ReraGenieLog inGet a buyer report

Home / Developers / RANADE REALTORS LLP

RANADE REALTORS LLP: RERA track record

Partnership ยท attribution by exact filing name, entity resolution in progress

RANADE REALTORS LLP has 10 registrations in this build, including PARIMAL and MAYANK. Its filings disclose 5 earlier MahaRERA projects: 3 of 5 past projects completed on time.

10Registrations in this build
5Past projects disclosed
on timeMedian delivery slip
0Registrations with litigation

Projects in this build

ProjectLocationUnits BookedStatus
PARIMALPune, Maharashtra--Completed
MAYANKPune, Maharashtra--Completed
ASEEMPune, Maharashtra--Completed
Seeta-GovindPune, Maharashtra4753%Completed
SHARAWATI APARTMENTSPune, Maharashtra1839%Completed
YASHODHANPune, Maharashtra1850%Completed
BUNIYADPune, Maharashtra1331%Completed
Sindhu ApartmentsPune, Maharashtra1520%Registered
Vishwanjali LaxmiPune, Maharashtra2025%Registered
Shwetambarishree Co-operative Housing Society LimitedPune, Maharashtra1060%Registered

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
EESHA RESIDENCES
21 Sep 201416 Oct 2014+1 months
NAVASHISH APARTMENTS
30 Nov 201814 Dec 2018On time
MADHUMITA APARTMENTS
28 Feb 201914 Sep 2018On time
RUCHA PHASE I
31 May 20195 Nov 2018On time
RUCHA PHASE II
31 May 201917 May 2019On time

Frequently asked questions

How do I verify RANADE REALTORS LLP as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with RANADE REALTORS LLP?

Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

The record above looks clean. What should I still check?

A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.

Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.