PRASANNA DEVELOPERS: RERA track record

Partnership ยท attribution by exact filing name, entity resolution in progress

PRASANNA DEVELOPERS has 7 registrations in this build, including PRASANNA I SQUARE and PRASANNA TULSHIBAUG. Its filings disclose 6 earlier MahaRERA projects: 0 of 2 past projects completed on time. Litigation is declared on 3 of its registrations.

7Registrations in this build
6Past projects disclosed
+41 monthsMedian delivery slip
3Registrations with litigation

Projects in this build

ProjectLocationUnits BookedStatus
PRASANNA I SQUAREPune, Maharashtra--Completed
PRASANNA TULSHIBAUGPune, Maharashtra4531%Registration lapsed
VTP Sierra Phase1Pune, Maharashtra51598%Registration lapsed
VTP SIERRA PHASE-2Pune, Maharashtra36198%Registered
VTP VervePune, Maharashtra70192%Registered
Moreshwar Park 7Nagpur, Maharashtra330%Completed
VTP SIERRA PHASE 3Pune, Maharashtra15284%Registered

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
Maruti Park 2
22 Dec 202210 Jan 2024+13 months
Moreshwar Park 5
27 Mar 202331 Dec 2028+69 months
VTP Sierra Phase1
P52100028378
30 Jun 2026Not completed yetOngoing
VTP SIERRA PHASE-2
P52100029394
31 Dec 2026Not completed yetOngoing
VTP SIERRA PHASE 3
P52100076811
30 Jun 2028Not completed yetOngoing
VTP Verve
P52100031556
31 Dec 2029Not completed yetOngoing

Frequently asked questions

How do I verify PRASANNA DEVELOPERS as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with PRASANNA DEVELOPERS?

Add the median slip shown above to any possession date this promoter quotes you, and plan your rent, loan and school-year decisions around that stressed date. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

Does the declared litigation make PRASANNA DEVELOPERS unsafe to buy from?

Not by itself. Litigation on a registration ranges from a boundary dispute to an allottee case about delay; what matters is the case type, which court or forum, and whether it touches the land title of the project you are buying. The case list is in each project's filed documents. Treat litigation as a question to resolve in writing before booking, not as a verdict either way.

Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.