Home / Developers / PANCHRATNA DEVELOPERS
PANCHRATNA DEVELOPERS: RERA track record
Partnership ยท attribution by exact filing name, entity resolution in progress
PANCHRATNA DEVELOPERS has 5 registrations in this build, including 1CITYPRIDE and NISARG RESIDENCY. Its filings disclose 7 earlier MahaRERA projects: 0 of 5 past projects completed on time.
Projects in this build
| Project | Location | Units | Booked | Status |
|---|---|---|---|---|
| 1CITYPRIDE | Ahmednagar, Maharashtra | - | - | Completed |
| NISARG RESIDENCY | Palghar, Maharashtra | - | - | Registration lapsed |
| PANCHRATNA DEVELOPERS B WING | Pune, Maharashtra | - | - | Registration lapsed |
| JAY TULJABHAWANI PARK | Satara, Maharashtra | 64 | 34% | Registered |
| PANCHRATNA SAPPHIRE | Thane, Maharashtra | 133 | 29% | Registered |
Past projects, as disclosed in RERA filings
| Project | Promised completion | Actual completion | Delivery |
|---|---|---|---|
| Madhumala Sanskrutik Bhavan | 15 Jan 2018 | 15 Mar 2018 | +2 months |
| Bhari Park | 31 Mar 2019 | 14 Aug 2019 | +4 months |
| Shri Sidhivinayak empire | 31 May 2019 | 30 Sep 2019 | +4 months |
| YASH PLAZA | 31 Jan 2020 | 31 May 2020 | +4 months |
| BANGLOW FOR SANJAY BAGAL | 30 Jun 2020 | 31 Aug 2020 | +2 months |
| PRISTINE VIEWS P51700056171 | 31 Dec 2025 | Not completed yet | Ongoing |
| PANCHRATNA SAPPHIRE P51700050689 | 31 Mar 2026 | Not completed yet | Ongoing |
Frequently asked questions
How do I verify PANCHRATNA DEVELOPERS as a legal entity before signing?
Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.
How should I use this delivery record when booking with PANCHRATNA DEVELOPERS?
Add the median slip shown above to any possession date this promoter quotes you, and plan your rent, loan and school-year decisions around that stressed date. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.
The record above looks clean. What should I still check?
A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.
Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.