024 | 26 Dec 2022 | On time |
| KUBER ANTONIA P52100035197 | 23 Feb 2026 | 31 Jan 2026 | On time |
| KUBER ANTONIA A WING P52100056209 | 24 Apr 2027 | Not completed yet | Ongoing |
| KUBER PROPERTIES KUBER ANTONIA B PR1260002501797 | 24 Apr 2027 | Not completed yet | Ongoing |
| KUBER MUDRA MEADOWS P52100077821 | 29 Aug 2027 | Not completed yet | Ongoing |
Frequently asked questions
How do I verify VIKAS VILAS BHALGAT as a legal entity before signing?
Your agreement for sale must name the exact entity registered for the project, not a group brand. Cross-check its GSTIN 27AAUPB3631J1ZK on the MCA and GST portals before signing anything. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.
How should I use this delivery record when booking with VIKAS VILAS BHALGAT?
Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.
The record above looks clean. What should I still check?
A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.