NEELKANTH ASSOCIATES: RERA track record

GSTIN 27AAIFN2122N1Z5 · Partnership · attribution by exact filing name, entity resolution in progress

NEELKANTH ASSOCIATES has 7 registrations in this build, including NEELKANTH ROYALE PALMS - F WING PHASE II and SHREE RAM KALPANA. Its filings disclose 8 earlier MahaRERA projects: 4 of 6 past projects completed on time.

7Registrations in this build
8Past projects disclosed
on timeMedian delivery slip
0Registrations with litigation

Projects in this build

ProjectLocationUnits BookedStatus
NEELKANTH ROYALE PALMS - F WING PHASE IIThane, Maharashtra1087%Registered
SHREE RAM KALPANARaigarh, Maharashtra--Completed
AJINKYARaigarh, Maharashtra--Completed
JANKIRaigarh, Maharashtra--Registration lapsed
SamarthRaigarh, Maharashtra6844%Registered
SnehshreeRaigarh, Maharashtra--Completed
AjitRaigarh, Maharashtra330%Registered

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
NEELKANTH ROYALE PAMS PHASE I
29 Apr 201729 Apr 2017On time
AJINKYA
9 Jan 202030 Oct 2020+10 months
AJINKYA
P52000018250
15 Dec 202130 Oct 2020On time
NAIVEDYA
P52000001344
15 Mar 202210 Aug 2021On time
JANKI
P52000048098
9 Dec 202423 Jan 2025+1 months
Snehshree
P52000048715
31 May 20259 Dec 2024On time
Samartha
P52000048483
30 Jun 2026Not completed yetOngoing
NEELKANTH ROYALE PALMS - F WING PHASE II
P51700012161
31 Dec 2026Not completed yetOngoing

Frequently asked questions

How do I verify NEELKANTH ASSOCIATES as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. Cross-check its GSTIN 27AAIFN2122N1Z5 on the MCA and GST portals before signing anything. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with NEELKANTH ASSOCIATES?

Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

The record above looks clean. What should I still check?

A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.

Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.