Home / Developers / GREEN CITY BUILDERS
GREEN CITY BUILDERS: RERA track record
Partnership ยท attribution by exact filing name, entity resolution in progress
GREEN CITY BUILDERS has 5 registrations on MahaRERA, including AMANS GREEN PARK and AMAN SERENITY. Its filings disclose 5 earlier MahaRERA projects: declares 0 of 2 past projects completed on time.
Projects by this developer
Showing all 5 projects.
Largest first, by the unit count in the filing.
| Project | Location | Units | Booked | Registered | Status |
|---|---|---|---|---|---|
| AMANS MANNATP50500008476 | Nagpur (M Corp.), Nagpur, 440013 | 78 | 63% | 19 Aug 2017 | Registered |
| AMANS MANNAT-BLOCK C-1P50500048603 | Opposite Ayyappa Temple Ring Road, Nagpur, 440013 | 52 | 63% | 10 Jan 2023 | Registered |
| AMAN SERENITYP50500004146 | Nagpur (M Corp.), Nagpur, 440013 | - | - | 8 Aug 2017 | Registration lapsed |
| AMANS GREEN PARKP50500004139 | Nagpur (M Corp.), Nagpur, 440013 | - | - | 8 Aug 2017 | Registration lapsed |
| AMANS MANNAT-BLOCK C-2P50500029956 | Opposite Ayyappa Temple Ring Road, Nagpur, 440013 | - | - | 18 Jul 2021 | Registered |
What this promoter declares as its own experience
GREEN CITY BUILDERS declares experience on 5 earlier projects. 3 of them carry a registration number we could match on MahaRERA, all under this promoter's own name.
3 of these declarations can be compared with the dates those projects' own registrations hold. On 1, the date given as the original completion date is the REVISED deadline that project carries after an extension rather than its original one. It changes nothing about whether that project was delivered on time.
From the promoter experience table each promoter files with MahaRERA, matched to the register by registration number. A declaration naming another promoter's project is a claim of involvement, and involvement takes several shapes: a parent and its project company, one firm re-registering under a second name, or a joint venture between two separate developers. We publish the claim as filed and do not treat it as proof that the entities are one builder.
Past projects, as disclosed in RERA filings
| Project | Promised completion | Actual completion | Delivery |
|---|---|---|---|
| AMAN SIGNATURE | 20 Mar 2014 | 25 Jun 2014 | +3 months |
| AMAN IMPERIAL | 11 Feb 2015 | 19 May 2015 | +3 months |
| AMANS MANNAT P50500008476 | 31 Mar 2025 | Not completed yet | Certificate Signed |
| AMANS MANNAT-BLOCK C-2 P50500029956 | 21 Sep 2025 | Not completed yet | Certificate Signed |
| AMANS MANNAT-BLOCK C-1 P50500048603 | 31 Mar 2027 | Not completed yet | Ongoing |
Frequently asked questions
How do I verify GREEN CITY BUILDERS as a legal entity before signing?
Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.
How should I use this delivery record when booking with GREEN CITY BUILDERS?
Add the median slip shown above to any possession date this promoter quotes you, and plan your rent, loan and school-year decisions around that stressed date. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.
The record above looks clean. What should I still check?
A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.
Spotted a project attributed to the wrong developer, or something else wrong on this page? Projects are grouped by the promoter name as filed, so a firm that registers under two spellings can split across two pages. Tell us and we will check it against the filings.
Report an errorShare feedbackData from official MahaRERA filings. How we handle corrections is on the about page.