KRISHNA CONSTRUCTIONS: RERA track record
Partnership ยท attribution by exact filing name, entity resolution in progress
KRISHNA CONSTRUCTIONS has 6 registrations on MahaRERA, including KRISHNA ANANDAM 2 and LOTUS COURT. Its filings disclose 6 earlier MahaRERA projects: declares 5 of 5 past projects completed on time. Litigation is declared on 1 of its registrations.
Projects by this developer
Showing all 6 projects.
Largest first, by the unit count in the filing.
| Project | Location | Units | Booked | Registered | Status |
|---|---|---|---|---|---|
| KRISHNA LEELAP50500054024 | JAITALA, Nagpur, 440036 | 50 | 82% | 19 Dec 2023 | Registered |
| Lotus Court Phase -IIP52100047958 | Kharadi, Pune, 411014 | 16 | 50% | 2 Dec 2022 | Registered |
| KRISHNA ANANDAM 2P50500012118 | Pannase Layout, Nagpur, 440033 | - | - | 1 Sep 2017 | Completed |
| KRISHNA VILLAP51600046113 | Trimbakeshwar, Nashik, 422212 | - | - | 20 Jun 2022 | Completed |
| KRUSHNA HEIGHTSP52200031659 | SAVEDI, Ahmednagar, 414003 | - | - | 3 Nov 2021 | Completed |
| LOTUS COURTP52100008752 | Kharadi, 411014 | - | - | 19 Aug 2017 | Completed |
What this promoter declares as its own experience
KRISHNA CONSTRUCTIONS declares experience on 6 earlier projects. 2 of them carry a registration number we could match on MahaRERA, all under this promoter's own name.
2 of these declarations can be compared with the dates those projects' own registrations hold. On 1, the date given as the original completion date is the REVISED deadline that project carries after an extension rather than its original one. That changes the arithmetic on the one completion recorded here as on time: measured against the original deadline the register itself holds, that one was finished after it.
From the promoter experience table each promoter files with MahaRERA, matched to the register by registration number. A declaration naming another promoter's project is a claim of involvement, and involvement takes several shapes: a parent and its project company, one firm re-registering under a second name, or a joint venture between two separate developers. We publish the claim as filed and do not treat it as proof that the entities are one builder.
Past projects, as disclosed in RERA filings
| Project | Promised completion | Actual completion | Delivery |
|---|---|---|---|
| KRISHNA MADHUBAN | 30 Nov 2013 | 10 Oct 2013 | On time |
| KRISHNA ANANDAM | 30 Mar 2015 | 13 Feb 2015 | On time |
| KRISHNA HEIGHTS | 30 Oct 2016 | 22 Sep 2016 | On time |
| KRISHNA VATIKA | 15 Jul 2017 | 20 Apr 2017 | On time |
| LOTUS COURT P52100008752 | 30 Dec 2023 | 9 Nov 2023 | On time |
| Lotus Court Phase -II P52100047958 | 31 Dec 2024 | Not completed yet | Ongoing |
Frequently asked questions
How do I verify KRISHNA CONSTRUCTIONS as a legal entity before signing?
Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.
How should I use this delivery record when booking with KRISHNA CONSTRUCTIONS?
Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.
Does the declared litigation make KRISHNA CONSTRUCTIONS unsafe to buy from?
Not by itself. Litigation on a registration ranges from a boundary dispute to an allottee case about delay; what matters is the case type, which court or forum, and whether it touches the land title of the project you are buying. The case list is in each project's filed documents. Treat litigation as a question to resolve in writing before booking, not as a verdict either way.