Home / Developers / VAASTU Builders & Developers

VAASTU Builders & Developers: RERA track record

Partnership ยท attribution by exact filing name, entity resolution in progress

VAASTU Builders & Developers has 6 registrations in this build, including VAASTU Prathamesh and VAASTU Sai. Its filings disclose 5 earlier MahaRERA projects: 1 of 5 past projects completed on time.

6Registrations in this build
5Past projects disclosed
+7 monthsMedian delivery slip
0Registrations with litigation

Projects in this build

ProjectLocationUnits BookedStatus
VAASTU PrathameshRaigarh, Maharashtra--Completed
VAASTU SaiRaigarh, Maharashtra--Completed
VAASTU ANKITARaigarh, Maharashtra2893%Registered
VAASTU ADARSHRaigarh, Maharashtra--Completed
VAASTU RUKMINIRaigarh, Maharashtra--Completed
VAASTU VITTHALRaigarh, Maharashtra--Registration lapsed

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
Tejas Omkar
31 Dec 201510 Jan 2017+12 months
Tejas Palak
30 Jun 201623 May 2017+11 months
Tejas Ojas
30 Jun 20161 Jun 2016On time
Tejsa Siddharth
31 Oct 201613 Jun 2017+7 months
VAASTU Acumen
31 May 201724 Jul 2017+2 months

Frequently asked questions

How do I verify VAASTU Builders & Developers as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with VAASTU Builders & Developers?

Add the median slip shown above to any possession date this promoter quotes you, and plan your rent, loan and school-year decisions around that stressed date. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

The record above looks clean. What should I still check?

A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.

Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.