Home / Developers / PSQUARE BUILDERS LLP
PSQUARE BUILDERS LLP: RERA track record
Partnership ยท attribution by exact filing name, entity resolution in progress
PSQUARE BUILDERS LLP has 10 registrations in this build, including NYATI ELAN WEST I and NYATI ELAN COMMERCIAL. Its filings disclose 7 earlier MahaRERA projects: 7 of 7 past projects completed on time.
Projects in this build
| Project | Location | Units | Booked | Status |
|---|---|---|---|---|
| NYATI ELAN WEST I | Pune, Maharashtra | - | - | Completed |
| NYATI ELAN COMMERCIAL | Pune, Maharashtra | - | - | Completed |
| NYATI ELAN WEST II | Pune, Maharashtra | - | - | Completed |
| NYATI ELAN SOUTH EAST I | Pune, Maharashtra | - | - | Completed |
| Nyati Elan West III | Pune, Maharashtra | - | - | Completed |
| NYATI ELAN CENTRAL I | Pune, Maharashtra | - | - | Completed |
| NYATI ELAN SOUTH I | Pune, Maharashtra | - | - | Completed |
| NYATI ELAN CENTRAL II | Pune, Maharashtra | - | - | Completed |
| NYATI ELAN CENTRAL III | Pune, Maharashtra | - | - | Registration lapsed |
| NYATI ELAN SOUTH II | Pune, Maharashtra | - | - | Registration lapsed |
Past projects, as disclosed in RERA filings
| Project | Promised completion | Actual completion | Delivery |
|---|---|---|---|
| Nyati Elan- South-East | 30 Jun 2017 | 10 Oct 2016 | On time |
| Nyati Elan- North | 30 Jun 2017 | 10 Oct 2016 | On time |
| Nyati Elan West I | 30 Jun 2018 | 16 Feb 2018 | On time |
| Nyati Elan Commercial | 31 Jan 2019 | 23 Jan 2019 | On time |
| Nyati Elan West II | 30 Sep 2019 | 30 Sep 2019 | On time |
| Nyati Elan South East I | 30 Sep 2021 | 30 Sep 2020 | On time |
| NYATI ELAN CENTRAL I P52100029005 | 30 Apr 2024 | 27 Mar 2024 | On time |
Frequently asked questions
How do I verify PSQUARE BUILDERS LLP as a legal entity before signing?
Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.
How should I use this delivery record when booking with PSQUARE BUILDERS LLP?
Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.
The record above looks clean. What should I still check?
A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.
Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.