Veer Global Infraconstruction Limited: RERA track record

CIN L45309MH2012PLC225939 · Company · attribution by exact filing name, entity resolution in progress

Veer Global Infraconstruction Limited has 10 registrations on MahaRERA, including VEER 2 and VEER SPLENDOR. Its filings disclose 6 earlier MahaRERA projects: declares 3 of 3 past projects completed on time. Litigation is declared on 1 of its registrations.

10RERA registrations
6Past projects disclosed
on timeMedian delivery slip
1Registrations with litigation
Follow this developer. An email when Veer Global Infraconstruction Limited registers a new project on MahaRERA, and when the filings of their existing projects change: new sales, moved possession dates, extensions, complaints. Runs 12 months, no auto-renew. Follow · Rs 999 / 12 months

Projects by this developer

Showing all 10 projects.

Largest first, by the unit count in the filing.

ProjectLocationUnitsBookedRegisteredStatus
AYODHYA NAGARI - 2PR1240002500834GOKHIVARE, Palghar, 4012082760%18 Sep 2025Registered
VEER 11P99000034206UMROLI EAST, Palghar, 4014048938%25 Mar 2022Registered
AYODHYA NAGARI -1PR1240002502919GOKHIVARE, Palghar, 401208840%18 Mar 2026Registered
Veer OneP99000031900Vasai East, Palghar, 40120810%22 Nov 2021Registered
PARASNATH TOWNSHIPP99000013822umroli, Palghar, 401404--27 Oct 2017Registered
VEER - 2, Building No.3P99000028513UMROLI, Palghar, 401404--8 Mar 2021Completed
VEER - 4P99000015602UMROLI EAST, Palghar, 401404--12 Mar 2018Completed
VEER 10P99000023346Umroli East, Palghar, 401404--12 Dec 2019Registration lapsed
VEER 2P99000007946umroli east, Palghar, 401404--18 Aug 2017Completed
VEER SPLENDORP99000011282Nalasopara east, Palghar, 401209--31 Aug 2017Completed

What this promoter declares as its own experience

Veer Global Infraconstruction Limited declares experience on 6 earlier projects. 5 of them carry a registration number we could match on MahaRERA, all under this promoter's own name.

5 of these declarations can be compared with the dates those projects' own registrations hold. On 2, the date given as the original completion date is the REVISED deadline that project carries after an extension rather than its original one. That changes the arithmetic on 1 of the 2 completions recorded here as on time: measured against the original deadline the register itself holds, that one was finished after it.

From the promoter experience table each promoter files with MahaRERA, matched to the register by registration number. A declaration naming another promoter's project is a claim of involvement, and involvement takes several shapes: a parent and its project company, one firm re-registering under a second name, or a joint venture between two separate developers. We publish the claim as filed and do not treat it as proof that the entities are one builder.

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
VEER - 4
P99000015602
30 Sep 202030 Sep 2020On time
VEER 2
30 Dec 202130 Dec 2021On time
VEER SPLENDOR
P99000011282
30 Dec 202230 Dec 2022On time
VEER 11
P99000034206
31 Dec 2025Not completed yetCertificate Signed
Veer One
P99000031900
31 Dec 2027Not completed yetCertificate Signed
PARASNATH TOWNSHIP
P99000013822
31 Dec 2027Not completed yetCertificate Signed

Frequently asked questions

How do I verify Veer Global Infraconstruction Limited as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. Cross-check its CIN L45309MH2012PLC225939 on the MCA and GST portals before signing anything. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with Veer Global Infraconstruction Limited?

Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

Does the declared litigation make Veer Global Infraconstruction Limited unsafe to buy from?

Not by itself. Litigation on a registration ranges from a boundary dispute to an allottee case about delay; what matters is the case type, which court or forum, and whether it touches the land title of the project you are buying. The case list is in each project's filed documents. Treat litigation as a question to resolve in writing before booking, not as a verdict either way.

Spotted a project attributed to the wrong developer, or something else wrong on this page? Projects are grouped by the promoter name as filed, so a firm that registers under two spellings can split across two pages. Tell us and we will check it against the filings.

Report an errorShare feedback

Data from official MahaRERA filings. How we handle corrections is on the about page.

Report an error or share feedback