Home / Developers / Kumar Properties and Real Estate Pvt. Ltd.
Kumar Properties and Real Estate Pvt. Ltd.: RERA track record
Company ยท attribution by exact filing name, entity resolution in progress
Kumar Properties and Real Estate Pvt. Ltd. has 8 registrations in this build, including Park Infinia Phase III and Picasso Phase II. Its filings disclose 10 earlier MahaRERA projects: 9 of 10 past projects completed on time.
Projects in this build
| Project | Location | Units | Booked | Status |
|---|---|---|---|---|
| Park Infinia Phase III | Pune, Maharashtra | - | - | Completed |
| Picasso Phase II | Pune, Maharashtra | - | - | Completed |
| Park Infinia Phase IV | Pune, Maharashtra | - | - | Completed |
| Park Infinia - I1, I2, I3, J2, J3 and K1 | Pune, Maharashtra | - | - | Completed |
| PICASSO - O | Pune, Maharashtra | - | - | Completed |
| Park Infinia - L2, L3, L4, K4, K5 and J4 | Pune, Maharashtra | - | - | Completed |
| Park Infinia - L1, K3 and I4 | Pune, Maharashtra | 168 | 99% | Completed |
| Park Infinia - B1 and B2 | Pune, Maharashtra | 94 | 99% | Completed |
Past projects, as disclosed in RERA filings
| Project | Promised completion | Actual completion | Delivery |
|---|---|---|---|
| Kumar Picasso Phase I | 5 Dec 2010 | 25 Sep 2010 | On time |
| Park Infinia Phase I | 25 Jun 2011 | 7 Aug 2010 | On time |
| Park Infinia Phase II | 7 Jan 2014 | 7 Jul 2013 | On time |
| Kumar Picasso - E | 2 May 2017 | 16 Jun 2017 | +1 months |
| Park Infinia Phase III | 31 May 2019 | 31 Mar 2018 | On time |
| Picasso Phase II | 31 Dec 2019 | 29 Sep 2018 | On time |
| Park Infinia Phase IV | 21 Feb 2022 | 8 Dec 2020 | On time |
| Kumar Picasso - O | 25 Feb 2022 | 18 Jan 2021 | On time |
| Park Infinia - I1, I2, I3, J2, J3 and K1 | 30 Jun 2023 | 2 Jun 2022 | On time |
| Park Infinia - L2, L3, L4, K4, K5, J4 | 30 Sep 2024 | 15 Jan 2024 | On time |
Frequently asked questions
How do I verify Kumar Properties and Real Estate Pvt. Ltd. as a legal entity before signing?
Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.
How should I use this delivery record when booking with Kumar Properties and Real Estate Pvt. Ltd.?
Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.
The record above looks clean. What should I still check?
A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.
Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.