JAGDALE INFRASTRUCTURE PVT. LTD.: RERA track record
CIN U45200MH2007PTC174171 · GSTIN 27AACCJ0653K1ZJ · Company · attribution by exact filing name, entity resolution in progress
JAGDALE INFRASTRUCTURE PVT. LTD. has 5 registrations on MahaRERA, including AMIZRA and JAGDALE AASTHA. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time.
Projects by this developer
Showing all 5 projects.
Largest first, by the unit count in the filing.
| Project | Location | Units | Booked | Registered | Status |
|---|---|---|---|---|---|
| Jagdale EdgeP51700078849 | THANE WEST, Thane, 400601 | 611 | 19% | 15 Jan 2025 | Registered |
| AVESAP51700030171 | Pokhran Road 2, Thane, 400601 | 278 | 36% | 5 Aug 2021 | Registered |
| JAGDALE AASTHAP51700026770 | Lokmanya Nagar 4, Thane, 400606 | 60 | 7% | 22 Oct 2020 | Registered |
| Jagdale GirirajP51800045510 | MULUND EAST, Mumbai Suburban, 400081 | 32 | 3% | 24 May 2022 | Registered |
| AMIZRAP51700006965 | Vartak Nagar, Thane, 400606 | - | - | 16 Aug 2017 | Completed |
What this promoter declares as its own experience
JAGDALE INFRASTRUCTURE PVT. LTD. declares experience on 1 earlier project. It carries no registration number we could match on MahaRERA, which is usual for work done before the register existed.
From the promoter experience table each promoter files with MahaRERA, matched to the register by registration number. A declaration naming another promoter's project is a claim of involvement, and involvement takes several shapes: a parent and its project company, one firm re-registering under a second name, or a joint venture between two separate developers. We publish the claim as filed and do not treat it as proof that the entities are one builder.
Past projects, as disclosed in RERA filings
| Project | Promised completion | Actual completion | Delivery |
|---|---|---|---|
| AMIZRA | 31 Dec 2018 | 27 Dec 2019 | +12 months |
Frequently asked questions
How do I verify JAGDALE INFRASTRUCTURE PVT. LTD. as a legal entity before signing?
Your agreement for sale must name the exact entity registered for the project, not a group brand. Cross-check its CIN U45200MH2007PTC174171 and GSTIN 27AACCJ0653K1ZJ on the MCA and GST portals before signing anything. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.
How should I use this delivery record when booking with JAGDALE INFRASTRUCTURE PVT. LTD.?
Add the median slip shown above to any possession date this promoter quotes you, and plan your rent, loan and school-year decisions around that stressed date. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.
The record above looks clean. What should I still check?
A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.
Spotted a project attributed to the wrong developer, or something else wrong on this page? Projects are grouped by the promoter name as filed, so a firm that registers under two spellings can split across two pages. Tell us and we will check it against the filings.
Report an errorShare feedbackData from official MahaRERA filings. How we handle corrections is on the about page.