Home / Developers / Shubh Housing
Shubh Housing: RERA track record
Partnership ยท attribution by exact filing name, entity resolution in progress
Shubh Housing has 10 registrations on MahaRERA, including SHIV ZEN WORLD - PHASE I and SHUBH SHAGUN. Its filings disclose 7 earlier MahaRERA projects: declares 4 of 4 past projects completed on time.
Projects by this developer
Showing all 10 projects.
Largest first, by the unit count in the filing.
| Project | Location | Units | Booked | Registered | Status |
|---|---|---|---|---|---|
| Shubh Tristar Wing-AP52100052695 | Mundhwa, Pune, 411014 | 112 | 76% | 22 Sep 2023 | Registered |
| SHREEJI LANDMARK PHASE IIP51700052645 | Village Shirgaon, Taluka Ambernath, Badlapur, Thane, 421503 | 111 | 15% | 15 Sep 2023 | Registered |
| SHIV ZEN WORLD PHASE IVPR1263032601891 | Manjari Budruk, Pune, 412307 | 94 | 0% | 11 Sep 2026 | Registered |
| Shubh Tristar Wing CPM1263032600557 | Mundhwa North, Pune, 411036 | 78 | 0% | 29 May 2026 | Registered |
| Atulyam-Inclusive HousingP52100053569 | Mundhwa, Pune, 411014 | 28 | 0% | 10 Nov 2023 | Registered |
| Shubh Tristar Wing-BP52100055763 | Mundhwa, Pune, 411014 | 9 | 22% | 16 Apr 2024 | Registered |
| SHIV ZEN WORLD - PHASE IP52100007579 | MANJARI Bk, Pune, 412307 | - | - | 17 Aug 2017 | Completed |
| Shiv Zen World Phase IIP52100022397 | Manjari, Pune, 412307 | - | - | 19 Sep 2019 | Completed |
| SHIV ZEN WORLD PHASE IIIP52100031835 | BEHIND VISTA LUXURIA, Pune, 412307 | - | - | 22 Nov 2021 | Registration lapsed |
| SHUBH SHAGUNP52100018614 | Kharadi, 411014 | - | - | 22 Nov 2018 | Registered |
What this promoter declares as its own experience
Shubh Housing declares experience on 7 earlier projects. 6 of them carry a registration number we could match on MahaRERA, all under this promoter's own name.
6 of these declarations can be compared with the dates those projects' own registrations hold. Every one of them gives the same original completion date its registration holds. A completion date is also recorded against 1 registration MahaRERA does not show as completed. A registration lapses when a promoter files neither a completion nor an extension, so that can mean the completion was never filed rather than that the project was not finished.
From the promoter experience table each promoter files with MahaRERA, matched to the register by registration number. A declaration naming another promoter's project is a claim of involvement, and involvement takes several shapes: a parent and its project company, one firm re-registering under a second name, or a joint venture between two separate developers. We publish the claim as filed and do not treat it as proof that the entities are one builder.
Past projects, as disclosed in RERA filings
| Project | Promised completion | Actual completion | Delivery |
|---|---|---|---|
| SHIV ZEN WORLD - PHASE I P52100007579 | 30 Dec 2021 | 30 Dec 2021 | On time |
| Shiv Zen World Phase II P52100022397 | 30 Dec 2023 | 30 Dec 2023 | On time |
| SHIV ZEN WORLD PHASE III P52100031835 | 1 Aug 2025 | 1 Aug 2025 | On time |
| Shubh Shagun | 31 Dec 2026 | 31 Mar 2022 | On time |
| Shubh Tristar Wing-A P52100052695 | 31 Dec 2027 | Not completed yet | Ongoing |
| Atulyam-Inclusive Housing P52100053569 | 31 Dec 2027 | Not completed yet | Ongoing |
| Shubh Tristar Wing-B P52100055763 | 31 Dec 2028 | Not completed yet | Ongoing |
Frequently asked questions
How do I verify Shubh Housing as a legal entity before signing?
Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.
How should I use this delivery record when booking with Shubh Housing?
Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.
The record above looks clean. What should I still check?
A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.