CIN U41001MH2023PTC402600 · GSTIN 27AANCP7511K1ZZ · Company · attribution by exact filing name, entity resolution in progress

Puranik Tokyo Bay Private Limited has 6 registrations on MahaRERA, including Tokyo Bay Phase - 2A and Tokyo Bay Phase - 1. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Litigation is declared on 1 of its registrations.

6RERA registrations
1Past projects disclosed
on timeMedian delivery slip
1Registrations with litigation
Follow this developer. An email when Puranik Tokyo Bay Private Limited registers a new project on MahaRERA, and when the filings of their existing projects change: new sales, moved possession dates, extensions, complaints. Runs 12 months, no auto-renew. Follow · Rs 999 / 12 months

Projects by this developer

Showing all 6 projects.

Largest first, by the unit count in the filing.

ProjectLocationUnitsBookedRegisteredStatus
IKIGAI - Phase 1P51700006605Ghodbunder Road, Thane, 40061562378%14 Aug 2017Registered
IKIGAI Phase 2P51700051124Village Owale, Taluka and District Thane, Thane, 40061530564%30 May 2023Registered
Tokyo Bay Phase 2BPR1332022500196Near Euro School, Thane, 40061526853%3 Jul 2025Registered
Tokyo Bay Phase - 2AP51700000520Near Aarambh Project, Thane, 40061520397%18 Jul 2017Registration lapsed
Tokyo Bay Phase - 1P51700000618Thane (M Corp.), Thane, 400615--18 Jul 2017Completed
Tokyo Bay Phase - 2CP51700020265Near Aarambh Project, Thane, 400615--30 Mar 2019De-registered

What this promoter declares as its own experience

Puranik Tokyo Bay Private Limited declares experience on 1 earlier project. One carries a registration number we could match on MahaRERA, under this promoter's own name.

One of these declarations can be compared with the dates that project's own registration holds. It gives the same original completion date that registration holds.

From the promoter experience table each promoter files with MahaRERA, matched to the register by registration number. A declaration naming another promoter's project is a claim of involvement, and involvement takes several shapes: a parent and its project company, one firm re-registering under a second name, or a joint venture between two separate developers. We publish the claim as filed and do not treat it as proof that the entities are one builder.

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
Tokyo Bay Phase - 1
P51700000618
30 Oct 202318 May 2022On time

Frequently asked questions

How do I verify Puranik Tokyo Bay Private Limited as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. Cross-check its CIN U41001MH2023PTC402600 and GSTIN 27AANCP7511K1ZZ on the MCA and GST portals before signing anything. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with Puranik Tokyo Bay Private Limited?

Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

Does the declared litigation make Puranik Tokyo Bay Private Limited unsafe to buy from?

Not by itself. Litigation on a registration ranges from a boundary dispute to an allottee case about delay; what matters is the case type, which court or forum, and whether it touches the land title of the project you are buying. The case list is in each project's filed documents. Treat litigation as a question to resolve in writing before booking, not as a verdict either way.

Spotted a project attributed to the wrong developer, or something else wrong on this page? Projects are grouped by the promoter name as filed, so a firm that registers under two spellings can split across two pages. Tell us and we will check it against the filings.

Report an errorShare feedback

Data from official MahaRERA filings. How we handle corrections is on the about page.