ReraGenieLog inGet a buyer report

Home / Developers / ELANTE PROPERTIES PRIVATE LIMITED

ELANTE PROPERTIES PRIVATE LIMITED: RERA track record

CIN U45309MH2022PTC375447 · GSTIN 27AAECL8967C1Z7 · Company · attribution by exact filing name, entity resolution in progress

ELANTE PROPERTIES PRIVATE LIMITED has 4 registrations in this build, including L and T Realty Evara Heights T1 and L and T Realty Evara Heights T2. Its filings disclose 9 earlier MahaRERA projects: 7 of 9 past projects completed on time. Litigation is declared on 4 of its registrations.

4Registrations in this build
9Past projects disclosed
on timeMedian delivery slip
4Registrations with litigation

Projects in this build

ProjectLocationUnits BookedStatus
L and T Realty Evara Heights T1Thane, Maharashtra43553%Registered
L and T Realty Evara Heights T2Thane, Maharashtra33443%Registered
L and T Realty Evara Heights T4Thane, Maharashtra7831%Registered
L and T Realty Evara Heights T5Thane, Maharashtra780%Registered

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
Crescent Bay - T1 - 40, 41 floors
31 Mar 201831 Mar 2018On time
Crescent Bay - T4
31 Mar 201819 Mar 2019+12 months
Crescent Bay - T5
31 Mar 201815 Mar 2018On time
Crescent Bay - T6
31 Jan 201930 Sep 2020+20 months
Crescent Bay - T2
31 Mar 201912 Mar 2019On time
Crescent Bay - T3
30 Mar 20231 Aug 2022On time
L and T Realty Evara Heights T4
30 Apr 203030 Apr 2030On time
L and T Realty Evara Heights T1
31 Aug 203031 Aug 2030On time
L and T Realty Evara Heights T2
31 Aug 203031 Aug 2030On time

Frequently asked questions

How do I verify ELANTE PROPERTIES PRIVATE LIMITED as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. Cross-check its CIN U45309MH2022PTC375447 and GSTIN 27AAECL8967C1Z7 on the MCA and GST portals before signing anything. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with ELANTE PROPERTIES PRIVATE LIMITED?

Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

Does the declared litigation make ELANTE PROPERTIES PRIVATE LIMITED unsafe to buy from?

Not by itself. Litigation on a registration ranges from a boundary dispute to an allottee case about delay; what matters is the case type, which court or forum, and whether it touches the land title of the project you are buying. The case list is in each project's filed documents. Treat litigation as a question to resolve in writing before booking, not as a verdict either way.

Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.