Home / Developers / DMK INFRASTRUCTURE PRIVATE LIMITED

DMK INFRASTRUCTURE PRIVATE LIMITED: RERA track record

CIN U74120MH2010PTC209246 · GSTIN 27AADCD6097Q1ZU · Company · attribution by exact filing name, entity resolution in progress

DMK INFRASTRUCTURE PRIVATE LIMITED has 2 registrations in this build, including STELLA A and STELLA B3. Its filings disclose 7 earlier MahaRERA projects: 1 of 2 past projects completed on time. Litigation is declared on 2 of its registrations.

2Registrations in this build
7Past projects disclosed
+18 monthsMedian delivery slip
2Registrations with litigation

Projects in this build

ProjectLocationUnits BookedStatus
STELLA APune, Maharashtra1090%Registered
STELLA B3Pune, Maharashtra1090%Registered

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
STELLA
P52100002747
24 Feb 201924 Feb 2019On time
CROWN C1
P52100020978
11 Oct 202211 Oct 2025+36 months
STELLA B1
P52100053511
1 Nov 2026Not completed yetOngoing
STELLA F1
P52100054567
9 Jan 2027Not completed yetOngoing
STELLA F3
P52100054729
31 Mar 2027Not completed yetOngoing
STELLA D3
P52100054604
9 May 2027Not completed yetOngoing
Stella B2
PR1260002500956
27 Mar 2028Not completed yetOngoing

Frequently asked questions

How do I verify DMK INFRASTRUCTURE PRIVATE LIMITED as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. Cross-check its CIN U74120MH2010PTC209246 and GSTIN 27AADCD6097Q1ZU on the MCA and GST portals before signing anything. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with DMK INFRASTRUCTURE PRIVATE LIMITED?

Add the median slip shown above to any possession date this promoter quotes you, and plan your rent, loan and school-year decisions around that stressed date. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

Does the declared litigation make DMK INFRASTRUCTURE PRIVATE LIMITED unsafe to buy from?

Not by itself. Litigation on a registration ranges from a boundary dispute to an allottee case about delay; what matters is the case type, which court or forum, and whether it touches the land title of the project you are buying. The case list is in each project's filed documents. Treat litigation as a question to resolve in writing before booking, not as a verdict either way.

Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.