Home / Developers / OMKAR ENTERPRISES

OMKAR ENTERPRISES: RERA track record

Partnership ยท attribution by exact filing name, entity resolution in progress

OMKAR ENTERPRISES has 15 registrations on MahaRERA, including OMKAR ENCLAVE and EKNATH TOWER. Its filings disclose 2 earlier MahaRERA projects: declares 0 of 1 past projects completed on time.

15RERA registrations
2Past projects disclosed
+31 monthsMedian delivery slip
0Registrations with litigation
Follow this developer. An email when OMKAR ENTERPRISES registers a new project on MahaRERA, and when the filings of their existing projects change: new sales, moved possession dates, extensions, complaints. Runs 12 months, no auto-renew. Follow · Rs 999 / 12 months

Projects by this developer

Showing all 15 projects.

Largest first, by the unit count in the filing.

ProjectLocationUnitsBookedRegisteredStatus
OMKAR PLANETP51700029084NERUL, Thane, 40070616415%26 Apr 2021Registered
OMKAR PLAZA D AND E WINGPM1331012600352BADLAPUR, Thane, 421503980%6 May 2026Registered
TRISHAN ENCLAVEP51700052828UMBARDE VILLAGE, KALYAN WEST, Thane, 421301350%5 Oct 2023Registered
Shri Jiveshwar ApartmentP51700056234Kulgaon, Thane, 421503307%22 May 2024Registered
Shree Datta Narhari ApartmentP51700049472Badlapur, Thane, 4215032080%15 Feb 2023Registration lapsed
OMKAR HEIGHTSP51700050864NEAR GADGE MAHARAJ HOSPITAL, SAINATH NAGAR, Thane, 42160120%9 May 2023Registered
EKNATH HEIGHTSP51700013019KATEMANEVALI, Thane, 421306--12 Sep 2017Registration lapsed
EKNATH HEIGHTS - 1P51700030031VITTHALWADI, Thane, 421306--26 Jul 2021Completed
EKNATH TOWERP51700012364Kalyan-Dombivali (M Corp.), Thane, 421201--1 Sep 2017Registration lapsed
LAXMI KRUPAP51700017824KABAD AALI, TEMBI NAKA, Thane, 400601--18 Sep 2018Registration lapsed
NUTAN OMKAR VIHARP51700029564SHIRGAON, Thane, 421503--4 Jun 2021Completed
OMKAR ENCLAVEP51700007523Kalyan-Dombivali (M Corp.), Thane, 421201--17 Aug 2017Completed
OMKAR PLAZAP51700015419SHIRGAON, Thane, 421503--23 Feb 2018Registration lapsed
OMKAR PLAZAP51700045862Village Shirgaon, Thane, 421503--15 Jun 2022Registration lapsed
RAVI OMKAR ESTATEP99000078719VASAI EAST, Palghar, 401208--7 Jan 2025Registered

What this promoter declares as its own experience

OMKAR ENTERPRISES declares experience on 2 earlier projects. One carries a registration number we could match on MahaRERA, under this promoter's own name.

One of these declarations can be compared with the dates that project's own registration holds. It gives the same original completion date that registration holds.

From the promoter experience table each promoter files with MahaRERA, matched to the register by registration number. A declaration naming another promoter's project is a claim of involvement, and involvement takes several shapes: a parent and its project company, one firm re-registering under a second name, or a joint venture between two separate developers. We publish the claim as filed and do not treat it as proof that the entities are one builder.

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
SHREE SAMARTHKURPA COMPLEX
1 Apr 201431 Oct 2016+31 months
OMKAR PLAZA
P51700045862
31 Dec 2025Not completed yetOngoing

Frequently asked questions

How do I verify OMKAR ENTERPRISES as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with OMKAR ENTERPRISES?

Add the median slip shown above to any possession date this promoter quotes you, and plan your rent, loan and school-year decisions around that stressed date. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

The record above looks clean. What should I still check?

A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.

Spotted a project attributed to the wrong developer, or something else wrong on this page? Projects are grouped by the promoter name as filed, so a firm that registers under two spellings can split across two pages. Tell us and we will check it against the filings.

Report an errorShare feedback

Data from official MahaRERA filings. How we handle corrections is on the about page.

Report an error or share feedback

About the OMKAR ENTERPRISES developer page. Projects are grouped by the promoter name as filed, so a wrongly attributed project is the most useful thing to report.

We read every report. We cannot promise a reply to each one.