SIDDHI DEVELOPERS: RERA track record
GSTIN 27AEVFS9085A1ZE · Partnership · attribution by exact filing name, entity resolution in progress
SIDDHI DEVELOPERS has 10 registrations on MahaRERA, including SIDDHI COMPLEX and Pragati Residency. Its filings disclose 3 earlier MahaRERA projects: declares 2 of 3 past projects completed on time.
Projects by this developer
Showing all 10 projects.
Largest first, by the unit count in the filing.
| Project | Location | Units | Booked | Registered | Status |
|---|---|---|---|---|---|
| SIDDHIVINAYAK ENCLAVEP51700052057 | BHAYANDER EAST, Thane, 401105 | 126 | 17% | 19 Jul 2023 | Registered |
| ROYAL PALM PHASE - 1P51700052162 | WASHIND, Thane, 421601 | 95 | 21% | 27 Jul 2023 | Registered |
| Padma Vishwa IconPC1220002501039 | College Road, Nashik, 422005 | 68 | 0% | 1 Oct 2025 | Registered |
| SIDDHI PARKP51600027607 | OZHAR, Nashik, 422206 | 33 | 48% | 23 Dec 2020 | Completed |
| 24 PRIMROSEP51500051680 | GARKHEDA, Aurangabad, 431005 | 24 | 58% | 27 Jun 2023 | Registered |
| GANGA SIDDHI SQUAREP51500033636 | DARGA ROAD, Aurangabad, 431005 | - | - | 2 Mar 2022 | Completed |
| Pragati ResidencyP53000015144 | Near New Polytechnic College, Kolhapur, 416005 | - | - | 2 Feb 2018 | Completed |
| Sai EnclaveP51100078770 | Nanded, Nanded, 431746 | - | - | 13 Jan 2025 | Registered |
| SAMARTH RESIDENCYP52000010559 | Ulawe, Raigarh, 410206 | - | - | 31 Aug 2017 | Completed |
| SIDDHI COMPLEXP52100004668 | PUNE, Pune, 411046 | - | - | 9 Aug 2017 | Completed |
What this promoter declares as its own experience
SIDDHI DEVELOPERS declares experience on 3 earlier projects. One carries a registration number we could match on MahaRERA, under this promoter's own name.
One of these declarations can be compared with the dates that project's own registration holds. It gives the same original completion date that registration holds.
From the promoter experience table each promoter files with MahaRERA, matched to the register by registration number. A declaration naming another promoter's project is a claim of involvement, and involvement takes several shapes: a parent and its project company, one firm re-registering under a second name, or a joint venture between two separate developers. We publish the claim as filed and do not treat it as proof that the entities are one builder.
Past projects, as disclosed in RERA filings
| Project | Promised completion | Actual completion | Delivery |
|---|---|---|---|
| Sai Siddhi | 15 Sep 2015 | 20 Sep 2016 | +12 months |
| SHREE HARI DARSHAN BUILDING NO-7 | 30 Dec 2024 | 16 Mar 2021 | On time |
| GANGA SIDDHI SQUARE P51500033636 | 31 Mar 2025 | 9 Sep 2023 | On time |
Frequently asked questions
How do I verify SIDDHI DEVELOPERS as a legal entity before signing?
Your agreement for sale must name the exact entity registered for the project, not a group brand. Cross-check its GSTIN 27AEVFS9085A1ZE on the MCA and GST portals before signing anything. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.
How should I use this delivery record when booking with SIDDHI DEVELOPERS?
Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.
The record above looks clean. What should I still check?
A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.